by SAMRIN INFRA PRIVATE LIMITED · Panchpakhadi, ThaneAlso near Naupada, Charai, Thane West

Possession date of SAMRIN HERITAGE: 30 April 2027, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700016394, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAMRIN HERITAGE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAMRIN HERITAGE has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51700017126)

    Reason the builder gave MahaRERA:
    “The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022. This has resulted in slow progress in construction. However we are trying to complete th…” Read the full reason“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. The status of current construction is reflected in Form 1 attached herewith. We intend to execute an agreement with the new customer to mention the date of possession on or before 29.12.2024. Kindly process our application and grant us the extension till 29.12.2024.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700024935)

    Reason the builder gave MahaRERA:
    “• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump chall…” Read the full reason“• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led…”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA27112518449)

    Reason the builder gave MahaRERA:
    “REASONS FOR DELAY 1.The Developer submits that the project could have been completed within the stipulated timeline; however, an ongoing litigation initiated by an adjoining landowner has directly impacted the project’s progress since March…” Read the full reason“REASONS FOR DELAY 1.The Developer submits that the project could have been completed within the stipulated timeline; however, an ongoing litigation initiated by an adjoining landowner has directly impacted the project’s progress since March 2023. 2.The proposed parking building was planned to be constructed on Plot No. 376. A litigation concerning the said plot was filed by Mr. Kamlakar B. Patil, registered as RCS No. 584/2020, and is presently pending before the City Civil Court, Thane, before Hon’ble Judge Smt. Jagdale. The next hearing in this matter is scheduled on 31/10/2025. 3.The Res…”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAMRIN HERITAGE’s extension records on MahaRERA (P51700016394), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAMRIN HERITAGE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700016394
Status
Registered and active
Builder
SAMRIN INFRA PRIVATE LIMITED
Location
Panchpakhadi, Thane · 400602
Project type
Others
Registered on
10 May 2018
Completion date at registration
December 2023
Latest completion date
April 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
412
Sold or booked
53%
Towers
4
Complaints on MahaRERA
4
Court cases listed
0
Title report on file
Not found

Construction progress of SAMRIN HERITAGE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
S1100%100%85%25%
S2100%100%80%85%
S3100%100%100%100%
S4100%50%25%25%

Commencement certificate (CC), as filed on MahaRERA

  • S1: covers 39 floors
  • S2: covers 39 floors
  • S3: covers 23 floors
  • S4: covers 37 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAMRIN HERITAGE every month.

SAMRIN HERITAGE: buildings, flats and land, as filed on MahaRERA

  • Buildings: S1 (39 floors, 164 units) · S2 (39 floors, 166 units) · S3 (23 floors, 80 units) · S4 (37 floors, 78 units)
  • Land: 8,423 sq m (about 2.1 acres) · sanctioned built-up 33,896 sq m · recreational space 796 sq m
  • Boundaries filed include: 24Pt40mt wide Almeda Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Samrin Dreamspaces (a group of 7 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 4 past the promised date (typically 12 months late); 3 lapsed. 37 complaints on MahaRERA across 6 projects.

Read Google reviews of SAMRIN HERITAGE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAMRIN HERITAGE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAMRIN HERITAGE

What is the possession date of SAMRIN HERITAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAMRIN HERITAGE in Panchpakhadi, Thane is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAMRIN HERITAGE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAMRIN HERITAGE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAMRIN HERITAGE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAMRIN HERITAGE's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. The status of current construction is reflected in Form 1 attached herewith. We intend to execute an agreement with the new customer to mention the date of possession on or before 29.12.2024. Kindly process our application and grant us the extension till 29.12.2024."; to 31 December 2025, giving the reason "• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led…"; to 31 December 2026, giving the reason "REASONS FOR DELAY 1.The Developer submits that the project could have been completed within the stipulated timeline; however, an ongoing litigation initiated by an adjoining landowner has directly impacted the project’s progress since March 2023. 2.The proposed parking building was planned to be constructed on Plot No. 376. A litigation concerning the said plot was filed by Mr. Kamlakar B. Patil, registered as RCS No. 584/2020, and is presently pending before the City Civil Court, Thane, before Hon’ble Judge Smt. Jagdale. The next hearing in this matter is scheduled on 31/10/2025. 3.The Res…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SAMRIN HERITAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAMRIN HERITAGE in Panchpakhadi, Thane is P51700016394.

Is SAMRIN HERITAGE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAMRIN HERITAGE is registered as P51700016394 and its status is "Registered and active".

What is the construction status of SAMRIN HERITAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), SAMRIN HERITAGE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 50% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does SAMRIN HERITAGE have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAMRIN HERITAGE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAMRIN HERITAGE is registered on MahaRERA as P51700016394, its completion date has moved 36 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAMRIN HERITAGE's possession date changes?

The latest dates are on SAMRIN HERITAGE's MahaRERA page (P51700016394). GharKundli's Kundli Watch sends a free WhatsApp update on SAMRIN HERITAGE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAMRIN HERITAGE have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAMRIN HERITAGE has 4 buildings filed: S1 with 39 floors and 164 units; S2 with 39 floors and 166 units; S3 with 23 floors and 80 units; S4 with 37 floors and 78 units.

How big is the land of SAMRIN HERITAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), SAMRIN HERITAGE stands on 8,423 sq m of land (about 2.1 acres), with 33,896 sq m of sanctioned built-up area and 796 sq m of recreational open space.

What is the track record of SAMRIN HERITAGE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Dreamspaces (a group of 7 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 4 past the promised date (typically 12 months late); 3 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAMRIN HERITAGE?

Google Maps has reviews of SAMRIN HERITAGE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAMRIN HERITAGE?

SAMRIN HERITAGE by SAMRIN INFRA PRIVATE LIMITED is in Panchpakhadi, Thane (pincode 400602), near Naupada, Charai, Thane West, Maharashtra, and is registered on MahaRERA as P51700016394, per GharKundli's check of MahaRERA records. Its boundaries filed there include 24Pt40mt wide Almeda Road.

How many homes are in SAMRIN HERITAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), SAMRIN HERITAGE has 412 homes in 4 towers registered on MahaRERA, and 53% of them are sold or booked.

When was SAMRIN HERITAGE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAMRIN HERITAGE was registered on MahaRERA on 10 May 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SAMRIN HERITAGE?

No court cases are listed for SAMRIN HERITAGE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAMRIN HERITAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAMRIN INFRA PRIVATE LIMITED.

All projects with possession due in 2027 in Thane →

Other projects in Panchpakhadi

All 258 projects in Naupada (400602) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.