Possession date of Sumit Star Exclusif (MahaRERA P51700008468): 30 June 2027, moved from 30 December 2021 (66 months later). It has 78 homes, 46% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700008468, and currently active.

Source: MahaRERA website — records for P51700008468, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Sumit Star Exclusif?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sumit Star Exclusif has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EXT51700027901)

    Reason the builder gave MahaRERA:
    “We are seeking extension vide Agreement dated 13.10.2022 the Owners of the property viz "Span Trident" Tower C situated at plot bearing Old Survey No. 663, New Survey No. 237, Revenue Village, Bhayander, Taluka and District- Thane, have cha…” Read the full reason“We are seeking extension vide Agreement dated 13.10.2022 the Owners of the property viz "Span Trident" Tower C situated at plot bearing Old Survey No. 663, New Survey No. 237, Revenue Village, Bhayander, Taluka and District- Thane, have changed the entire layout of the project. Hence Tower C which is to be developed by us in pursuance to the Development Agreement dated 10.04.2012 is now a stand alone building having its separate and distinctive amenities as against common podium amenities etc envisaged under Development Agreement dated 10.04.2012. Accordingly new permissions/approvals have…”

Source: Sumit Star Exclusif’s extension records on MahaRERA (P51700008468), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sumit Star Exclusif

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700008468
Status
Registered and active
Builder
Sumit Star Land Developers LLP
Location
Bhayandar, Thane · 401101
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
December 2021
Latest completion date
June 2027
Delay so far
66 months
Homes
78
Sold or booked
46%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sumit Star Exclusif, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
building C100%100%70%35%

Commencement certificate (CC), as filed on MahaRERA

  • building C: covers Stilt +1st Podium + 2nd Podium + 1st to 13th Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sumit Star Exclusif every 1–2 months.

Sumit Star Exclusif: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sumit Garden Grove Construction (a group of 6 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 1 within the promised date and 4 needed more time (typically 5 months); 1 still being built, 1 past the promised date (typically 46 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Sumit Star Exclusif →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sumit Star Exclusif: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sumit Star Exclusif

What is the possession date of Sumit Star Exclusif?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sumit Star Exclusif in Bhayandar, Thane is 30 June 2027 — 66 months later than 30 December 2021, the date given at registration.

The date has already moved 66 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Sumit Star Exclusif?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sumit Star Exclusif's builder has filed on MahaRERA, the official one, is 30 June 2027, already 66 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sumit Star Exclusif extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "We are seeking extension vide Agreement dated 13.10.2022 the Owners of the property viz "Span Trident" Tower C situated at plot bearing Old Survey No. 663, New Survey No. 237, Revenue Village, Bhayander, Taluka and District- Thane, have changed the entire layout of the project. Hence Tower C which is to be developed by us in pursuance to the Development Agreement dated 10.04.2012 is now a stand alone building having its separate and distinctive amenities as against common podium amenities etc envisaged under Development Agreement dated 10.04.2012. Accordingly new permissions/approvals have…".

What is the RERA number of Sumit Star Exclusif?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sumit Star Exclusif in Bhayandar, Thane is P51700008468.

Is Sumit Star Exclusif registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif is registered as P51700008468 and its status is "Registered and active".

What is the current construction status of Sumit Star Exclusif? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif's status on MahaRERA is "Registered and active". As filed by the builder, slab work on building C is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does Sumit Star Exclusif have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sumit Star Exclusif safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif is registered on MahaRERA as P51700008468, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sumit Star Exclusif?

Sumit Star Exclusif is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sumit Star Exclusif?

For a flat in Sumit Star Exclusif (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Sumit Star Exclusif received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif is still under construction, with 30 June 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Sumit Star Exclusif uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sumit Star Exclusif was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sumit Star Exclusif's possession date changes?

The latest dates are on Sumit Star Exclusif's MahaRERA page (P51700008468). GharKundli's Kundli Watch sends a free WhatsApp update on Sumit Star Exclusif every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sumit Star Exclusif have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif has one building filed: building C with 16 floors and 78 units.

How big is the land of Sumit Star Exclusif?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif stands on 2,425 sq m of land (about 0.6 acres), with 4,853 sq m of sanctioned built-up area and 548 sq m of recreational open space.

What is the track record of Sumit Star Exclusif's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Garden Grove Construction (a group of 6 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 1 within the promised date and 4 needed more time (typically 5 months); 1 still being built, 1 past the promised date (typically 46 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sumit Star Exclusif?

Google Maps has reviews of Sumit Star Exclusif written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sumit Star Exclusif?

Sumit Star Exclusif by Sumit Star Land Developers LLP is in Bhayandar, Thane, pincode 401101 (near Navghar, Goddev), Maharashtra, and is registered on MahaRERA as P51700008468, per GharKundli's check of MahaRERA records. Its land is filed as 237. GharKundli lists all 99 MahaRERA projects in Bhayander West (401101).

How many flats are in Sumit Star Exclusif, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif has 78 homes in 1 tower registered on MahaRERA, and 46% of them are sold or booked.

When was Sumit Star Exclusif registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumit Star Exclusif was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Does Sumit Star Exclusif have any legal issues or court cases?

No court cases are listed for Sumit Star Exclusif on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sumit Star Exclusif?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sumit Star Land Developers LLP.

All projects with possession due in 2027 in Thane →

Other projects in Bhayander West (401101)

All 99 projects in Bhayander West (401101) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.