by Sugee Developers Private Limited · Mulund West, MumbaiAlso near Mulund East, Bhandup west, Ghatkopar East

Possession date of Sugee Vaayu: 30 April 2032, moved from 31 December 2029 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800053945, and currently active. Its completion date has moved from December 2029 to April 2032: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Sugee Vaayu?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sugee Vaayu has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 31 December 2031

    Extended at the builder's request (MahaRERA application EA21022619941)

    Reason the builder gave MahaRERA:
    “The Promoter submits that the construction timeline of the project has been affected due to changes in the sanctioned plan involving revision in F.S.I. utilization and addition of upper floors. The correction is already approved by the RERA…” Read the full reason“The Promoter submits that the construction timeline of the project has been affected due to changes in the sanctioned plan involving revision in F.S.I. utilization and addition of upper floors. The correction is already approved by the RERA Authority.”
  3. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sugee Vaayu’s extension records on MahaRERA (P51800053945), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sugee Vaayu

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800053945
Status
Registered and active
Builder
Sugee Developers Private Limited
Location
Mulund West, Mumbai · 400078
Project type
Others
Registered on
11 Dec 2023
Completion date at registration
December 2029
Latest completion date
April 2032
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
540
Sold or booked
0%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Sugee Vaayu, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower A0%0%0%0%
Tower B0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Tower A: covers Top of basement level
  • Tower B: covers Top of basement level

Latest CC order on MahaRERA: dated 25/03/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sugee Vaayu every month.

Sugee Vaayu: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK573 – 645293
1 BHK460 – 643247
Shops241 – 4625
3 BHK5761
  • Buildings: Tower A (56 floors, 388 units) · Tower B (31 floors, 158 units)
  • Car parking: 710 covered
  • Land: 10,071 sq m (about 2.5 acres) · sanctioned built-up 30,763 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Sugee Developers (a group of 14 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 9 months); 11 still being built, none past the promised date yet; 4 lapsed. 5 complaints on MahaRERA across 4 projects.

Read Google reviews of Sugee Vaayu →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sugee Vaayu: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sugee Vaayu

What is the possession date of Sugee Vaayu?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sugee Vaayu in Mulund West, Mumbai is 30 April 2032 — 24 months later than 31 December 2029, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sugee Vaayu?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sugee Vaayu's builder has filed on MahaRERA, the official one, is 30 April 2032, already 24 months later than the 31 December 2029 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sugee Vaayu extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Vaayu's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "The Promoter submits that the construction timeline of the project has been affected due to changes in the sanctioned plan involving revision in F.S.I. utilization and addition of upper floors. The correction is already approved by the RERA Authority.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Sugee Vaayu?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sugee Vaayu in Mulund West, Mumbai is P51800053945.

Is Sugee Vaayu registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Vaayu is registered as P51800053945 and its status is "Registered and active".

What is the construction status of Sugee Vaayu?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Vaayu's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sugee Vaayu have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sugee Vaayu safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Vaayu is registered on MahaRERA as P51800053945, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sugee Vaayu's possession date changes?

The latest dates are on Sugee Vaayu's MahaRERA page (P51800053945). GharKundli's Kundli Watch sends a free WhatsApp update on Sugee Vaayu every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sugee Vaayu have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Vaayu has 2 buildings filed: Tower A with 56 floors and 388 units; Tower B with 31 floors and 158 units.

What are the flat sizes (carpet area) in Sugee Vaayu?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sugee Vaayu: 2 BHK: 573 to 645 sq ft carpet (293 homes); 1 BHK: 460 to 643 sq ft carpet (247 homes); 3 BHK: 576 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Sugee Vaayu have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 710 covered car parking spaces for Sugee Vaayu.

How big is the land of Sugee Vaayu?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Vaayu stands on 10,071 sq m of land (about 2.5 acres), with 30,763 sq m of sanctioned built-up area.

What is the track record of Sugee Vaayu's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Developers (a group of 14 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 9 months); 11 still being built, none past the promised date yet; 4 lapsed. 5 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sugee Vaayu?

Google Maps has reviews of Sugee Vaayu written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sugee Vaayu?

Sugee Vaayu by Sugee Developers Private Limited is in Mulund West, Mumbai (pincode 400078), near Mulund East, Bhandup west, Ghatkopar East, Maharashtra, and is registered on MahaRERA as P51800053945, per GharKundli's check of MahaRERA records.

How many homes are in Sugee Vaayu?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Vaayu has 540 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was Sugee Vaayu registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Vaayu was registered on MahaRERA on 11 December 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Sugee Vaayu?

No court cases are listed for Sugee Vaayu on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Sugee Vaayu?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sugee Developers Private Limited, which has 2 other projects registered on MahaRERA.

Other projects in Kurla

All 176 projects in Bhandup West (400078) →

Other projects by Sugee Developers Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.