by SONAM HOMES PRIVATE LIMITED · Kashigaon, Mira Bhayander, Thane 401107Also near Mira Road EastRegistered on MahaRERA as “INDRADHANUSH”

What’s in the report? →

Possession date of Sonam Indradhanush (MahaRERA P51700019830): 30 March 2027, moved from 30 October 2024 (29 months later). It has 360 homes, 71% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700019830, and currently active.

Source: MahaRERA website — records for P51700019830, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Sonam Indradhanush?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sonam Indradhanush has moved

  1. 30 October 2024

    Completion date given when the project was registered

  2. 30 October 2025

    Extended at the builder's request (MahaRERA application EXT51700008422)

    Reason the builder gave MahaRERA: “Project is to be extended because of Covid 19, non availability of contractors, labours and materials. As well as the natural calamity like flood also affected the constructions”
  3. 30 March 2027

    Extended at the builder's request (MahaRERA application EXT51700010948)

    Reason the builder gave MahaRERA:
    “With the implementation of new DCR, higher FSI is granded by Govt of Maharashtra. Accordingly the structure of the building is changing from Ground+1 Podium+20 floors to Ground+ 2Podium+30 floors. Thus, extension is required to revise build…” Read the full reason“With the implementation of new DCR, higher FSI is granded by Govt of Maharashtra. Accordingly the structure of the building is changing from Ground+1 Podium+20 floors to Ground+ 2Podium+30 floors. Thus, extension is required to revise building plans, revise CC and construct increased floors.”

Source: Sonam Indradhanush’s extension records on MahaRERA (P51700019830), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sonam Indradhanush

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700019830
Status
Registered and active
Builder
SONAM HOMES PRIVATE LIMITED
Location
Kashigaon, Mira Bhayander, Thane · 401107
Project type
Others
Registered on
5 Mar 2019
Completion date at registration
October 2024
Latest completion date
March 2027
Delay so far
29 months
Homes
360
Sold or booked
71%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sonam Indradhanush, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
INDRADHANUSH AB-1100%100%100%100%
INDRADHANUSH AB-2100%100%100%100%
INDRADHANUSH AB-3100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • INDRADHANUSH AB-1: covers 33 floors
  • INDRADHANUSH AB-2: covers 33 floors
  • INDRADHANUSH AB-3: covers 1 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sonam Indradhanush every 1–2 months.

Sonam Indradhanush: buildings, flats and land, as filed on MahaRERA

  • Buildings: INDRADHANUSH AB-1 (33 floors, 180 units) · INDRADHANUSH AB-2 (33 floors, 180 units) · INDRADHANUSH AB-3 (1 floors, 14 units)
  • Land: 8,790 sq m (about 2.2 acres) · sanctioned built-up 14,640 sq m · recreational space 1,277 sq m
  • Boundaries filed include: GREEN WOOD COMPLEX, AMISHA GARDEN
  • Land, as filed: 20/2
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Sonam Spark Infra (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 5 months); 2 still being built, 1 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Sonam Indradhanush →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sonam Indradhanush: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sonam Indradhanush

What is the possession date of Sonam Indradhanush?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sonam Indradhanush in Kashigaon, Mira Bhayander, Thane is 30 March 2027 — 29 months later than 30 October 2024, the date given at registration.

The date has already moved 29 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Sonam Indradhanush?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sonam Indradhanush's builder has filed on MahaRERA, the official one, is 30 March 2027, already 29 months later than the 30 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sonam Indradhanush extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush's builder applied to MahaRERA to extend the completion date 2 times: to 30 October 2025, giving the reason "Project is to be extended because of Covid 19, non availability of contractors, labours and materials. As well as the natural calamity like flood also affected the constructions"; to 30 March 2027, giving the reason "With the implementation of new DCR, higher FSI is granded by Govt of Maharashtra. Accordingly the structure of the building is changing from Ground+1 Podium+20 floors to Ground+ 2Podium+30 floors. Thus, extension is required to revise building plans, revise CC and construct increased floors.".

What is the RERA number of Sonam Indradhanush?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sonam Indradhanush in Kashigaon, Mira Bhayander, Thane is P51700019830.

Is Sonam Indradhanush registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush is registered as P51700019830 and its status is "Registered and active".

What is the current construction status of Sonam Indradhanush? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Sonam Indradhanush have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sonam Indradhanush safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush is registered on MahaRERA as P51700019830, its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sonam Indradhanush?

Sonam Indradhanush is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sonam Indradhanush?

For a flat in Sonam Indradhanush (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Sonam Indradhanush received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush is still under construction, with 30 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Sonam Indradhanush uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sonam Indradhanush was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sonam Indradhanush's possession date changes?

The latest dates are on Sonam Indradhanush's MahaRERA page (P51700019830). GharKundli's Kundli Watch sends a free WhatsApp update on Sonam Indradhanush every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sonam Indradhanush have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush has 3 buildings filed: INDRADHANUSH AB-1 with 33 floors and 180 units; INDRADHANUSH AB-2 with 33 floors and 180 units; INDRADHANUSH AB-3 with 1 floors and 14 units.

How big is the land of Sonam Indradhanush?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush stands on 8,790 sq m of land (about 2.2 acres), with 14,640 sq m of sanctioned built-up area and 1,277 sq m of recreational open space.

What is the track record of Sonam Indradhanush's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Spark Infra (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 5 months); 2 still being built, 1 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sonam Indradhanush?

Google Maps has reviews of Sonam Indradhanush written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sonam Indradhanush?

Sonam Indradhanush by SONAM HOMES PRIVATE LIMITED is in Kashigaon, Mira Bhayander, Thane, pincode 401107 (near Mira Road East), Maharashtra, and is registered on MahaRERA as P51700019830, per GharKundli's check of MahaRERA records. Its boundaries filed there include GREEN WOOD COMPLEX, AMISHA GARDEN. Its land is filed as 20/2. GharKundli lists all 323 MahaRERA projects in Mira Road East (401107).

How many flats are in Sonam Indradhanush, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush has 360 homes in 3 towers registered on MahaRERA, and 71% of them are sold or booked.

When was Sonam Indradhanush registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonam Indradhanush was registered on MahaRERA on 5 March 2019. GharKundli did not find a title report on the land on file there.

Does Sonam Indradhanush have any legal issues or court cases?

No court cases are listed for Sonam Indradhanush on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sonam Indradhanush?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SONAM HOMES PRIVATE LIMITED.

All projects with possession due in 2027 in Thane →

Other projects in Thane

All 323 projects in Mira Road East (401107) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.