What’s in the report? →Possession date of Venkatesh Silver Spring (MahaRERA P51700006557): 31 December 2025, moved from 30 March 2022 (45 months later), and it has already passed. It has 132 homes, 60% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700006557. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700006557, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Venkatesh Silver Spring?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Venkatesh Silver Spring has moved
30 March 2022
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT51700011857)
Reason the builder gave MahaRERA:
“Due to Covid pandemic there was a slow down in construction work and various permission from respected gov authorities was delayed and therefore there was a need to extend the date of Completion of Project. As regard to Maharera Notificatio…” Read the full reason
“Due to Covid pandemic there was a slow down in construction work and various permission from respected gov authorities was delayed and therefore there was a need to extend the date of Completion of Project. As regard to Maharera Notification all the compliance related to extension is completed and attach for your reference. We request Maharera for please accept our application and update for extension date as soon as possible. Thank You”31 December 2025
Extended at the builder's request (MahaRERA application EXT51700027162)
Reason the builder gave MahaRERA:
“To, The Authority, Maharashtra Real Estate Regulatory Authority (MahaRERA), Mumbai, Maharashtra. Subject: Request for Extension of Project Registration for "Silver Spring" under RERA No. P51700006557 Respected Sir/Madam, We, M/s Shri Venkat…” Read the full reason
“To, The Authority, Maharashtra Real Estate Regulatory Authority (MahaRERA), Mumbai, Maharashtra. Subject: Request for Extension of Project Registration for "Silver Spring" under RERA No. P51700006557 Respected Sir/Madam, We, M/s Shri Venkatesh Ramdev Homes, are the developers of the project "Silver Spring," registered under RERA No. P51700006557, located at New S. No. 11, Hissa No. 2B. The project comprises two buildings, Wing A and Wing C, with a total of 132 units (83 units in Wing A and 49 units in Wing C). We wish to bring the following details to your kind attention: Occupancy Certific…”
Source: Venkatesh Silver Spring’s extension records on MahaRERA (P51700006557), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Venkatesh Silver Spring
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700006557
- Status
- Lapsed (registration period ended)
- Builder
- M/s. Shri Venkatesh Ramdev Homes
- Location
- Bhayandar, Thane · 401101
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2022
- Latest completion date
- December 2025
- Delay so far
- 45 months
- Homes
- 132
- Sold or booked
- 60%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Venkatesh Silver Spring, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Silver Spring Wing A | 100% | 100% | 70% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Silver Spring Wing A: covers 17 floors
- SILVER SPRING WING C: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Venkatesh Silver Spring every 1–2 months.
Venkatesh Silver Spring: buildings, flats and land, as filed on MahaRERA
- Buildings: Silver Spring Wing A (18 floors, 83 units) · SILVER SPRING WING C (19 floors, 49 units)
- Land: 3,780 sq m (about 0.9 acres) · sanctioned built-up 9,739 sq m · recreational space 489 sq m
- Boundaries filed include: Kamla Park Bungalow, Kasturi Hospital
- Land, as filed: New Survey No 11 Hissa No 2B
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Venkatesh Silver Spring →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Venkatesh Silver Spring: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Venkatesh Silver Spring
What is the possession date of Venkatesh Silver Spring?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Venkatesh Silver Spring in Bhayandar, Thane is 31 December 2025 — 45 months later than 30 March 2022, the date given at registration. That date has already passed.
The date has already moved 45 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Venkatesh Silver Spring?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Venkatesh Silver Spring's builder has filed on MahaRERA, the official one, is 31 December 2025, already 45 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Venkatesh Silver Spring extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "Due to Covid pandemic there was a slow down in construction work and various permission from respected gov authorities was delayed and therefore there was a need to extend the date of Completion of Project. As regard to Maharera Notification all the compliance related to extension is completed and attach for your reference. We request Maharera for please accept our application and update for extension date as soon as possible. Thank You"; to 31 December 2025, giving the reason "To, The Authority, Maharashtra Real Estate Regulatory Authority (MahaRERA), Mumbai, Maharashtra. Subject: Request for Extension of Project Registration for "Silver Spring" under RERA No. P51700006557 Respected Sir/Madam, We, M/s Shri Venkatesh Ramdev Homes, are the developers of the project "Silver Spring," registered under RERA No. P51700006557, located at New S. No. 11, Hissa No. 2B. The project comprises two buildings, Wing A and Wing C, with a total of 132 units (83 units in Wing A and 49 units in Wing C). We wish to bring the following details to your kind attention: Occupancy Certific…".
What is the RERA number of Venkatesh Silver Spring?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Venkatesh Silver Spring in Bhayandar, Thane is P51700006557.
Is Venkatesh Silver Spring registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring is registered as P51700006557 and its status is "Lapsed (registration period ended)".
What is the current construction status of Venkatesh Silver Spring? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Silver Spring Wing A is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does Venkatesh Silver Spring have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Venkatesh Silver Spring safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring is registered on MahaRERA as P51700006557, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Venkatesh Silver Spring?
Venkatesh Silver Spring isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Venkatesh Silver Spring?
For a flat in Venkatesh Silver Spring (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Venkatesh Silver Spring received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Venkatesh Silver Spring?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Venkatesh Silver Spring uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Venkatesh Silver Spring was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Venkatesh Silver Spring's possession date changes?
The latest dates are on Venkatesh Silver Spring's MahaRERA page (P51700006557). GharKundli's Kundli Watch sends a free WhatsApp update on Venkatesh Silver Spring every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Venkatesh Silver Spring have?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring has 2 buildings filed: Silver Spring Wing A with 18 floors and 83 units; SILVER SPRING WING C with 19 floors and 49 units.
How big is the land of Venkatesh Silver Spring?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring stands on 3,780 sq m of land (about 0.9 acres), with 9,739 sq m of sanctioned built-up area and 489 sq m of recreational open space.
What are the reviews of Venkatesh Silver Spring?
Google Maps has reviews of Venkatesh Silver Spring written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Venkatesh Silver Spring?
Venkatesh Silver Spring by M/s. Shri Venkatesh Ramdev Homes is in Bhayandar, Thane, pincode 401101, Maharashtra, and is registered on MahaRERA as P51700006557, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kamla Park Bungalow, Kasturi Hospital. Its land is filed as New Survey No 11 Hissa No 2B. GharKundli lists all 99 MahaRERA projects in Bhayander West (401101).
How many flats are in Venkatesh Silver Spring, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring has 132 homes in 2 towers registered on MahaRERA, and 60% of them are sold or booked.
When was Venkatesh Silver Spring registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Silver Spring was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Does Venkatesh Silver Spring have any legal issues or court cases?
No court cases are listed for Venkatesh Silver Spring on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Venkatesh Silver Spring?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. Shri Venkatesh Ramdev Homes.
Check it yourself on MahaRERA
- How to check the possession date of Venkatesh Silver Spring
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Bhayander West (401101)
- Sudama Vallabh wing A,B,C
- Man Mandir
- Salasar Grandeur II
- Anantsavitri Ratna Heights
- North Westend Tower 2
- North Westend Tower 1
- Mukundam
- Imperial Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.