Tesla - Building No.2
by Raheja Universal (Pvt.) Ltd. · D Block, TTC Industrial Area, MIDC, Thane
Possession: Tesla - Building No.2 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700019181. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Tesla - Building No.2?
GharKundli’s full report on Tesla - Building No.2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700019181
- Status
- Completed
- Builder
- Raheja Universal (Pvt.) Ltd.
- Location
- D Block, TTC Industrial Area, MIDC, Thane · 400705
- Project type
- Mixed
- Registered on
- 9 Jan 2019
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 0
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 17
Construction progress of Tesla - Building No.2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tesla Building No2 | 100% | 100% | 95% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Tesla Building No2: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tesla - Building No.2 every month.
Tesla - Building No.2: buildings, flats and land, as filed on MahaRERA
- Buildings: Tesla Building No2 (5 floors, 324 units)
- Land: 4,745 sq m (about 1.2 acres) · sanctioned built-up 20,582 sq m · recreational space 5,390 sq m
- Boundaries filed include: Internal Road of Larger Layout
The builder’s record and reviews
Raheja Universal (a group of 2 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 2 finished, all within the promised date; 17 still being built, none past the promised date yet. 18 complaints on MahaRERA across 7 projects.
Read Google reviews of Tesla - Building No.2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tesla - Building No.2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Tesla - Building No.2
What is the possession date of Tesla - Building No.2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tesla - Building No.2 in D Block, TTC Industrial Area, MIDC, Thane is 30 December 2025 — 12 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Tesla - Building No.2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tesla - Building No.2's builder has filed on MahaRERA, the official one, is 30 December 2025, already 12 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Tesla - Building No.2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tesla - Building No.2 in D Block, TTC Industrial Area, MIDC, Thane is P51700019181.
Is Tesla - Building No.2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tesla - Building No.2 is registered as P51700019181 and its status is "Completed".
What is the construction status of Tesla - Building No.2?
According to GharKundli's check of MahaRERA records (updated October 2026), Tesla - Building No.2's status on MahaRERA is "Completed". As filed by the builder, slab work on Tesla Building No2 is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Tesla - Building No.2 have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Tesla - Building No.2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tesla - Building No.2 is registered on MahaRERA as P51700019181, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Tesla - Building No.2's possession date changes?
The latest dates are on Tesla - Building No.2's MahaRERA page (P51700019181). GharKundli's Kundli Watch sends a free WhatsApp update on Tesla - Building No.2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tesla - Building No.2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tesla - Building No.2 has one building filed: Tesla Building No2 with 5 floors and 324 units.
How big is the land of Tesla - Building No.2?
According to GharKundli's check of MahaRERA records (updated October 2026), Tesla - Building No.2 stands on 4,745 sq m of land (about 1.2 acres), with 20,582 sq m of sanctioned built-up area and 5,390 sq m of recreational open space.
What is the track record of Tesla - Building No.2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Universal (a group of 2 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 2 finished, all within the promised date; 17 still being built, none past the promised date yet. 18 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Tesla - Building No.2?
Google Maps has reviews of Tesla - Building No.2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Tesla - Building No.2?
Tesla - Building No.2 by Raheja Universal (Pvt.) Ltd. is in D Block, TTC Industrial Area, MIDC, Thane (pincode 400705), Maharashtra, and is registered on MahaRERA as P51700019181, per GharKundli's check of MahaRERA records. Its boundaries filed there include Internal Road of Larger Layout.
How many homes are in Tesla - Building No.2?
According to GharKundli's check of MahaRERA records (updated October 2026), Tesla - Building No.2 has 0 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Tesla - Building No.2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tesla - Building No.2 was registered on MahaRERA on 9 January 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Tesla - Building No.2?
No court cases are listed for Tesla - Building No.2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Tesla - Building No.2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Raheja Universal (Pvt.) Ltd., which has 17 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Tesla - Building No.2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects in Sanpada (400705) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.