by M/s. Arun Bhoomi Corporation · Mira Road, ThaneAlso near Mahajanwadi, Pleasant Park
Possession date of KRISHNA PRESTIGE: 30 January 2028, moved from 29 December 2022 (57 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700011183, and currently active. Its completion date has moved from December 2022 to January 2028: 57 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 72 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KRISHNA PRESTIGE?
How the possession date of KRISHNA PRESTIGE has moved
29 December 2022
Completion date given when the project was registered
29 December 2023
Extended at the builder's request (MahaRERA application EXT51700012865)
Reason the builder gave MahaRERA:
“1) Order dated 8/2/2019 passed by authority restraining promoter in creating 3rd party rights. The authority had no jurisdiction to pass such order due to lack of inherent jurisdiction and the said order came to be set aside by appellate au…” Read the full reason
“1) Order dated 8/2/2019 passed by authority restraining promoter in creating 3rd party rights. The authority had no jurisdiction to pass such order due to lack of inherent jurisdiction and the said order came to be set aside by appellate authority stating authority had no jurisdiction to pass such orders vide an order dated 28/10/2021. 2) Covid affected payment capacity of many allottees. 3) Various hurdles beyond our control at MBMC i.e authority giving sanctions due to i. Change in DCPR rules ii. Further Amendment in under construction project in DCPR rules. iii. ULC related State enquiri…”30 June 2025
Extended at the builder's request (MahaRERA application EXT51700018518)
Reason the builder gave MahaRERA:
“Order dated 8/2/2019 passed by authority restraining promoter in creating 3rd party rights. The authority had no jurisdiction to pass such order due to lack of inherent jurisdiction and the said order came to be set aside by appellate autho…” Read the full reason
“Order dated 8/2/2019 passed by authority restraining promoter in creating 3rd party rights. The authority had no jurisdiction to pass such order due to lack of inherent jurisdiction and the said order came to be set aside by appellate authority stating authority had no jurisdiction to pass such orders vide an order dated 28/10/2021. Covid affected payment capacity of many allottees. Various hurdles at MBMC i.e authority giving sanctions due to i. Change in DCPR rules ii. Further Amendment in under construction project in DCPR rules. iii. ULC related State enquiries affecting the availabilit…”30 June 2026
Extended at the builder's request (MahaRERA application EA19062501683)
Reason the builder gave MahaRERA:
“We sincerely apologize for the delay in completion and for the late submission of this extension application. The delay in the project execution and final completion has been caused due to a combination of unforeseen legal, regulatory, and…” Read the full reason
“We sincerely apologize for the delay in completion and for the late submission of this extension application. The delay in the project execution and final completion has been caused due to a combination of unforeseen legal, regulatory, and administrative circumstances, as outlined below: 1. Judicial Restraint on Creating Third-Party Rights: An order dated 08/02/2019 was passed by the Authority restraining the promoter from creating third-party rights. This order was passed without jurisdiction and was subsequently set aside by the Appellate Authority on 28/10/2021, citing the Authority’s la…”30 September 2027
Extended at the builder's request (MahaRERA application EA01062621184)
Reason the builder gave MahaRERA:
“We, M/s. Arun Bhoomi Corporation, hereby declare the following with respect to the project Krishna Prestige bearing registration number P51700011183 registered under MahaRERA. The delay in completion of the project was occasioned by several…” Read the full reason
“We, M/s. Arun Bhoomi Corporation, hereby declare the following with respect to the project Krishna Prestige bearing registration number P51700011183 registered under MahaRERA. The delay in completion of the project was occasioned by several circumstances, many of which were beyond the control of the Promoter, including the following: 1. By an Order dated 08.02.2019, the Authority restrained the Promoter from creating any third-party rights in respect of the project. Subsequently, the Appellate Authority, vide its Order dated 28.10.2021, set aside the said Order on the ground that the Author…”30 January 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: KRISHNA PRESTIGE’s extension records on MahaRERA (P51700011183), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KRISHNA PRESTIGE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 72 complaints and 5 court cases, and how it ended
- Construction pace against the January 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700011183
- Status
- Registered and active
- Builder
- M/s. Arun Bhoomi Corporation
- Location
- Mira Road, Thane · 401107
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- January 2028
- Delay so far
- 57 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 226
- Sold or booked
- 81%
- Towers
- 2
- Complaints on MahaRERA
- 72
- Court cases listed
- 5
- Appeals at the tribunal
- 3
- Title report on file
- Not found
Construction progress of KRISHNA PRESTIGE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KRISHNA PRESTIGE ABC | 100% | 62% | 35% | 0% |
| KRISHNA PRESTIGE DE | 100% | 100% | 95% | 25% |
Commencement certificate (CC), as filed on MahaRERA
- KRISHNA PRESTIGE ABC: covers 15 floors
- KRISHNA PRESTIGE DE: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KRISHNA PRESTIGE every month.
