Godrej Nurture - Tower 2
by Godrej Properties Limited (Mahalunge) · Bhandup, MumbaiAlso near Mulund West
Possession date of Godrej Nurture - Tower 2: 31 March 2032, moved from 31 March 2031 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800077080, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Godrej Nurture - Tower 2?
How the possession date of Godrej Nurture - Tower 2 has moved
31 March 2031
Completion date given when the project was registered
31 March 2032
Extended at the builder's request (MahaRERA application EA03082622005)
Reason the builder gave MahaRERA:
“The Project is approximately 30% completed. Tab 1 - Form B uploaded Tab 2 - Declaration for Extension uploaded Tab 3 - PERT Chart uploaded Tab 4 - Notarised Declaration Tab 5 - Comparative Statement Tab 6 - Commencement certificate the Proj…” Read the full reason
“The Project is approximately 30% completed. Tab 1 - Form B uploaded Tab 2 - Declaration for Extension uploaded Tab 3 - PERT Chart uploaded Tab 4 - Notarised Declaration Tab 5 - Comparative Statement Tab 6 - Commencement certificate the Project is registered POST COVID, the lingering effects of the after effects of the pandemic, including reduced labour availability, supply chain disruptions, and lower site productivity, continued to impact the execution schedule also Due to the prevailing war situation and its consequential impact on the supply chain, there has been a severe shortage of con…”
Source: Godrej Nurture - Tower 2’s extension records on MahaRERA (P51800077080), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Godrej Nurture - Tower 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Godrej Nurture - Tower 3P51800077085 · possession 31 Jul 2032
- MahaRERA registration
- P51800077080
- Status
- Registered and active
- Builder
- Godrej Properties Limited
- Location
- Bhandup, Mumbai · 400078
- Project type
- Residential / Group Housing
- Registered on
- 23 Jul 2024
- Completion date at registration
- March 2031
- Latest completion date
- March 2032
- Delay so far
- 12 months
- Homes
- 303
- Sold or booked
- 40%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 27
Construction progress of Godrej Nurture - Tower 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Godrej Nurture- Tower 2 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Godrej Nurture- Tower 2: covers 10 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Godrej Nurture - Tower 2 every month.
Godrej Nurture - Tower 2: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 654 – 682 | 154 |
| 3 BHK | 658 – 1,105 | 149 |
- Buildings: Godrej Nurture- Tower 2 (45 floors, 303 units)
- Land: 1,145 sq m (about 0.3 acres) · sanctioned built-up 25,943 sq m · recreational space 5,437 sq m
The builder’s record and reviews
Godrej Properties (a group of 18 linked companies) has 99 projects on MahaRERA since 2017, this one included. Of the 94 GharKundli has checked: 22 finished, 17 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late); 1 lapsed. 567 complaints on MahaRERA across 61 projects.
Read Google reviews of Godrej Nurture - Tower 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Godrej Nurture - Tower 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Godrej Nurture - Tower 2
What is the possession date of Godrej Nurture - Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Godrej Nurture - Tower 2 in Bhandup, Mumbai is 31 March 2032 — 12 months later than 31 March 2031, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Godrej Nurture - Tower 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Godrej Nurture - Tower 2's builder has filed on MahaRERA, the official one, is 31 March 2032, already 12 months later than the 31 March 2031 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Godrej Nurture - Tower 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Nurture - Tower 2's builder applied to MahaRERA to extend the completion date once: to 31 March 2032, giving the reason "The Project is approximately 30% completed. Tab 1 - Form B uploaded Tab 2 - Declaration for Extension uploaded Tab 3 - PERT Chart uploaded Tab 4 - Notarised Declaration Tab 5 - Comparative Statement Tab 6 - Commencement certificate the Project is registered POST COVID, the lingering effects of the after effects of the pandemic, including reduced labour availability, supply chain disruptions, and lower site productivity, continued to impact the execution schedule also Due to the prevailing war situation and its consequential impact on the supply chain, there has been a severe shortage of con…".
What is the RERA number of Godrej Nurture - Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Godrej Nurture - Tower 2 in Bhandup, Mumbai is P51800077080.
Is Godrej Nurture - Tower 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Nurture - Tower 2 is registered as P51800077080 and its status is "Registered and active".
What is the construction status of Godrej Nurture - Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Nurture - Tower 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Godrej Nurture- Tower 2 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Godrej Nurture - Tower 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Godrej Nurture - Tower 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Nurture - Tower 2 is registered on MahaRERA as P51800077080, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Godrej Nurture - Tower 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Godrej Nurture - Tower 3 (P51800077085, possession 31 Jul 2032). Check that your agreement names the registration of your own wing.
How can I get updates if Godrej Nurture - Tower 2's possession date changes?
The latest dates are on Godrej Nurture - Tower 2's MahaRERA page (P51800077080). GharKundli's Kundli Watch sends a free WhatsApp update on Godrej Nurture - Tower 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Godrej Nurture - Tower 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Nurture - Tower 2 has one building filed: Godrej Nurture- Tower 2 with 45 floors and 303 units.
What are the flat sizes (carpet area) in Godrej Nurture - Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Godrej Nurture - Tower 2: 2 BHK: 654 to 682 sq ft carpet (154 homes); 3 BHK: 658 to 1105 sq ft carpet (149 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Godrej Nurture - Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Nurture - Tower 2 stands on 1,145 sq m of land (about 0.3 acres), with 25,943 sq m of sanctioned built-up area and 5,437 sq m of recreational open space.
What is the track record of Godrej Nurture - Tower 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Properties (a group of 18 linked companies) has 99 projects on MahaRERA since 2017, this one included. Of the 94 GharKundli has checked: 22 finished, 17 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late); 1 lapsed. 567 complaints on MahaRERA across 61 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Godrej Nurture - Tower 2?
Google Maps has reviews of Godrej Nurture - Tower 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Godrej Nurture - Tower 2?
Godrej Nurture - Tower 2 by Godrej Properties Limited (Mahalunge) is in Bhandup, Mumbai (pincode 400078), near Mulund West, Maharashtra, and is registered on MahaRERA as P51800077080, per GharKundli's check of MahaRERA records.
How many homes are in Godrej Nurture - Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Nurture - Tower 2 has 303 homes in 1 tower registered on MahaRERA, and 40% of them are sold or booked.
When was Godrej Nurture - Tower 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Nurture - Tower 2 was registered on MahaRERA on 23 July 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Godrej Nurture - Tower 2?
No court cases are listed for Godrej Nurture - Tower 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Godrej Nurture - Tower 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Godrej Properties Limited, the company Mahalunge files this project under, which has 27 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Godrej Nurture - Tower 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400078
- Runwal Forests Tower 9 - 11
- Horizon
- Valentina CHS
- Sugee Vaayu
- Vanita Sadan CHS
- Godrej Nurture - Tower 3
- BHOOMI GREEN HILL
- Pandora by Shraddha
Other projects by Godrej Properties Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.