HIRAYS OLEANDER

by JAGANNATH DASHARATH HIRAY · Navi Mumbai, Raigarh

Possession date of HIRAYS OLEANDER: 31 July 2026, moved from 30 June 2021 (57 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000005407. Status: Lapsed (registration period ended). Its completion date has moved from June 2021 to July 2026: 57 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about HIRAYS OLEANDER?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HIRAYS OLEANDER has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT52000008468)

    Reason the builder gave MahaRERA:
    “We had applied for the plinth completion certificate on 31/08/2018. We have received the plinth completion certificate on 30/09/2020. The reason behind this delay is there was some issue with regards to the Maveja in CIDCO as CIDCO is the a…” Read the full reason“We had applied for the plinth completion certificate on 31/08/2018. We have received the plinth completion certificate on 30/09/2020. The reason behind this delay is there was some issue with regards to the Maveja in CIDCO as CIDCO is the approving authority for all the permissions. Because of which the process was stopped in CIDCO due to this issue. Also, due to COVID Pandemic, there was a significant addition in the delay to obtain the plinth completion certificate. So, we request you to extend the date of completion of this project till December 2024 as there are more challenges with reg…”
  3. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52000016751)

    Reason the builder gave MahaRERA:
    “Dear Team, We want to apply for an extension due to the delay caused because of shortage of labor after the covid lockdown and the strike of material suppliers. 1. The labor resources required for construction are still not available in the…” Read the full reason“Dear Team, We want to apply for an extension due to the delay caused because of shortage of labor after the covid lockdown and the strike of material suppliers. 1. The labor resources required for construction are still not available in the real estate field. After the covid pandemic, there has been a good amount of shortage of manpower in the real estate development sector. 2. The procurement of material was not easily available after the Covid pandemic which also severely affected the timeline of the project. The procurement of materials was very difficult as there was a shortage of mater…”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52000019312)

    Reason the builder gave MahaRERA:
    “Dear Maharera Authorities, I hope this email finds you well. We are writing to formally request a nine-month extension for our ongoing construction project Hiray’s Oleander having RERA registration no. P52000005407. The project is in the la…” Read the full reason“Dear Maharera Authorities, I hope this email finds you well. We are writing to formally request a nine-month extension for our ongoing construction project Hiray’s Oleander having RERA registration no. P52000005407. The project is in the last stage of construction. The project work is affected because of a shortage of skilled and unskilled labor. Also, we are facing delays in the procurement of the construction materials. The delays in construction material procurement is affecting our supply chain, hindering seamless progress. Even though we are facing issues in labour and material procure…”
  5. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT52000025653)

    Reason the builder gave MahaRERA:
    “Dear Sir/Madam, I, Mr. Jagannath D. Hiray, writing you regarding the extension for the project Hiray’s Oleander having RERA registration no. P52000005407 and extension application no. EXT52000025653. The project extension is required as the…” Read the full reason“Dear Sir/Madam, I, Mr. Jagannath D. Hiray, writing you regarding the extension for the project Hiray’s Oleander having RERA registration no. P52000005407 and extension application no. EXT52000025653. The project extension is required as the construction is in its final stage. We have already finished RCC works, brickwork and plaster, outer painting works, interior works like gypsum, bathroom and kitchen tiling, plumbing, flooring, fire pump room construction, etc. The only works which are pending are lift installation works, parking tiling works, and ground drainage works which are currentl…”
  6. 31 March 2026

    Extended at the builder's request (MahaRERA application EA27122519058)

    Reason the builder gave MahaRERA:
    “Respected Sir/Madam, I, Mr Jagannath D. Hiray, Promoter of the project “Hiray’s Oleander”, situated at Plot No. 179, Sector 23, Ulwe, Navi Mumbai, respectfully submit the following reasons for applying again on the MahaRERA portal along wit…” Read the full reason“Respected Sir/Madam, I, Mr Jagannath D. Hiray, Promoter of the project “Hiray’s Oleander”, situated at Plot No. 179, Sector 23, Ulwe, Navi Mumbai, respectfully submit the following reasons for applying again on the MahaRERA portal along with the updated CPM schedule. At present, the project construction is fully completed in all respects, including RCC structure, masonry, plaster, internal finishes, flooring, plumbing, electrical works, lifts installation, compound wall, parking, and all allied development works. The only approval presently pending is the Fire Department NOC from the concer…”
  7. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: HIRAYS OLEANDER’s extension records on MahaRERA (P52000005407), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HIRAYS OLEANDER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000005407
Status
Lapsed (registration period ended)
Builder
JAGANNATH DASHARATH HIRAY
Location
Navi Mumbai, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
11 Aug 2017
Completion date at registration
June 2021
Latest completion date
July 2026
Delay so far
57 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
44
Sold or booked
30%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of HIRAYS OLEANDER, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HIRAYS OLEANDER100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • HIRAYS OLEANDER: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HIRAYS OLEANDER every month.

HIRAYS OLEANDER: buildings, flats and land, as filed on MahaRERA

  • Buildings: HIRAYS OLEANDER (16 floors, 44 units)
  • Car parking: 18 covered, 1 open
  • Land: 998 sq m (about 0.2 acres) · sanctioned built-up 1,496 sq m

The builder’s record and reviews

Jagannath Dasharath Hiray has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of HIRAYS OLEANDER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HIRAYS OLEANDER: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HIRAYS OLEANDER

What is the possession date of HIRAYS OLEANDER?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HIRAYS OLEANDER in Navi Mumbai, Raigarh is 31 July 2026 — 57 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for HIRAYS OLEANDER?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HIRAYS OLEANDER's builder has filed on MahaRERA, the official one, is 31 July 2026, already 57 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HIRAYS OLEANDER extended?

