PEHLA GHAR - SHIVA COMPLEX

by LAABH BUILDERS and DEVELOPERS · Bhiwandi, ThaneAlso near Vidyashram

Possession date of PEHLA GHAR - SHIVA COMPLEX: 30 December 2025. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700005607. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about PEHLA GHAR - SHIVA COMPLEX?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on PEHLA GHAR - SHIVA COMPLEX

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700005607
Status
Lapsed (registration period ended)
Builder
LAABH BUILDERS and DEVELOPERS
Location
Bhiwandi, Thane · 421308
Project type
Others
Registered on
11 Aug 2017
Completion date at registration
December 2025
Latest completion date
December 2025
Homes
160
Sold or booked
40%
Towers
3
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of PEHLA GHAR - SHIVA COMPLEX, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING C100%100%100%90%
WING B0%0%0%0%
WING A0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • WING C: covers GROUND + 7TH FLOORS
  • WING B: covers GROUND + 7TH FLOORS
  • WING A: covers GROUND + 7TH FLOORS

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PEHLA GHAR - SHIVA COMPLEX every month.

PEHLA GHAR - SHIVA COMPLEX: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING C (9 floors, 56 units) · WING B (9 floors, 42 units) · WING A (9 floors, 62 units)
  • Land: 2,650 sq m (about 0.7 acres) · sanctioned built-up 2,099 sq m · recreational space 370 sq m

The builder’s record and reviews

Laabh Builders And Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late); 2 lapsed. 7 complaints on MahaRERA across 3 projects.

Read Google reviews of PEHLA GHAR - SHIVA COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PEHLA GHAR - SHIVA COMPLEX: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PEHLA GHAR - SHIVA COMPLEX

What is the possession date of PEHLA GHAR - SHIVA COMPLEX?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PEHLA GHAR - SHIVA COMPLEX in Bhiwandi, Thane is 30 December 2025. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PEHLA GHAR - SHIVA COMPLEX?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PEHLA GHAR - SHIVA COMPLEX's builder has filed on MahaRERA, the official one, is 30 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of PEHLA GHAR - SHIVA COMPLEX?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PEHLA GHAR - SHIVA COMPLEX in Bhiwandi, Thane is P51700005607.

Is PEHLA GHAR - SHIVA COMPLEX registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PEHLA GHAR - SHIVA COMPLEX is registered as P51700005607 and its status is "Lapsed (registration period ended)".

What is the construction status of PEHLA GHAR - SHIVA COMPLEX?

According to GharKundli's check of MahaRERA records (updated November 2026), PEHLA GHAR - SHIVA COMPLEX's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does PEHLA GHAR - SHIVA COMPLEX have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PEHLA GHAR - SHIVA COMPLEX safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PEHLA GHAR - SHIVA COMPLEX is registered on MahaRERA as P51700005607, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PEHLA GHAR - SHIVA COMPLEX's possession date changes?

The latest dates are on PEHLA GHAR - SHIVA COMPLEX's MahaRERA page (P51700005607). GharKundli's Kundli Watch sends a free WhatsApp update on PEHLA GHAR - SHIVA COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PEHLA GHAR - SHIVA COMPLEX have?

According to GharKundli's check of MahaRERA records (updated November 2026), PEHLA GHAR - SHIVA COMPLEX has 3 buildings filed: WING C with 9 floors and 56 units; WING B with 9 floors and 42 units; WING A with 9 floors and 62 units.

How big is the land of PEHLA GHAR - SHIVA COMPLEX?

According to GharKundli's check of MahaRERA records (updated November 2026), PEHLA GHAR - SHIVA COMPLEX stands on 2,650 sq m of land (about 0.7 acres), with 2,099 sq m of sanctioned built-up area and 370 sq m of recreational open space.

What is the track record of PEHLA GHAR - SHIVA COMPLEX's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Laabh Builders And Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late); 2 lapsed. 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of PEHLA GHAR - SHIVA COMPLEX?

Google Maps has reviews of PEHLA GHAR - SHIVA COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PEHLA GHAR - SHIVA COMPLEX?

PEHLA GHAR - SHIVA COMPLEX by LAABH BUILDERS and DEVELOPERS is in Bhiwandi, Thane (pincode 421308), near Vidyashram, Maharashtra, and is registered on MahaRERA as P51700005607, per GharKundli's check of MahaRERA records.

How many homes are in PEHLA GHAR - SHIVA COMPLEX?

According to GharKundli's check of MahaRERA records (updated November 2026), PEHLA GHAR - SHIVA COMPLEX has 160 homes in 3 towers registered on MahaRERA, and 40% of them are sold or booked.

When was PEHLA GHAR - SHIVA COMPLEX registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PEHLA GHAR - SHIVA COMPLEX was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PEHLA GHAR - SHIVA COMPLEX?

No court cases are listed for PEHLA GHAR - SHIVA COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PEHLA GHAR - SHIVA COMPLEX?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is LAABH BUILDERS and DEVELOPERS.