by SHRADDHA LANDMARK PRIVATE LIMITED · Bhandup West, Mumbai 400078Also near Mulund West, Bhandup East

What’s in the report? →

Possession date of Shraddha Evoque (MahaRERA P51800008864): 30 August 2026, moved from 30 December 2023 (32 months later), and it has already passed. It has 639 homes (1 BHK and 2 BHK, 229–582 sq ft carpet), 93% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800008864. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800008864, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (August 2026) has passed.

What do you want to know about Shraddha Evoque?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shraddha Evoque has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800015282)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025628)

    Reason the builder gave MahaRERA:
    “The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working dili…” Read the full reason“The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We have received Occupancy Certificate for Building A, B, C & F & the remaining work is finished. Given the circumstances, we kindly request an extension until 30-12-2025 to complete the project and fulfil all regulatory requirements. We seek your understanding and approval of this request.”
  4. 30 August 2026

    Extended at the builder's request (MahaRERA application EA22042620696)

    Reason the builder gave MahaRERA:
    “The project is substantially completed, with all major construction activities finished. Only minor finishing works such as final touch-ups, common area detailing, testing/commissioning of services, and statutory compliances remain. The ext…” Read the full reason“The project is substantially completed, with all major construction activities finished. Only minor finishing works such as final touch-ups, common area detailing, testing/commissioning of services, and statutory compliances remain. The extension is sought solely to complete these residual works and to obtain the OC, ensuring full compliance with statutory requirements and delivering the project in a proper and compliant manner to allottees. The extension is requested to complete residual works and obtain the OC in compliance with statutory requirements. Given the circumstances, we kindly r…”

Source: Shraddha Evoque’s extension records on MahaRERA (P51800008864), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shraddha Evoque

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800008864
Status
Lapsed (registration period ended)
Builder
SHRADDHA LANDMARK PRIVATE LIMITED
Location
Bhandup West, Mumbai · 400078
Project type
Others
Registered on
19 Aug 2017
Completion date at registration
December 2023
Latest completion date
August 2026
Delay so far
32 months
Homes
639
Sold or booked
93%
Towers
8
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
20

Construction progress of Shraddha Evoque, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SALE TOWER 1 WING B100%100%100%100%
SALE TOWER 1 WING A100%100%100%100%
SALE TOWER 1 WING C100%100%100%100%
SALE TOWER 1 WING D100%100%100%100%
SALE TOWER 1 WING F100%100%100%100%
SALE TOWER 1 WING E100%100%100%100%
SALE TOWER 2100%100%100%100%
SALE TOWER 3100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • SALE TOWER 1 WING B: covers G + 22
  • SALE TOWER 1 WING A: covers G + 22
  • SALE TOWER 1 WING C: covers G + 22
  • SALE TOWER 1 WING D: covers G + 40
  • SALE TOWER 1 WING F: covers G + 22
  • SALE TOWER 1 WING E: covers 0 floors
  • SALE TOWER 2: covers 0 floors
  • SALE TOWER 3: covers 0 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shraddha Evoque every 1–2 months.

Shraddha Evoque: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Unspecified—594
1 BHK229 – 509444
2 BHK509 – 582195
Shops107 – 66435
  • Buildings: SALE TOWER 1 WING B (24 floors, 110 units) · SALE TOWER 1 WING A (24 floors, 73 units) · SALE TOWER 1 WING C (24 floors, 112 units) · SALE TOWER 1 WING D (42 floors, 274 units) · SALE TOWER 1 WING F (24 floors, 105 units) · SALE TOWER 1 WING E (24 floors) · SALE TOWER 2 (8 floors) · SALE TOWER 3 (8 floors)
  • Land: 10,442 sq m (about 2.6 acres) · sanctioned built-up 15,653 sq m · recreational space 1,042 sq m
  • Land, as filed: 112 PT, 112 / 2
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects.

