by WESTERN REAL ESTATE PVT. LTD. · Mira Road East, ThaneAlso near Village Ghodbunder, Vinaynagar

Possession date of WESTERN PARK: 31 July 2028, moved from 30 October 2020 (89 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700004620, and currently active. Its completion date has moved from October 2020 to July 2028: 89 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about WESTERN PARK?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on WESTERN PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 2 court cases, and how it ended
  • Construction pace against the July 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700004620
Status
Registered and active
Builder
WESTERN REAL ESTATE PVT. LTD.
Location
Mira Road East, Thane · 401107
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
October 2020
Latest completion date
July 2028
Delay so far
89 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
395
Towers
2
Complaints on MahaRERA
1
Court cases listed
2
Title report on file
Not found

Construction progress of WESTERN PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AL- FAROOQUE APARTMENT100%100%100%100%
AL- SIDDIQUE APARTMENT100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on WESTERN PARK every month.

WESTERN PARK: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of WESTERN PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

WESTERN PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about WESTERN PARK

What is the possession date of WESTERN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for WESTERN PARK in Mira Road East, Thane is 31 July 2028 — 89 months later than 30 October 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for WESTERN PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date WESTERN PARK's builder has filed on MahaRERA, the official one, is 31 July 2028, already 89 months later than the 30 October 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of WESTERN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of WESTERN PARK in Mira Road East, Thane is P51700004620.

Is WESTERN PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), WESTERN PARK is registered as P51700004620 and its status is "Registered and active".

What is the construction status of WESTERN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), WESTERN PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does WESTERN PARK have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is WESTERN PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), WESTERN PARK is registered on MahaRERA as P51700004620, its completion date has moved 89 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if WESTERN PARK's possession date changes?

The latest dates are on WESTERN PARK's MahaRERA page (P51700004620). GharKundli's Kundli Watch sends a free WhatsApp update on WESTERN PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does WESTERN PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), WESTERN PARK has 2 buildings filed: AL- FAROOQUE APARTMENT with 12 floors; AL- SIDDIQUE APARTMENT with 12 floors.

How big is the land of WESTERN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), WESTERN PARK stands on 2,655 sq m of land (about 0.7 acres), with 15,269 sq m of sanctioned built-up area.

Where can I read reviews of WESTERN PARK?

Google Maps has reviews of WESTERN PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is WESTERN PARK?

WESTERN PARK by WESTERN REAL ESTATE PVT. LTD. is in Mira Road East, Thane (pincode 401107), near Village Ghodbunder, Vinaynagar, Maharashtra, and is registered on MahaRERA as P51700004620, per GharKundli's check of MahaRERA records.

How many homes are in WESTERN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), WESTERN PARK has 395 homes in 2 towers registered on MahaRERA.

When was WESTERN PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), WESTERN PARK was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on WESTERN PARK?

2 court cases are listed for WESTERN PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of WESTERN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is WESTERN REAL ESTATE PVT. LTD..

All projects with possession due in 2028 in Thane →

Other projects in pincode 401107

All 322 projects in Mira Road East (401107) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.