Neha Heena Presidency
by Neha Developers · Mira Road, Thane 401107Also near Pleasant Park, Kashimira, Village GhodbunderRegistered on MahaRERA as “Heena Presidency”
What’s in the report? →Possession date of Neha Heena Presidency (MahaRERA P51800001920): 31 December 2026, moved from 30 December 2024 (24 months later). It has 137 homes, 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800001920, and currently active.
Source: MahaRERA website — records for P51800001920, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Neha Heena Presidency?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Neha Heena Presidency has moved
30 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025454)
Reason the builder gave MahaRERA:
“. Grounds for Delay: • Anticipated Occupancy Certificate Timeline: Initially, we were confident that we would receive our Occupancy Certificate from the Planning Authority (MBMC) by December 30, 2024. This timeline was set based on the stan…” Read the full reason
“. Grounds for Delay: • Anticipated Occupancy Certificate Timeline: Initially, we were confident that we would receive our Occupancy Certificate from the Planning Authority (MBMC) by December 30, 2024. This timeline was set based on the standard processing period and our project schedule. • Impact of State Assembly Elections in Maharashtra: The recent Assembly elections in Maharashtra contributed significantly to delays in administrative processes and approvals. During the election period, government offices and planning authorities often experience operational slowdowns due to resource real…”31 December 2026
Extended at the builder's request (MahaRERA application EA20112518384)
Reason the builder gave MahaRERA:
“I, Mr. Pradip Shah, hereby declare the following with respect to the project “Heena Presidency” bearing registration number P51800001920 registered under MahaRERA 1. Grounds for Delay: • Anticipated Occupancy Certificate Timeline: Initially…” Read the full reason
“I, Mr. Pradip Shah, hereby declare the following with respect to the project “Heena Presidency” bearing registration number P51800001920 registered under MahaRERA 1. Grounds for Delay: • Anticipated Occupancy Certificate Timeline: Initially, we were confident that we would receive our Occupancy Certificate from the Planning Authority (MBMC) by December 30, 2025. This timeline was set based on the standard processing period and our project schedule. • Delay from Planning Authority (MBMC): In addition, there have been unforeseen delays in the issuance of the Occupancy Certificate by the MBMC,…”
Source: Neha Heena Presidency’s extension records on MahaRERA (P51800001920), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Neha Heena Presidency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800001920
- Status
- Registered and active
- Builder
- Neha Developers
- Location
- Mira Road, Thane · 401107
- Project type
- Residential / Group Housing
- Registered on
- 29 Jul 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 137
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Neha Heena Presidency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Heena Presidency | 100% | 100% | 100% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- Heena Presidency: covers 24 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Neha Heena Presidency every 1–2 months.
Neha Heena Presidency: buildings, flats and land, as filed on MahaRERA
- Buildings: Heena Presidency (24 floors, 143 units)
- Car parking: 92 covered
- Land: 1,372 sq m (about 0.3 acres) · sanctioned built-up 3,350 sq m
- Land, as filed: 72/2, 73/1,2,3,4, 74/1,2, 75/1, 79/1,3,4
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Neha Heena Presidency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Neha Heena Presidency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Neha Heena Presidency
What is the possession date of Neha Heena Presidency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neha Heena Presidency in Mira Road, Thane is 31 December 2026 — 24 months later than 30 December 2024, the date given at registration.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Neha Heena Presidency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Neha Heena Presidency's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Neha Heena Presidency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason ". Grounds for Delay: • Anticipated Occupancy Certificate Timeline: Initially, we were confident that we would receive our Occupancy Certificate from the Planning Authority (MBMC) by December 30, 2024. This timeline was set based on the standard processing period and our project schedule. • Impact of State Assembly Elections in Maharashtra: The recent Assembly elections in Maharashtra contributed significantly to delays in administrative processes and approvals. During the election period, government offices and planning authorities often experience operational slowdowns due to resource real…"; to 31 December 2026, giving the reason "I, Mr. Pradip Shah, hereby declare the following with respect to the project “Heena Presidency” bearing registration number P51800001920 registered under MahaRERA 1. Grounds for Delay: • Anticipated Occupancy Certificate Timeline: Initially, we were confident that we would receive our Occupancy Certificate from the Planning Authority (MBMC) by December 30, 2025. This timeline was set based on the standard processing period and our project schedule. • Delay from Planning Authority (MBMC): In addition, there have been unforeseen delays in the issuance of the Occupancy Certificate by the MBMC,…".
What is the RERA number of Neha Heena Presidency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Neha Heena Presidency in Mira Road, Thane is P51800001920.
Is Neha Heena Presidency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency is registered as P51800001920 and its status is "Registered and active".
What is the current construction status of Neha Heena Presidency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Heena Presidency is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Neha Heena Presidency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Neha Heena Presidency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency is registered on MahaRERA as P51800001920, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Neha Heena Presidency?
Neha Heena Presidency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Neha Heena Presidency?
For a flat in Neha Heena Presidency (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Neha Heena Presidency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Neha Heena Presidency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Neha Heena Presidency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Neha Heena Presidency's possession date changes?
The latest dates are on Neha Heena Presidency's MahaRERA page (P51800001920). GharKundli's Kundli Watch sends a free WhatsApp update on Neha Heena Presidency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Neha Heena Presidency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency has one building filed: Heena Presidency with 24 floors and 143 units.
How much parking does Neha Heena Presidency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 92 covered car parking spaces for Neha Heena Presidency.
How big is the land of Neha Heena Presidency?
According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency stands on 1,372 sq m of land (about 0.3 acres), with 3,350 sq m of sanctioned built-up area.
What are the reviews of Neha Heena Presidency?
Google Maps has reviews of Neha Heena Presidency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Neha Heena Presidency?
Neha Heena Presidency by Neha Developers is in Mira Road, Thane, pincode 401107 (near Pleasant Park, Kashimira, Village Ghodbunder), Maharashtra, and is registered on MahaRERA as P51800001920, per GharKundli's check of MahaRERA records. Its land is filed as 72/2, 73/1,2,3,4, 74/1,2, 75/1, 79/1,3,4. GharKundli lists all 323 MahaRERA projects in Mira Road East (401107).
How many flats are in Neha Heena Presidency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency has 137 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Neha Heena Presidency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neha Heena Presidency was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.
Does Neha Heena Presidency have any legal issues or court cases?
1 court case is listed for Neha Heena Presidency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Neha Heena Presidency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Neha Developers.
Check it yourself on MahaRERA
- How to check the possession date of Neha Heena Presidency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Mira Road East (401107)
- Lotus
- Umiya Oasis
- Shanti Signature by Ashit Shah
- Sheetal Utsav
- JP Connect-miraroad
- Chandresh Terrace
- Urban Reserve Wing B
- Palm Lands
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.