Skip to content
GharKundli

SATYAM VALENCIA

by ARHAM DEVELOPERS · Navi Mumbai, Raigarh

Possession date of SATYAM VALENCIA: 30 April 2028, moved from 26 March 2025 (33 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000033087, and currently active. Its completion date has moved from March 2025 to April 2028: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SATYAM VALENCIA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SATYAM VALENCIA has moved

  1. 26 March 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT52000018254)

    Reason the builder gave MahaRERA: “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control. We have consent of 0% allottees as we have not sold a single flat in the project.”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SATYAM VALENCIA’s extension records on MahaRERA (P52000033087), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SATYAM VALENCIA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000033087
Status
Registered and active
Builder
ARHAM DEVELOPERS
Location
Navi Mumbai, Raigarh · 410210
Project type
Others
Registered on
3 Feb 2022
Completion date at registration
March 2025
Latest completion date
April 2028
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
80
Sold or booked
67%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of SATYAM VALENCIA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SATYAM VALENCIA100%100%95%90%

Commencement certificate (CC), as filed on MahaRERA

  • SATYAM VALENCIA: covers 32 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SATYAM VALENCIA every month.

SATYAM VALENCIA: buildings, flats and land, as filed on MahaRERA

  • Buildings: SATYAM VALENCIA (32 floors, 97 units)
  • Car parking: 158 covered
  • Land: 2,732 sq m (about 0.7 acres) · sanctioned built-up 15,327 sq m
  • Boundaries filed include: 11 MTRWIDE ROAD

The builder’s record and reviews

Arham Developers has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA.

Read Google reviews of SATYAM VALENCIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SATYAM VALENCIA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SATYAM VALENCIA

What is the possession date of SATYAM VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SATYAM VALENCIA in Navi Mumbai, Raigarh is 30 April 2028 — 33 months later than 26 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SATYAM VALENCIA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SATYAM VALENCIA's builder has filed on MahaRERA, the official one, is 30 April 2028, already 33 months later than the 26 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SATYAM VALENCIA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SATYAM VALENCIA's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control. We have consent of 0% allottees as we have not sold a single flat in the project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SATYAM VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SATYAM VALENCIA in Navi Mumbai, Raigarh is P52000033087.

Is SATYAM VALENCIA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SATYAM VALENCIA is registered as P52000033087 and its status is "Registered and active".

What is the construction status of SATYAM VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), SATYAM VALENCIA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SATYAM VALENCIA is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does SATYAM VALENCIA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SATYAM VALENCIA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SATYAM VALENCIA is registered on MahaRERA as P52000033087, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SATYAM VALENCIA's possession date changes?

The latest dates are on SATYAM VALENCIA's MahaRERA page (P52000033087). GharKundli's Kundli Watch sends a free WhatsApp update on SATYAM VALENCIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SATYAM VALENCIA have?

According to GharKundli's check of MahaRERA records (updated October 2026), SATYAM VALENCIA has one building filed: SATYAM VALENCIA with 32 floors and 97 units.

How much parking does SATYAM VALENCIA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 158 covered car parking spaces for SATYAM VALENCIA.

How big is the land of SATYAM VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), SATYAM VALENCIA stands on 2,732 sq m of land (about 0.7 acres), with 15,327 sq m of sanctioned built-up area.

What is the track record of SATYAM VALENCIA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Arham Developers has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SATYAM VALENCIA?

Google Maps has reviews of SATYAM VALENCIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SATYAM VALENCIA?

SATYAM VALENCIA by ARHAM DEVELOPERS is in Navi Mumbai, Raigarh (pincode 410210), Maharashtra, and is registered on MahaRERA as P52000033087, per GharKundli's check of MahaRERA records. Its boundaries filed there include 11 MTRWIDE ROAD.

How many homes are in SATYAM VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), SATYAM VALENCIA has 80 homes in 1 tower registered on MahaRERA, and 67% of them are sold or booked.

When was SATYAM VALENCIA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SATYAM VALENCIA was registered on MahaRERA on 3 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SATYAM VALENCIA?

No court cases are listed for SATYAM VALENCIA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SATYAM VALENCIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARHAM DEVELOPERS, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2028 in Raigad →

Other projects in Navi Mumbai

All 185 projects in Kharghar (410210) →

Other projects by ARHAM DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.