According to GharKundli's check of MahaRERA records (updated October 2026), HIRAYS OLEANDER's builder applied to MahaRERA to extend the completion date 5 times: to 31 December 2022, giving the reason "We had applied for the plinth completion certificate on 31/08/2018. We have received the plinth completion certificate on 30/09/2020. The reason behind this delay is there was some issue with regards to the Maveja in CIDCO as CIDCO is the approving authority for all the permissions. Because of which the process was stopped in CIDCO due to this issue. Also, due to COVID Pandemic, there was a significant addition in the delay to obtain the plinth completion certificate. So, we request you to extend the date of completion of this project till December 2024 as there are more challenges with reg…"; to 31 March 2024, giving the reason "Dear Team, We want to apply for an extension due to the delay caused because of shortage of labor after the covid lockdown and the strike of material suppliers. 1. The labor resources required for construction are still not available in the real estate field. After the covid pandemic, there has been a good amount of shortage of manpower in the real estate development sector. 2. The procurement of material was not easily available after the Covid pandemic which also severely affected the timeline of the project. The procurement of materials was very difficult as there was a shortage of mater…"; to 31 December 2024, giving the reason "Dear Maharera Authorities, I hope this email finds you well. We are writing to formally request a nine-month extension for our ongoing construction project Hiray’s Oleander having RERA registration no. P52000005407. The project is in the last stage of construction. The project work is affected because of a shortage of skilled and unskilled labor. Also, we are facing delays in the procurement of the construction materials. The delays in construction material procurement is affecting our supply chain, hindering seamless progress. Even though we are facing issues in labour and material procure…"; to 31 December 2025, giving the reason "Dear Sir/Madam, I, Mr. Jagannath D. Hiray, writing you regarding the extension for the project Hiray’s Oleander having RERA registration no. P52000005407 and extension application no. EXT52000025653. The project extension is required as the construction is in its final stage. We have already finished RCC works, brickwork and plaster, outer painting works, interior works like gypsum, bathroom and kitchen tiling, plumbing, flooring, fire pump room construction, etc. The only works which are pending are lift installation works, parking tiling works, and ground drainage works which are currentl…"; to 31 March 2026, giving the reason "Respected Sir/Madam, I, Mr Jagannath D. Hiray, Promoter of the project “Hiray’s Oleander”, situated at Plot No. 179, Sector 23, Ulwe, Navi Mumbai, respectfully submit the following reasons for applying again on the MahaRERA portal along with the updated CPM schedule. At present, the project construction is fully completed in all respects, including RCC structure, masonry, plaster, internal finishes, flooring, plumbing, electrical works, lifts installation, compound wall, parking, and all allied development works. The only approval presently pending is the Fire Department NOC from the concer…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of HIRAYS OLEANDER?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HIRAYS OLEANDER in Navi Mumbai, Raigarh is P52000005407.

Is HIRAYS OLEANDER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HIRAYS OLEANDER is registered as P52000005407 and its status is "Lapsed (registration period ended)".

What is the construction status of HIRAYS OLEANDER?

According to GharKundli's check of MahaRERA records (updated October 2026), HIRAYS OLEANDER's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on HIRAYS OLEANDER is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does HIRAYS OLEANDER have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is HIRAYS OLEANDER safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), HIRAYS OLEANDER is registered on MahaRERA as P52000005407, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 57 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HIRAYS OLEANDER's possession date changes?

The latest dates are on HIRAYS OLEANDER's MahaRERA page (P52000005407). GharKundli's Kundli Watch sends a free WhatsApp update on HIRAYS OLEANDER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HIRAYS OLEANDER have?

According to GharKundli's check of MahaRERA records (updated October 2026), HIRAYS OLEANDER has one building filed: HIRAYS OLEANDER with 16 floors and 44 units.

How much parking does HIRAYS OLEANDER have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered and 1 open car parking spaces for HIRAYS OLEANDER.

How big is the land of HIRAYS OLEANDER?

According to GharKundli's check of MahaRERA records (updated October 2026), HIRAYS OLEANDER stands on 998 sq m of land (about 0.2 acres), with 1,496 sq m of sanctioned built-up area.

What is the track record of HIRAYS OLEANDER's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Jagannath Dasharath Hiray has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of HIRAYS OLEANDER?

Google Maps has reviews of HIRAYS OLEANDER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HIRAYS OLEANDER?

HIRAYS OLEANDER by JAGANNATH DASHARATH HIRAY is in Navi Mumbai, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000005407, per GharKundli's check of MahaRERA records.

How many homes are in HIRAYS OLEANDER?

According to GharKundli's check of MahaRERA records (updated October 2026), HIRAYS OLEANDER has 44 homes in 1 tower registered on MahaRERA, and 30% of them are sold or booked.

When was HIRAYS OLEANDER registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HIRAYS OLEANDER was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on HIRAYS OLEANDER?

No court cases are listed for HIRAYS OLEANDER on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of HIRAYS OLEANDER?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JAGANNATH DASHARATH HIRAY, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Raigad →

Other projects in Navi Mumbai

All 2,664 projects in Panvel (410206) →

Other projects by JAGANNATH DASHARATH HIRAY