THE ADDRESS BUILDING NO.7/8/9
by STRAWBERRY CONSTRUCTIONS PVT. LTD. · Mira Road East, ThaneAlso near Bhayander, Village Navghar, Borivali West
Possession date of THE ADDRESS BUILDING NO.7/8/9: 7 March 2024, moved from 30 June 2021 (33 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700010224. Status: Lapsed (registration period ended). 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (March 2024) has passed.
What do you want to know about THE ADDRESS BUILDING NO.7/8/9?
How the possession date of THE ADDRESS BUILDING NO.7/8/9 has moved
30 June 2021
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT51700009922)
Reason the builder gave MahaRERA: “Civil work of the said buildings has been completed. Due to the Covid-19 pandemic the labours and machinery are shortage. Hence, the pending work like Garden/Lifts/doors and windows fitting are in slowly process.”
7 March 2024
Extended at the builder's request (MahaRERA application EXT51700025218)
Reason the builder gave MahaRERA:
“The Construction work of the said building was completed in all respect on December 2021. Further we have given the possession of flats to the flat owners but we were delayed to obtained ULC NOC (Urban Land Ceiling NOC) due to this reason w…” Read the full reason
“The Construction work of the said building was completed in all respect on December 2021. Further we have given the possession of flats to the flat owners but we were delayed to obtained ULC NOC (Urban Land Ceiling NOC) due to this reason we were unable to obtained Occupation Certificate. But now we have obtained Occupation Certificate Vide Ref. No. MNP/NR/3978/2023-2024 dated 07.03.2024 and we have already give peaceful possession to our flat buyer.”
Source: THE ADDRESS BUILDING NO.7/8/9’s extension records on MahaRERA (P51700010224), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on THE ADDRESS BUILDING NO.7/8/9
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints and 5 court cases, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- THE ADDRESS BLDG. NO. 1P51700018632 · possession 30 Apr 2029
- THE ADDRESS BLDG. NO. 6P51700018682 · possession 30 Apr 2028
- THE ADDRESS BUILDING NO. 2P51700029653 · possession 30 Apr 2027
- THE ADDRESS BUILDING NO. 3P51700029362 · possession 30 Apr 2027
- THE ADDRESS BUILDING NO.4P51700029361 · possession 30 Apr 2027
- THE ADDRESS BUILDING NO.5P51700010395 · possession 30 Apr 2029
- MahaRERA registration
- P51700010224
- Status
- Lapsed (registration period ended)
- Builder
- STRAWBERRY CONSTRUCTIONS PVT. LTD.
- Location
- Mira Road East, Thane · 401107
- Project type
- Residential / Group Housing
- Registered on
- 24 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- March 2024
- Delay so far
- 33 months
- Towers
- 3
- Complaints on MahaRERA
- 8
- Court cases listed
- 5
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of THE ADDRESS BUILDING NO.7/8/9, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 7/8/9 | 100% | 100% | 100% | 100% |
| BUILDING NO 8 | 100% | 100% | 100% | 100% |
| BUILDING NO 9 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE ADDRESS BUILDING NO.7/8/9 every month.
THE ADDRESS BUILDING NO.7/8/9: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 7/8/9 (16 floors) · BUILDING NO 8 (16 floors) · BUILDING NO 9 (16 floors)
- Land: 2,429 sq m (about 0.6 acres) · sanctioned built-up 12,867 sq m · recreational space 7,273 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Strawberry Constructions (a group of 2 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 16 months); 6 still being built, 3 past the promised date (typically 18 months late). 10 complaints on MahaRERA across 2 projects.
Read Google reviews of THE ADDRESS BUILDING NO.7/8/9 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
THE ADDRESS BUILDING NO.7/8/9: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about THE ADDRESS BUILDING NO.7/8/9
What is the possession date of THE ADDRESS BUILDING NO.7/8/9?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE ADDRESS BUILDING NO.7/8/9 in Mira Road East, Thane is 7 March 2024 — 33 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for THE ADDRESS BUILDING NO.7/8/9?