KRISHNA PRESTIGE: buildings, flats and land, as filed on MahaRERA
- Buildings: KRISHNA PRESTIGE ABC (16 floors, 157 units) · KRISHNA PRESTIGE DE (14 floors, 108 units)
- Land: 6,380 sq m (about 1.6 acres) · sanctioned built-up 5,515 sq m · recreational space 1,073 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KRISHNA PRESTIGE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KRISHNA PRESTIGE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KRISHNA PRESTIGE
What is the possession date of KRISHNA PRESTIGE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KRISHNA PRESTIGE in Mira Road, Thane is 30 January 2028 — 57 months later than 29 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KRISHNA PRESTIGE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KRISHNA PRESTIGE's builder has filed on MahaRERA, the official one, is 30 January 2028, already 57 months later than the 29 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KRISHNA PRESTIGE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA PRESTIGE's builder applied to MahaRERA to extend the completion date 4 times: to 29 December 2023, giving the reason "1) Order dated 8/2/2019 passed by authority restraining promoter in creating 3rd party rights. The authority had no jurisdiction to pass such order due to lack of inherent jurisdiction and the said order came to be set aside by appellate authority stating authority had no jurisdiction to pass such orders vide an order dated 28/10/2021. 2) Covid affected payment capacity of many allottees. 3) Various hurdles beyond our control at MBMC i.e authority giving sanctions due to i. Change in DCPR rules ii. Further Amendment in under construction project in DCPR rules. iii. ULC related State enquiri…"; to 30 June 2025, giving the reason "Order dated 8/2/2019 passed by authority restraining promoter in creating 3rd party rights. The authority had no jurisdiction to pass such order due to lack of inherent jurisdiction and the said order came to be set aside by appellate authority stating authority had no jurisdiction to pass such orders vide an order dated 28/10/2021. Covid affected payment capacity of many allottees. Various hurdles at MBMC i.e authority giving sanctions due to i. Change in DCPR rules ii. Further Amendment in under construction project in DCPR rules. iii. ULC related State enquiries affecting the availabilit…"; to 30 June 2026, giving the reason "We sincerely apologize for the delay in completion and for the late submission of this extension application. The delay in the project execution and final completion has been caused due to a combination of unforeseen legal, regulatory, and administrative circumstances, as outlined below: 1. Judicial Restraint on Creating Third-Party Rights: An order dated 08/02/2019 was passed by the Authority restraining the promoter from creating third-party rights. This order was passed without jurisdiction and was subsequently set aside by the Appellate Authority on 28/10/2021, citing the Authority’s la…"; to 30 September 2027, giving the reason "We, M/s. Arun Bhoomi Corporation, hereby declare the following with respect to the project Krishna Prestige bearing registration number P51700011183 registered under MahaRERA. The delay in completion of the project was occasioned by several circumstances, many of which were beyond the control of the Promoter, including the following: 1. By an Order dated 08.02.2019, the Authority restrained the Promoter from creating any third-party rights in respect of the project. Subsequently, the Appellate Authority, vide its Order dated 28.10.2021, set aside the said Order on the ground that the Author…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of KRISHNA PRESTIGE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KRISHNA PRESTIGE in Mira Road, Thane is P51700011183.
Is KRISHNA PRESTIGE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA PRESTIGE is registered as P51700011183 and its status is "Registered and active".
What is the construction status of KRISHNA PRESTIGE?
According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA PRESTIGE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 62% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does KRISHNA PRESTIGE have complaints on MahaRERA?
72 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KRISHNA PRESTIGE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA PRESTIGE is registered on MahaRERA as P51700011183, its completion date has moved 57 months since registration and 72 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KRISHNA PRESTIGE's possession date changes?
The latest dates are on KRISHNA PRESTIGE's MahaRERA page (P51700011183). GharKundli's Kundli Watch sends a free WhatsApp update on KRISHNA PRESTIGE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KRISHNA PRESTIGE have?
According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA PRESTIGE has 2 buildings filed: KRISHNA PRESTIGE ABC with 16 floors and 157 units; KRISHNA PRESTIGE DE with 14 floors and 108 units.
How big is the land of KRISHNA PRESTIGE?
According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA PRESTIGE stands on 6,380 sq m of land (about 1.6 acres), with 5,515 sq m of sanctioned built-up area and 1,073 sq m of recreational open space.
Where can I read reviews of KRISHNA PRESTIGE?
Google Maps has reviews of KRISHNA PRESTIGE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 72 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KRISHNA PRESTIGE?
KRISHNA PRESTIGE by M/s. Arun Bhoomi Corporation is in Mira Road, Thane (pincode 401107), near Mahajanwadi, Pleasant Park, Maharashtra, and is registered on MahaRERA as P51700011183, per GharKundli's check of MahaRERA records.
How many homes are in KRISHNA PRESTIGE?
According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA PRESTIGE has 226 homes in 2 towers registered on MahaRERA, and 81% of them are sold or booked.
When was KRISHNA PRESTIGE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA PRESTIGE was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KRISHNA PRESTIGE?
5 court cases are listed for KRISHNA PRESTIGE on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KRISHNA PRESTIGE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. Arun Bhoomi Corporation.
Check it yourself on MahaRERA
- How to check the possession date of KRISHNA PRESTIGE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in pincode 401107
- Umiya Oasis
- PALM LANDS
- Sheetal Utsav
- JP CONNECT-MIRAROAD
- URBAN RESERVE WING B
- CHANDRESH TERRACE
- SHANTI SIGNATURE BY ASHIT SHAH
- LOTUS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.