AKSHAR EVITA
by M/S.AKSHAR OM CONSTRUCTION (Geomatrix) · Navi Mumbai, Thane
Possession date of AKSHAR EVITA: 15 November 2026, moved from 30 June 2021 (65 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700004758, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (November 2026) has passed.
What do you want to know about AKSHAR EVITA?
How the possession date of AKSHAR EVITA has moved
30 June 2021
Completion date given when the project was registered
15 November 2026
Extended at the builder's request (MahaRERA application EA22072621828)
Reason the builder gave MahaRERA:
“we, M/s. Akshar Om Construction, hereby declare the following with respect to the project Akshar Evita bearing registration number P51700004758 registered under MahaRERA. The delay in the completion of the real estate project has been prima…” Read the full reason
“we, M/s. Akshar Om Construction, hereby declare the following with respect to the project Akshar Evita bearing registration number P51700004758 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 06/10/2025 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, total…”
Source: AKSHAR EVITA’s extension records on MahaRERA (P51700004758), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AKSHAR EVITA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700004758
- Status
- Registered and active
- Builder
- M/S.AKSHAR OM CONSTRUCTION
- Location
- Navi Mumbai, Thane · 400706
- Project type
- Others
- Registered on
- 9 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- November 2026
- Delay so far
- 65 months
- Homes
- 69
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AKSHAR EVITA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AKSHAR EVITA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- AKSHAR EVITA: covers 13(Ground + 12 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AKSHAR EVITA every month.
AKSHAR EVITA: buildings, flats and land, as filed on MahaRERA
- Buildings: AKSHAR EVITA (13 floors, 76 units)
- Car parking: 22 covered
- Land: 1,450 sq m (about 0.4 acres) · sanctioned built-up 2,173 sq m
- Boundaries filed include: 22 MTS WIDE ROAD
The builder’s record and reviews
Akshar Developers (a group of 12 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 6 finished, 4 within the promised date and 2 needed more time (typically 36 months); 8 still being built, 2 past the promised date (typically 29 months late); 2 lapsed. 10 complaints on MahaRERA across 2 projects.
Read Google reviews of AKSHAR EVITA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AKSHAR EVITA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AKSHAR EVITA
What is the possession date of AKSHAR EVITA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AKSHAR EVITA in Navi Mumbai, Thane is 15 November 2026 — 65 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for AKSHAR EVITA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AKSHAR EVITA's builder has filed on MahaRERA, the official one, is 15 November 2026, already 65 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AKSHAR EVITA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAR EVITA's builder applied to MahaRERA to extend the completion date once: to 15 November 2026, giving the reason "we, M/s. Akshar Om Construction, hereby declare the following with respect to the project Akshar Evita bearing registration number P51700004758 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 06/10/2025 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, total…".
What is the RERA number of AKSHAR EVITA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AKSHAR EVITA in Navi Mumbai, Thane is P51700004758.
Is AKSHAR EVITA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAR EVITA is registered as P51700004758 and its status is "Registered and active".
What is the construction status of AKSHAR EVITA?
According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAR EVITA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AKSHAR EVITA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does AKSHAR EVITA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is AKSHAR EVITA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAR EVITA is registered on MahaRERA as P51700004758, its completion date has moved 65 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AKSHAR EVITA's possession date changes?
The latest dates are on AKSHAR EVITA's MahaRERA page (P51700004758). GharKundli's Kundli Watch sends a free WhatsApp update on AKSHAR EVITA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AKSHAR EVITA have?
According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAR EVITA has one building filed: AKSHAR EVITA with 13 floors and 76 units.
How much parking does AKSHAR EVITA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 covered car parking spaces for AKSHAR EVITA.
How big is the land of AKSHAR EVITA?
According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAR EVITA stands on 1,450 sq m of land (about 0.4 acres), with 2,173 sq m of sanctioned built-up area.
What is the track record of AKSHAR EVITA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Developers (a group of 12 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 6 finished, 4 within the promised date and 2 needed more time (typically 36 months); 8 still being built, 2 past the promised date (typically 29 months late); 2 lapsed. 10 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of AKSHAR EVITA?
Google Maps has reviews of AKSHAR EVITA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AKSHAR EVITA?
AKSHAR EVITA by M/S.AKSHAR OM CONSTRUCTION (Geomatrix) is in Navi Mumbai, Thane (pincode 400706), Maharashtra, and is registered on MahaRERA as P51700004758, per GharKundli's check of MahaRERA records. Its boundaries filed there include 22 MTS WIDE ROAD.
How many homes are in AKSHAR EVITA?
According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAR EVITA has 69 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was AKSHAR EVITA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAR EVITA was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on AKSHAR EVITA?
No court cases are listed for AKSHAR EVITA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AKSHAR EVITA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S.AKSHAR OM CONSTRUCTION, the company Geomatrix files this project under.
Check it yourself on MahaRERA
- How to check the possession date of AKSHAR EVITA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Navi Mumbai
- MAULI KRUPA
- VRINDAVAN CHANDAR HEIGHTS
- SATYAM VALENCIA
- DREAM DIGIT
- AAROHI COMPLEX
- FLORENCE
- NEELKANTH EXOTICA
- HIRAYS OLEANDER
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.