BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN
by UDAY GHANSHYAM NAIK · Mira Road East, Thane
Possession date of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN: 30 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700008895, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
How the possession date of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51700018249)
Reason the builder gave MahaRERA: “Revised Commencement Certificate not yet received due to delay in ULC Clearance.”
30 December 2027
Extended at the builder's request (MahaRERA application EXT51700025656)
Reason the builder gave MahaRERA: “as per application enclosed”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN’s extension records on MahaRERA (P51700008895), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints and 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700008895
- Status
- Registered and active
- Builder
- UDAY GHANSHYAM NAIK
- Location
- Mira Road East, Thane · 401107
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2028
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 85
- Sold or booked
- 60%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN | 100% | 4% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN: covers 22 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN every month.
BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN: buildings, flats and land, as filed on MahaRERA
- Buildings: BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN (23 floors, 85 units)
- Land: 5,509 sq m (about 1.4 acres) · sanctioned built-up 198 sq m · recreational space 1,921 sq m
The builder’s record and reviews
Uday Ghanshyam Naik has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 33 months late). 6 complaints on MahaRERA across 2 projects.
Read Google reviews of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN
What is the possession date of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN in Mira Road East, Thane is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "Revised Commencement Certificate not yet received due to delay in ULC Clearance."; to 30 December 2027, giving the reason "as per application enclosed". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN in Mira Road East, Thane is P51700008895.
Is BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN is registered as P51700008895 and its status is "Registered and active".
What is the construction status of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
According to GharKundli's check of MahaRERA records (updated October 2026), BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN is 4% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN is registered on MahaRERA as P51700008895, its completion date has moved 48 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN's possession date changes?
The latest dates are on BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN's MahaRERA page (P51700008895). GharKundli's Kundli Watch sends a free WhatsApp update on BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN has one building filed: BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN with 23 floors and 85 units.
How big is the land of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
According to GharKundli's check of MahaRERA records (updated October 2026), BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN stands on 5,509 sq m of land (about 1.4 acres), with 198 sq m of sanctioned built-up area and 1,921 sq m of recreational open space.
What is the track record of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Uday Ghanshyam Naik has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 33 months late). 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
Google Maps has reviews of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN by UDAY GHANSHYAM NAIK is in Mira Road East, Thane (pincode 401107), Maharashtra, and is registered on MahaRERA as P51700008895, per GharKundli's check of MahaRERA records.
How many homes are in BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
According to GharKundli's check of MahaRERA records (updated October 2026), BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN has 85 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.
When was BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
1 court case is listed for BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UDAY GHANSHYAM NAIK, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in pincode 401107
- Umiya Oasis
- PALM LANDS
- Sheetal Utsav
- JP CONNECT-MIRAROAD
- URBAN RESERVE WING B
- CHANDRESH TERRACE
- SHANTI SIGNATURE BY ASHIT SHAH
- LOTUS
Other projects by UDAY GHANSHYAM NAIK
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.