by Acme Housing India Private Limited · Village Chitalsar, Manpada, ThaneAlso near Hiranandani Meadows, Majiwade, Chakala, Andheri East

Possession date of Herbelia: 30 December 2023, moved from 30 December 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700001038. Status: Lapsed (registration period ended). 25 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about Herbelia?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Herbelia

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 25 complaints and 6 court cases, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700001038
Status
Lapsed (registration period ended)
Builder
Acme Housing India Private Limited
Location
Village Chitalsar, Manpada, Thane · 400607
Project type
Residential / Group Housing
Registered on
25 Jul 2017
Completion date at registration
December 2022
Latest completion date
December 2023
Delay so far
12 months
Homes
184
Towers
1
Complaints on MahaRERA
25
Court cases listed
6
Appeals at the tribunal
4
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of Herbelia, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Herbelia100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Herbelia every month.

Herbelia: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Acme Housing has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 6 finished, 4 within the promised date and 2 needed more time (typically 16 months); 1 still being built, none past the promised date yet; 1 lapsed. 59 complaints on MahaRERA across 6 projects.

Read Google reviews of Herbelia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Herbelia: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Herbelia

What is the possession date of Herbelia?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Herbelia in Village Chitalsar, Manpada, Thane is 30 December 2023 — 12 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Herbelia?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Herbelia's builder has filed on MahaRERA, the official one, is 30 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Herbelia?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Herbelia in Village Chitalsar, Manpada, Thane is P51700001038.

Is Herbelia registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Herbelia is registered as P51700001038 and its status is "Lapsed (registration period ended)".

What is the construction status of Herbelia?

According to GharKundli's check of MahaRERA records (updated November 2026), Herbelia's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Herbelia is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Herbelia have complaints on MahaRERA?

25 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Herbelia safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Herbelia is registered on MahaRERA as P51700001038, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 25 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Herbelia's possession date changes?

The latest dates are on Herbelia's MahaRERA page (P51700001038). GharKundli's Kundli Watch sends a free WhatsApp update on Herbelia every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Herbelia have?

According to GharKundli's check of MahaRERA records (updated November 2026), Herbelia has one building filed: Herbelia with 28 floors.

How big is the land of Herbelia?

According to GharKundli's check of MahaRERA records (updated November 2026), Herbelia stands on 630 sq m of land (about 0.2 acres), with 13,241 sq m of sanctioned built-up area.

What is the track record of Herbelia's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Acme Housing has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 6 finished, 4 within the promised date and 2 needed more time (typically 16 months); 1 still being built, none past the promised date yet; 1 lapsed. 59 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Herbelia?

Google Maps has reviews of Herbelia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 25 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Herbelia?

Herbelia by Acme Housing India Private Limited is in Village Chitalsar, Manpada, Thane (pincode 400607), near Hiranandani Meadows, Majiwade, Chakala, Andheri East, Maharashtra, and is registered on MahaRERA as P51700001038, per GharKundli's check of MahaRERA records.

How many homes are in Herbelia?

According to GharKundli's check of MahaRERA records (updated November 2026), Herbelia has 184 homes in 1 tower registered on MahaRERA.

When was Herbelia registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Herbelia was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Herbelia?

6 court cases are listed for Herbelia on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Herbelia?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Acme Housing India Private Limited, which has 7 other projects registered on MahaRERA.

All projects in Sandozbaugh (400607) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.