Sector 5 - Wing A
by Agile Real Estate Pvt. Ltd. (Kalpataru) · Village Balkum, ThaneAlso near Dhokali, Kolshet, Deccan Gymkhana
Possession date of Sector 5 - Wing A: 30 April 2031, moved from 30 December 2027 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700020201, and currently active. Its completion date has moved from December 2027 to April 2031: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sector 5 - Wing A?
How the possession date of Sector 5 - Wing A has moved
30 December 2027
Completion date given when the project was registered
30 December 2030
Extended at the builder's request (MahaRERA application EXT51700019818)
Reason the builder gave MahaRERA:
“At the time of filing of the application on MahaRERA portal, we have submitted the Project completion date as 30th December, 2027. We would like to inform you that after the registration of the Project, we have made certain amendments and m…” Read the full reason
“At the time of filing of the application on MahaRERA portal, we have submitted the Project completion date as 30th December, 2027. We would like to inform you that after the registration of the Project, we have made certain amendments and modifications in the existing sanctioned plans of the Project in compliance with the applicable laws and rules/regulations made thereunder. The construction of the Project is yet to be commenced. We would further like to inform you that we have sold only one apartment in the Project and consent of the allottee of the said apartment has been obtained on 13t…”30 April 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sector 5 - Wing A’s extension records on MahaRERA (P51700020201), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sector 5 - Wing A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the April 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Sector 5 - Wing BP51700020237 · possession 30 Apr 2028
- Sector 5 - Wing CP51700020196 · possession 30 Apr 2028
- Sector 5 - Wing G and HP51700020175 · possession 30 Apr 2028
- Sector 5 - Wing J and KP51700020264 · possession 30 Apr 2028
- Sector B- Tower A and BPR1332022500106 · possession 31 Dec 2031
- MahaRERA registration
- P51700020201
- Status
- Registered and active
- Builder
- Agile Real Estate Pvt. Ltd.
- Location
- Village Balkum, Thane · 400607
- Project type
- Residential / Group Housing
- Registered on
- 29 Mar 2019
- Completion date at registration
- December 2027
- Latest completion date
- April 2031
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 319
- Sold or booked
- 18%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 18
Construction progress of Sector 5 - Wing A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sector 5 - Wing A every month.
Sector 5 - Wing A: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A (53 floors)
- Land: 1,210 sq m (about 0.3 acres) · sanctioned built-up 20,688 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 90 GharKundli has checked: 55 finished, 51 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 385 complaints on MahaRERA across 56 projects.
Read Google reviews of Sector 5 - Wing A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sector 5 - Wing A: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sector 5 - Wing A
What is the possession date of Sector 5 - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sector 5 - Wing A in Village Balkum, Thane is 30 April 2031 — 36 months later than 30 December 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sector 5 - Wing A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sector 5 - Wing A's builder has filed on MahaRERA, the official one, is 30 April 2031, already 36 months later than the 30 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sector 5 - Wing A extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sector 5 - Wing A's builder applied to MahaRERA to extend the completion date once: to 30 December 2030, giving the reason "At the time of filing of the application on MahaRERA portal, we have submitted the Project completion date as 30th December, 2027. We would like to inform you that after the registration of the Project, we have made certain amendments and modifications in the existing sanctioned plans of the Project in compliance with the applicable laws and rules/regulations made thereunder. The construction of the Project is yet to be commenced. We would further like to inform you that we have sold only one apartment in the Project and consent of the allottee of the said apartment has been obtained on 13t…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sector 5 - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sector 5 - Wing A in Village Balkum, Thane is P51700020201.
Is Sector 5 - Wing A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sector 5 - Wing A is registered as P51700020201 and its status is "Registered and active".
What is the construction status of Sector 5 - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), Sector 5 - Wing A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Sector 5 - Wing A have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sector 5 - Wing A safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sector 5 - Wing A is registered on MahaRERA as P51700020201, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Sector 5 - Wing A have other wings or phases?
Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Sector 5 - Wing B (P51700020237, possession 30 Apr 2028); Sector 5 - Wing C (P51700020196, possession 30 Apr 2028); Sector 5 - Wing G and H (P51700020175, possession 30 Apr 2028); Sector 5 - Wing J and K (P51700020264, possession 30 Apr 2028); Sector B- Tower A and B (PR1332022500106, possession 31 Dec 2031). Check that your agreement names the registration of your own wing.
How can I get updates if Sector 5 - Wing A's possession date changes?
The latest dates are on Sector 5 - Wing A's MahaRERA page (P51700020201). GharKundli's Kundli Watch sends a free WhatsApp update on Sector 5 - Wing A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sector 5 - Wing A have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sector 5 - Wing A has one building filed: Wing A with 53 floors.
How big is the land of Sector 5 - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), Sector 5 - Wing A stands on 1,210 sq m of land (about 0.3 acres), with 20,688 sq m of sanctioned built-up area.
What is the track record of Sector 5 - Wing A's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 90 GharKundli has checked: 55 finished, 51 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 385 complaints on MahaRERA across 56 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sector 5 - Wing A?
Google Maps has reviews of Sector 5 - Wing A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sector 5 - Wing A?
Sector 5 - Wing A by Agile Real Estate Pvt. Ltd. (Kalpataru) is in Village Balkum, Thane (pincode 400607), near Dhokali, Kolshet, Deccan Gymkhana, Maharashtra, and is registered on MahaRERA as P51700020201, per GharKundli's check of MahaRERA records.
How many homes are in Sector 5 - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), Sector 5 - Wing A has 319 homes in 1 tower registered on MahaRERA, and 18% of them are sold or booked.
When was Sector 5 - Wing A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sector 5 - Wing A was registered on MahaRERA on 29 March 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Sector 5 - Wing A?
2 court cases are listed for Sector 5 - Wing A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Sector 5 - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Agile Real Estate Pvt. Ltd., the company Kalpataru files this project under, which has 18 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sector 5 - Wing A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Thane →
Other projects in Village Balkum
- Sector B- Tower A and B
- Sector 5 - Wing B
- Sector 5 - Wing C
- Sector 5 - Wing G and H
- Sector 5 - Wing J and K
Other projects by Agile Real Estate Pvt. Ltd.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.