The Imperial I
by SDC TOWNSHIP PRIVATE LIMITED · Tardeo, MumbaiAlso near Malabar Hill, mumbai central, Malabar Cumballa Hill
Possession date of The Imperial I: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900050473, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about The Imperial I?
How the possession date of The Imperial I has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: The Imperial I’s extension records on MahaRERA (P51900050473), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Imperial I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900050473
- Status
- Registered and active
- Builder
- SDC TOWNSHIP PRIVATE LIMITED
- Location
- Tardeo, Mumbai · 400034
- Project type
- Residential / Group Housing
- Registered on
- 17 Apr 2023
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 109
- Sold or booked
- 35%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of The Imperial I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| The Imperial I | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- The Imperial I: covers top of 22nd Habbitable floor
Latest CC order on MahaRERA: dated 20/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Imperial I every month.
The Imperial I: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 4 BHK | 1,776 – 2,593 | 81 |
| 3 BHK | 1,610 | 15 |
| Shops | 1,382 | 9 |
| 5 BHK | 3,343 – 4,436 | 7 |
| 6 BHK | 3,192 – 4,768 | 6 |
- Buildings: The Imperial I (58 floors, 118 units)
- Car parking: 308 covered
- Land: 10,122 sq m (about 2.5 acres) · sanctioned built-up 26,452 sq m · recreational space 786 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of The Imperial I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Imperial I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about The Imperial I
What is the possession date of The Imperial I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Imperial I in Tardeo, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for The Imperial I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Imperial I's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of The Imperial I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Imperial I in Tardeo, Mumbai is P51900050473.
Is The Imperial I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Imperial I is registered as P51900050473 and its status is "Registered and active".
What is the construction status of The Imperial I?
According to GharKundli's check of MahaRERA records (updated October 2026), The Imperial I's status on MahaRERA is "Registered and active". As filed by the builder, slab work on The Imperial I is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does The Imperial I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is The Imperial I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), The Imperial I is registered on MahaRERA as P51900050473, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if The Imperial I's possession date changes?
The latest dates are on The Imperial I's MahaRERA page (P51900050473). GharKundli's Kundli Watch sends a free WhatsApp update on The Imperial I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Imperial I have?
According to GharKundli's check of MahaRERA records (updated October 2026), The Imperial I has one building filed: The Imperial I with 58 floors and 118 units.
What are the flat sizes (carpet area) in The Imperial I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for The Imperial I: 4 BHK: 1776 to 2593 sq ft carpet (81 homes); 3 BHK: 1610 sq ft carpet (15 homes); 5 BHK: 3343 to 4436 sq ft carpet (7 homes); 6 BHK: 3192 to 4768 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does The Imperial I have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 308 covered car parking spaces for The Imperial I.
How big is the land of The Imperial I?
According to GharKundli's check of MahaRERA records (updated October 2026), The Imperial I stands on 10,122 sq m of land (about 2.5 acres), with 26,452 sq m of sanctioned built-up area and 786 sq m of recreational open space.
Where can I read reviews of The Imperial I?
Google Maps has reviews of The Imperial I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is The Imperial I?
The Imperial I by SDC TOWNSHIP PRIVATE LIMITED is in Tardeo, Mumbai (pincode 400034), near Malabar Hill, mumbai central, Malabar Cumballa Hill, Maharashtra, and is registered on MahaRERA as P51900050473, per GharKundli's check of MahaRERA records.
How many homes are in The Imperial I?
According to GharKundli's check of MahaRERA records (updated October 2026), The Imperial I has 109 homes in 1 tower registered on MahaRERA, and 35% of them are sold or booked.
When was The Imperial I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Imperial I was registered on MahaRERA on 17 April 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on The Imperial I?
No court cases are listed for The Imperial I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of The Imperial I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SDC TOWNSHIP PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of The Imperial I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai City →
Other projects in Tardeo
- RAHEJA SOBO RESIDENCES
- 25 Downtown-Wing 5-Amber Oasis
- Aplite Sapphire
- 25 Downtown – The Galleria
- Imperial T3 Wing C1
- Marq
- Imperial T3 Wing C
- 25 Downtown-Wing 1-Emerald Palm
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.