Read Google reviews of Shraddha Evoque →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shraddha Evoque: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shraddha Evoque

What is the possession date of Shraddha Evoque?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shraddha Evoque in Bhandup West, Mumbai is 30 August 2026 — 32 months later than 30 December 2023, the date given at registration. That date has already passed.

The date has already moved 32 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shraddha Evoque?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shraddha Evoque's builder has filed on MahaRERA, the official one, is 30 August 2026, already 32 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shraddha Evoque extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 December 2025, giving the reason "The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We have received Occupancy Certificate for Building A, B, C & F & the remaining work is finished. Given the circumstances, we kindly request an extension until 30-12-2025 to complete the project and fulfil all regulatory requirements. We seek your understanding and approval of this request."; to 30 August 2026, giving the reason "The project is substantially completed, with all major construction activities finished. Only minor finishing works such as final touch-ups, common area detailing, testing/commissioning of services, and statutory compliances remain. The extension is sought solely to complete these residual works and to obtain the OC, ensuring full compliance with statutory requirements and delivering the project in a proper and compliant manner to allottees. The extension is requested to complete residual works and obtain the OC in compliance with statutory requirements. Given the circumstances, we kindly r…".

What is the RERA number of Shraddha Evoque?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shraddha Evoque in Bhandup West, Mumbai is P51800008864.

Is Shraddha Evoque registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque is registered as P51800008864 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shraddha Evoque? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does Shraddha Evoque have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shraddha Evoque safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque is registered on MahaRERA as P51800008864, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 32 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shraddha Evoque?

Shraddha Evoque isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shraddha Evoque are 229 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shraddha Evoque?

For a flat in Shraddha Evoque (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shraddha Evoque received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 August 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shraddha Evoque?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 August 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Shraddha Evoque a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque is a redevelopment: 62 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Shraddha Evoque uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shraddha Evoque was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shraddha Evoque's possession date changes?

The latest dates are on Shraddha Evoque's MahaRERA page (P51800008864). GharKundli's Kundli Watch sends a free WhatsApp update on Shraddha Evoque every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shraddha Evoque have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque has 8 buildings filed: SALE TOWER 1 WING B with 24 floors and 110 units; SALE TOWER 1 WING A with 24 floors and 73 units; SALE TOWER 1 WING C with 24 floors and 112 units; SALE TOWER 1 WING D with 42 floors and 274 units; SALE TOWER 1 WING F with 24 floors and 105 units; SALE TOWER 1 WING E with 24 floors; and 2 more.

What are the flat sizes (carpet area) in Shraddha Evoque?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shraddha Evoque: 1 BHK: 229 to 509 sq ft carpet (444 homes); 2 BHK: 509 to 582 sq ft carpet (195 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Shraddha Evoque?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque stands on 10,442 sq m of land (about 2.6 acres), with 15,653 sq m of sanctioned built-up area and 1,042 sq m of recreational open space.

What is the track record of Shraddha Evoque's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shraddha Evoque?

Google Maps has reviews of Shraddha Evoque written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shraddha Evoque?

Shraddha Evoque by SHRADDHA LANDMARK PRIVATE LIMITED is in Bhandup West, Mumbai, pincode 400078 (near Mulund West, Bhandup East), Maharashtra, and is registered on MahaRERA as P51800008864, per GharKundli's check of MahaRERA records. Its land is filed as 112 PT, 112 / 2. GharKundli lists all 176 MahaRERA projects in Bhandup West (400078).

How many flats are in Shraddha Evoque, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque has 639 homes in 8 towers registered on MahaRERA, and 93% of them are sold or booked.

When was Shraddha Evoque registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Evoque was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Does Shraddha Evoque have any legal issues or court cases?

No court cases are listed for Shraddha Evoque on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shraddha Evoque?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRADDHA LANDMARK PRIVATE LIMITED, which has 20 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Bhandup West (400078)

All 176 projects in Bhandup West (400078) →

Other projects by SHRADDHA LANDMARK PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.