Builders and listing sites often quote an earlier "target" date for handover. The completion date THE ADDRESS BUILDING NO.7/8/9's builder has filed on MahaRERA, the official one, is 7 March 2024, already 33 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of THE ADDRESS BUILDING NO.7/8/9 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ADDRESS BUILDING NO.7/8/9's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "Civil work of the said buildings has been completed. Due to the Covid-19 pandemic the labours and machinery are shortage. Hence, the pending work like Garden/Lifts/doors and windows fitting are in slowly process."; to 7 March 2024, giving the reason "The Construction work of the said building was completed in all respect on December 2021. Further we have given the possession of flats to the flat owners but we were delayed to obtained ULC NOC (Urban Land Ceiling NOC) due to this reason we were unable to obtained Occupation Certificate. But now we have obtained Occupation Certificate Vide Ref. No. MNP/NR/3978/2023-2024 dated 07.03.2024 and we have already give peaceful possession to our flat buyer.".
What is the RERA number of THE ADDRESS BUILDING NO.7/8/9?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE ADDRESS BUILDING NO.7/8/9 in Mira Road East, Thane is P51700010224.
Is THE ADDRESS BUILDING NO.7/8/9 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ADDRESS BUILDING NO.7/8/9 is registered as P51700010224 and its status is "Lapsed (registration period ended)".
What is the construction status of THE ADDRESS BUILDING NO.7/8/9?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ADDRESS BUILDING NO.7/8/9's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does THE ADDRESS BUILDING NO.7/8/9 have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is THE ADDRESS BUILDING NO.7/8/9 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ADDRESS BUILDING NO.7/8/9 is registered on MahaRERA as P51700010224, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 33 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does THE ADDRESS BUILDING NO.7/8/9 have other wings or phases?
Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: THE ADDRESS BLDG. NO. 1 (P51700018632, possession 30 Apr 2029); THE ADDRESS BLDG. NO. 6 (P51700018682, possession 30 Apr 2028); THE ADDRESS BUILDING NO. 2 (P51700029653, possession 30 Apr 2027); THE ADDRESS BUILDING NO. 3 (P51700029362, possession 30 Apr 2027); THE ADDRESS BUILDING NO.4 (P51700029361, possession 30 Apr 2027); THE ADDRESS BUILDING NO.5 (P51700010395, possession 30 Apr 2029). Check that your agreement names the registration of your own wing.
How can I get updates if THE ADDRESS BUILDING NO.7/8/9's possession date changes?
The latest dates are on THE ADDRESS BUILDING NO.7/8/9's MahaRERA page (P51700010224). GharKundli's Kundli Watch sends a free WhatsApp update on THE ADDRESS BUILDING NO.7/8/9 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does THE ADDRESS BUILDING NO.7/8/9 have?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ADDRESS BUILDING NO.7/8/9 has 3 buildings filed: BUILDING NO 7/8/9 with 16 floors; BUILDING NO 8 with 16 floors; BUILDING NO 9 with 16 floors.
How big is the land of THE ADDRESS BUILDING NO.7/8/9?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ADDRESS BUILDING NO.7/8/9 stands on 2,429 sq m of land (about 0.6 acres), with 12,867 sq m of sanctioned built-up area and 7,273 sq m of recreational open space.
What is the track record of THE ADDRESS BUILDING NO.7/8/9's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Strawberry Constructions (a group of 2 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 16 months); 6 still being built, 3 past the promised date (typically 18 months late). 10 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of THE ADDRESS BUILDING NO.7/8/9?
Google Maps has reviews of THE ADDRESS BUILDING NO.7/8/9 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is THE ADDRESS BUILDING NO.7/8/9?
THE ADDRESS BUILDING NO.7/8/9 by STRAWBERRY CONSTRUCTIONS PVT. LTD. is in Mira Road East, Thane (pincode 401107), near Bhayander, Village Navghar, Borivali West, Maharashtra, and is registered on MahaRERA as P51700010224, per GharKundli's check of MahaRERA records.
When was THE ADDRESS BUILDING NO.7/8/9 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE ADDRESS BUILDING NO.7/8/9 was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on THE ADDRESS BUILDING NO.7/8/9?
5 court cases are listed for THE ADDRESS BUILDING NO.7/8/9 on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of THE ADDRESS BUILDING NO.7/8/9?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is STRAWBERRY CONSTRUCTIONS PVT. LTD., which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of THE ADDRESS BUILDING NO.7/8/9
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401107
- Umiya Oasis
- PALM LANDS
- Sheetal Utsav
- JP CONNECT-MIRAROAD
- URBAN RESERVE WING B
- CHANDRESH TERRACE
- SHANTI SIGNATURE BY ASHIT SHAH
- LOTUS
Other projects by STRAWBERRY CONSTRUCTIONS PVT. LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.