Skip to content
GharKundli

MAULI KRUPA

by VIGHNESH CONSTRUCTIONS · Navi Mumbai, ThaneAlso near Ghansoli

Possession date of MAULI KRUPA: 30 April 2027, moved from 31 August 2018 (100 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700011488, and currently active. Its completion date has moved from August 2018 to April 2027: 100 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MAULI KRUPA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MAULI KRUPA has moved

  1. 31 August 2018

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA29062621606)

    Reason the builder gave MahaRERA:
    “The project construction has been substantially completed, and the application for the Occupancy Certificate (OC) has already been submitted to the competent Planning Authority. The OC is pending due to administrative reasons beyond the Pro…” Read the full reason“The project construction has been substantially completed, and the application for the Occupancy Certificate (OC) has already been submitted to the competent Planning Authority. The OC is pending due to administrative reasons beyond the Promoter's control, despite full compliance with all statutory requirements and regular follow-ups. Since possession cannot be legally handed over without the OC, the extension of project registration is sought solely to maintain compliance under MahaRERA until the OC is received. No additional construction or changes are proposed, and the Promoter remains c…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MAULI KRUPA’s extension records on MahaRERA (P51700011488), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MAULI KRUPA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700011488
Status
Registered and active
Builder
VIGHNESH CONSTRUCTIONS
Location
Navi Mumbai, Thane · 400701
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
August 2018
Latest completion date
April 2027
Delay so far
100 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
16
Sold or booked
28%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of MAULI KRUPA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MAULI KRUPA100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • MAULI KRUPA: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAULI KRUPA every month.

MAULI KRUPA: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK29910
2 BHK4508

The builder’s record and reviews

SAI Krupa Builders & Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 20 months); 3 still being built, 3 past the promised date (typically 94 months late). No complaints on MahaRERA.

Read Google reviews of MAULI KRUPA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MAULI KRUPA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MAULI KRUPA

What is the possession date of MAULI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAULI KRUPA in Navi Mumbai, Thane is 30 April 2027 — 100 months later than 31 August 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MAULI KRUPA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MAULI KRUPA's builder has filed on MahaRERA, the official one, is 30 April 2027, already 100 months later than the 31 August 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MAULI KRUPA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MAULI KRUPA's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The project construction has been substantially completed, and the application for the Occupancy Certificate (OC) has already been submitted to the competent Planning Authority. The OC is pending due to administrative reasons beyond the Promoter's control, despite full compliance with all statutory requirements and regular follow-ups. Since possession cannot be legally handed over without the OC, the extension of project registration is sought solely to maintain compliance under MahaRERA until the OC is received. No additional construction or changes are proposed, and the Promoter remains c…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MAULI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MAULI KRUPA in Navi Mumbai, Thane is P51700011488.

Is MAULI KRUPA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAULI KRUPA is registered as P51700011488 and its status is "Registered and active".

What is the construction status of MAULI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAULI KRUPA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MAULI KRUPA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MAULI KRUPA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MAULI KRUPA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MAULI KRUPA is registered on MahaRERA as P51700011488, its completion date has moved 100 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MAULI KRUPA's possession date changes?

The latest dates are on MAULI KRUPA's MahaRERA page (P51700011488). GharKundli's Kundli Watch sends a free WhatsApp update on MAULI KRUPA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MAULI KRUPA have?

According to GharKundli's check of MahaRERA records (updated October 2026), MAULI KRUPA has one building filed: MAULI KRUPA with 6 floors and 18 units.

What are the flat sizes (carpet area) in MAULI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MAULI KRUPA: 2 BHK: 450 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does MAULI KRUPA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered and 2 open car parking spaces for MAULI KRUPA.

How big is the land of MAULI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAULI KRUPA stands on 391 sq m of land (about 0.1 acres), with 586 sq m of sanctioned built-up area.

What is the track record of MAULI KRUPA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI Krupa Builders & Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 20 months); 3 still being built, 3 past the promised date (typically 94 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MAULI KRUPA?

Google Maps has reviews of MAULI KRUPA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MAULI KRUPA?

MAULI KRUPA by VIGHNESH CONSTRUCTIONS is in Navi Mumbai, Thane (pincode 400701), near Ghansoli, Maharashtra, and is registered on MahaRERA as P51700011488, per GharKundli's check of MahaRERA records.

How many homes are in MAULI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAULI KRUPA has 16 homes in 1 tower registered on MahaRERA, and 28% of them are sold or booked.

When was MAULI KRUPA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAULI KRUPA was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MAULI KRUPA?

1 court case is listed for MAULI KRUPA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of MAULI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIGHNESH CONSTRUCTIONS.

All projects with possession due in 2027 in Thane →

Other projects in Navi Mumbai

All 79 projects in Ghansoli (400701) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.