Possession date of Marq: 30 November 2028, moved from 31 May 2027 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900046132, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Marq?
How the possession date of Marq has moved
31 May 2027
Completion date given when the project was registered
30 November 2028
Extended at the builder's request (MahaRERA application EXT51900017799)
Reason the builder gave MahaRERA: “Delay In Launch”
Source: Marq’s extension records on MahaRERA (P51900046132), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Marq
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900046132
- Status
- Registered and active
- Builder
- Lodha Developers Limited
- Location
- Tardeo, Mumbai · 400007
- Project type
- Residential / Group Housing
- Registered on
- 20 Jun 2022
- Completion date at registration
- May 2027
- Latest completion date
- November 2028
- Delay so far
- 18 months
- Homes
- 81
- Sold or booked
- 54%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 180
Construction progress of Marq, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Lodha Tardeo | 0% | 57% | 12% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Lodha Tardeo: covers 20 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Marq every month.
Marq: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Other | 1,389 – 6,390 | 27 |
| 3 BHK | 1,389 | 25 |
| 5 BHK | 2,793 | 25 |
| 4 BHK | 2,388 – 2,849 | 4 |
- Buildings: Lodha Tardeo (34 floors, 81 units)
- Land: 6,139 sq m (about 1.5 acres) · sanctioned built-up 27,722 sq m · recreational space 1,762 sq m
- Boundaries filed include: Tukaram Javaji Road
The builder’s record and reviews
Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.
Read Google reviews of Marq →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Marq: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Marq
What is the possession date of Marq?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Marq in Tardeo, Mumbai is 30 November 2028 — 18 months later than 31 May 2027, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Marq?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Marq's builder has filed on MahaRERA, the official one, is 30 November 2028, already 18 months later than the 31 May 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Marq extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Marq's builder applied to MahaRERA to extend the completion date once: to 30 November 2028, giving the reason "Delay In Launch".
What is the RERA number of Marq?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Marq in Tardeo, Mumbai is P51900046132.
Is Marq registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Marq is registered as P51900046132 and its status is "Registered and active".
What is the construction status of Marq?
According to GharKundli's check of MahaRERA records (updated October 2026), Marq's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Lodha Tardeo is 57% done and internal work 12%. GharKundli's full report compares construction progress with the deadline.
Does Marq have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Marq safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Marq is registered on MahaRERA as P51900046132, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Marq's possession date changes?
The latest dates are on Marq's MahaRERA page (P51900046132). GharKundli's Kundli Watch sends a free WhatsApp update on Marq every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Marq have?
According to GharKundli's check of MahaRERA records (updated October 2026), Marq has one building filed: Lodha Tardeo with 34 floors and 81 units.
What are the flat sizes (carpet area) in Marq?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Marq: Other: 1389 to 6390 sq ft carpet (27 homes); 3 BHK: 1389 sq ft carpet (25 homes); 5 BHK: 2793 sq ft carpet (25 homes); 4 BHK: 2388 to 2849 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Marq?
According to GharKundli's check of MahaRERA records (updated October 2026), Marq stands on 6,139 sq m of land (about 1.5 acres), with 27,722 sq m of sanctioned built-up area and 1,762 sq m of recreational open space.
What is the track record of Marq's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Marq?
Google Maps has reviews of Marq written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Marq?
Marq by Lodha Developers Limited is in Tardeo, Mumbai (pincode 400007), near Grant Road, Cumballa Hill, Mumbai Central, Maharashtra, and is registered on MahaRERA as P51900046132, per GharKundli's check of MahaRERA records. Its boundaries filed there include Tukaram Javaji Road.
How many homes are in Marq?
According to GharKundli's check of MahaRERA records (updated October 2026), Marq has 81 homes in 1 tower registered on MahaRERA, and 54% of them are sold or booked.
When was Marq registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Marq was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Marq?
No court cases are listed for Marq on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Marq?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Marq
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai City →
Other projects in pincode 400007
- SHREE SAMMET SHIKHAR HEIGHTS
- FORTUNE AURA
- SUGAN HEIGHTS
- Shapoorji Pallonji The Odyssey 1
- SHREE SAMMET SHIKHAR HEIGHTS - C WING
- SEVEN DHULEVA
- Aplite Sapphire
- NIRVAANA PEARL
Other projects by Lodha Developers Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.