by Agile Real Estate Pvt. Ltd. (Kalpataru) · Village Balkum, Thane

Possession date of Sector 5 - Wing G and H: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700020175, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sector 5 - Wing G and H?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sector 5 - Wing G and H has moved

  1. 30 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sector 5 - Wing G and H’s extension records on MahaRERA (P51700020175), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sector 5 - Wing G and H

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints and 2 court cases, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700020175
Status
Registered and active
Builder
Agile Real Estate Pvt. Ltd.
Location
Village Balkum, Thane · 400607
Project type
Residential / Group Housing
Registered on
29 Mar 2019
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
524
Sold or booked
63%
Towers
2
Complaints on MahaRERA
6
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
18

Construction progress of Sector 5 - Wing G and H, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing G100%100%35%8%
Wing H100%84%9%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sector 5 - Wing G and H every month.

Sector 5 - Wing G and H: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing G (47 floors) · Wing H (38 floors)
  • Land: 1,851 sq m (about 0.5 acres) · sanctioned built-up 29,617 sq m

The builder’s record and reviews

Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 84 GharKundli has checked: 49 finished, 45 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 372 complaints on MahaRERA across 51 projects.

Read Google reviews of Sector 5 - Wing G and H →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sector 5 - Wing G and H: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sector 5 - Wing G and H

What is the possession date of Sector 5 - Wing G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sector 5 - Wing G and H in Village Balkum, Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sector 5 - Wing G and H?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sector 5 - Wing G and H's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sector 5 - Wing G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sector 5 - Wing G and H in Village Balkum, Thane is P51700020175.

Is Sector 5 - Wing G and H registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sector 5 - Wing G and H is registered as P51700020175 and its status is "Registered and active".

What is the construction status of Sector 5 - Wing G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), Sector 5 - Wing G and H's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 84% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sector 5 - Wing G and H have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sector 5 - Wing G and H safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sector 5 - Wing G and H is registered on MahaRERA as P51700020175, its completion date has not been moved by the builder and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Sector 5 - Wing G and H have other wings or phases?

Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Sector 5 - Wing A (P51700020201, possession 30 Apr 2031); Sector 5 - Wing B (P51700020237, possession 30 Apr 2028); Sector 5 - Wing C (P51700020196, possession 30 Apr 2028); Sector 5 - Wing J and K (P51700020264, possession 30 Apr 2028); Sector B- Tower A and B (PR1332022500106, possession 31 Dec 2031). Check that your agreement names the registration of your own wing.

How can I get updates if Sector 5 - Wing G and H's possession date changes?

The latest dates are on Sector 5 - Wing G and H's MahaRERA page (P51700020175). GharKundli's Kundli Watch sends a free WhatsApp update on Sector 5 - Wing G and H every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sector 5 - Wing G and H have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sector 5 - Wing G and H has 2 buildings filed: Wing G with 47 floors; Wing H with 38 floors.

How big is the land of Sector 5 - Wing G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), Sector 5 - Wing G and H stands on 1,851 sq m of land (about 0.5 acres), with 29,617 sq m of sanctioned built-up area.

What is the track record of Sector 5 - Wing G and H's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 84 GharKundli has checked: 49 finished, 45 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 372 complaints on MahaRERA across 51 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sector 5 - Wing G and H?

Google Maps has reviews of Sector 5 - Wing G and H written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sector 5 - Wing G and H?

Sector 5 - Wing G and H by Agile Real Estate Pvt. Ltd. (Kalpataru) is in Village Balkum, Thane (pincode 400607), Maharashtra, and is registered on MahaRERA as P51700020175, per GharKundli's check of MahaRERA records.

How many homes are in Sector 5 - Wing G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), Sector 5 - Wing G and H has 524 homes in 2 towers registered on MahaRERA, and 63% of them are sold or booked.

When was Sector 5 - Wing G and H registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sector 5 - Wing G and H was registered on MahaRERA on 29 March 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Sector 5 - Wing G and H?

2 court cases are listed for Sector 5 - Wing G and H on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Sector 5 - Wing G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Agile Real Estate Pvt. Ltd., the company Kalpataru files this project under, which has 18 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Village Balkum

All 218 projects in Sandozbaugh (400607) →

Other projects by Agile Real Estate Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.