What’s in the report? →Possession date of Godrej Skyshore (MahaRERA PM1180002500076): 30 April 2032. It has 126 homes (3 BHK, 4 BHK and Duplex, 1573–3566 sq ft carpet), 51% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1180002500076, and currently active. Its completion date is now April 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PM1180002500076, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Godrej Skyshore?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Godrej Skyshore has moved
31 December 2031
Completion date given when the project was registered
30 April 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Godrej Skyshore’s extension records on MahaRERA (PM1180002500076), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Godrej Skyshore
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1180002500076
- Status
- Registered and active
- Builder
- Godrej Properties Limited
- Location
- Versova, Mumbai · 400061
- Project type
- Mixed
- Registered on
- 16 Jun 2025
- Completion date at registration
- December 2031
- Latest completion date
- April 2032
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 126
- Sold or booked
- 51%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 27
Construction progress of Godrej Skyshore, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower A | 0% | 0% | 0% | 0% |
| Tower B | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Tower A: covers Plinth level
- Tower B: covers Plinth Level
Latest CC order on MahaRERA: dated 25/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Godrej Skyshore every 1–2 months.
Godrej Skyshore: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 4 BHK | 2,154 – 2,646 | 76 |
| 3 BHK | 1,573 – 1,578 | 44 |
| Shops | 716 – 7,233 | 12 |
| Duplex | 3,565 – 3,566 | 6 |
- Buildings: Tower A (31 floors, 68 units) · Tower B (31 floors, 70 units)
- Car parking: 401 covered
- Land: 8,048 sq m (about 2.0 acres) · sanctioned built-up 31,016 sq m · recreational space 560 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Godrej Properties (a group of 18 linked companies) has 99 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 23 finished, 18 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late); 2 lapsed. 571 complaints on MahaRERA across 62 projects.
Read Google reviews of Godrej Skyshore →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Godrej Skyshore: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Godrej Skyshore
What is the possession date of Godrej Skyshore?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Godrej Skyshore in Versova, Mumbai is 30 April 2032, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Godrej Skyshore?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Godrej Skyshore's builder has filed on MahaRERA, the official one, is 30 April 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Godrej Skyshore?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Godrej Skyshore in Versova, Mumbai is PM1180002500076.
Is Godrej Skyshore registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Skyshore is registered as PM1180002500076 and its status is "Registered and active".
What is the current construction status of Godrej Skyshore? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Skyshore's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Godrej Skyshore have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Godrej Skyshore safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Skyshore is registered on MahaRERA as PM1180002500076, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Godrej Skyshore?
Godrej Skyshore is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Godrej Skyshore start at 1573 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Godrej Skyshore?
For a flat in Godrej Skyshore (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Godrej Skyshore received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Skyshore is still under construction, with 30 April 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Godrej Skyshore uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Godrej Skyshore was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Godrej Skyshore's possession date changes?
The latest dates are on Godrej Skyshore's MahaRERA page (PM1180002500076). GharKundli's Kundli Watch sends a free WhatsApp update on Godrej Skyshore every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Godrej Skyshore have?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Skyshore has 2 buildings filed: Tower A with 31 floors and 68 units; Tower B with 31 floors and 70 units.
What are the flat sizes (carpet area) in Godrej Skyshore?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Godrej Skyshore: 4 BHK: 2154 to 2646 sq ft carpet (76 homes); 3 BHK: 1573 to 1578 sq ft carpet (44 homes); Duplex: 3565 to 3566 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Godrej Skyshore have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 401 covered car parking spaces for Godrej Skyshore.
How big is the land of Godrej Skyshore?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Skyshore stands on 8,048 sq m of land (about 2.0 acres), with 31,016 sq m of sanctioned built-up area and 560 sq m of recreational open space.
What is the track record of Godrej Skyshore's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Properties (a group of 18 linked companies) has 99 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 23 finished, 18 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late); 2 lapsed. 571 complaints on MahaRERA across 62 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Godrej Skyshore?
Google Maps has reviews of Godrej Skyshore written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Godrej Skyshore?
Godrej Skyshore by Godrej Properties Limited (Mahalunge) is in Versova, Mumbai, pincode 400061, Maharashtra, and is registered on MahaRERA as PM1180002500076, per GharKundli's check of MahaRERA records. GharKundli lists all 21 MahaRERA projects in Vesava (400061).
How many flats are in Godrej Skyshore, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Skyshore has 126 homes in 2 towers registered on MahaRERA, and 51% of them are sold or booked.
When was Godrej Skyshore registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Skyshore was registered on MahaRERA on 16 June 2025. GharKundli did not find a title report on the land on file there.
Does Godrej Skyshore have any legal issues or court cases?
No court cases are listed for Godrej Skyshore on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Godrej Skyshore?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Godrej Properties Limited, the company Mahalunge files this project under, which has 27 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Godrej Skyshore
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Vesava (400061)
All 21 projects in Vesava (400061) →Other projects by Godrej Properties Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.