Skip to content
GharKundli

25 Downtown-Wing 5-Amber Oasis

by TWENTY FIVE DOWNTOWN REALTY LIMITED · Tardeo, MumbaiAlso near agripada, Mahalaxmi, Byculla

Possession date of 25 Downtown-Wing 5-Amber Oasis: 30 April 2036. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1170002502282, and currently active. Its completion date is now April 2036, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about 25 Downtown-Wing 5-Amber Oasis?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 25 Downtown-Wing 5-Amber Oasis has moved

  1. 31 December 2035

    Completion date given when the project was registered

  2. 30 April 2036

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: 25 Downtown-Wing 5-Amber Oasis’s extension records on MahaRERA (PR1170002502282), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 25 Downtown-Wing 5-Amber Oasis

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2036 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1170002502282
Status
Registered and active
Builder
TWENTY FIVE DOWNTOWN REALTY LIMITED
Location
Tardeo, Mumbai · 400034
Project type
Residential / Group Housing
Registered on
6 Feb 2026
Completion date at registration
December 2035
Latest completion date
April 2036
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
34
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of 25 Downtown-Wing 5-Amber Oasis, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing - 50%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing - 5: covers PLINTH

Latest CC order on MahaRERA: dated 13/07/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 25 Downtown-Wing 5-Amber Oasis every month.

25 Downtown-Wing 5-Amber Oasis: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other10,05428
4 BHK6,6786

The builder’s record and reviews

Rare Townships (a group of 2 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 15 finished, 4 within the promised date and 11 needed more time (typically 6 months); 8 still being built, none past the promised date yet. 219 complaints on MahaRERA across 18 projects.

Read Google reviews of 25 Downtown-Wing 5-Amber Oasis →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

25 Downtown-Wing 5-Amber Oasis: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 25 Downtown-Wing 5-Amber Oasis

What is the possession date of 25 Downtown-Wing 5-Amber Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 25 Downtown-Wing 5-Amber Oasis in Tardeo, Mumbai is 30 April 2036, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for 25 Downtown-Wing 5-Amber Oasis?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 25 Downtown-Wing 5-Amber Oasis's builder has filed on MahaRERA, the official one, is 30 April 2036, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of 25 Downtown-Wing 5-Amber Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 25 Downtown-Wing 5-Amber Oasis in Tardeo, Mumbai is PR1170002502282.

Is 25 Downtown-Wing 5-Amber Oasis registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 25 Downtown-Wing 5-Amber Oasis is registered as PR1170002502282 and its status is "Registered and active".

What is the construction status of 25 Downtown-Wing 5-Amber Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), 25 Downtown-Wing 5-Amber Oasis's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing - 5 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does 25 Downtown-Wing 5-Amber Oasis have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is 25 Downtown-Wing 5-Amber Oasis safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), 25 Downtown-Wing 5-Amber Oasis is registered on MahaRERA as PR1170002502282, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 25 Downtown-Wing 5-Amber Oasis's possession date changes?

The latest dates are on 25 Downtown-Wing 5-Amber Oasis's MahaRERA page (PR1170002502282). GharKundli's Kundli Watch sends a free WhatsApp update on 25 Downtown-Wing 5-Amber Oasis every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 25 Downtown-Wing 5-Amber Oasis have?

According to GharKundli's check of MahaRERA records (updated October 2026), 25 Downtown-Wing 5-Amber Oasis has one building filed: Wing - 5 with 52 floors and 34 units.

What are the flat sizes (carpet area) in 25 Downtown-Wing 5-Amber Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for 25 Downtown-Wing 5-Amber Oasis: Other: 10054 sq ft carpet (28 homes); 4 BHK: 6678 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does 25 Downtown-Wing 5-Amber Oasis have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 125 covered car parking spaces for 25 Downtown-Wing 5-Amber Oasis.

How big is the land of 25 Downtown-Wing 5-Amber Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), 25 Downtown-Wing 5-Amber Oasis stands on 74,537 sq m of land (about 18.4 acres), with 38,571 sq m of sanctioned built-up area.

What is the track record of 25 Downtown-Wing 5-Amber Oasis's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rare Townships (a group of 2 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 15 finished, 4 within the promised date and 11 needed more time (typically 6 months); 8 still being built, none past the promised date yet. 219 complaints on MahaRERA across 18 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of 25 Downtown-Wing 5-Amber Oasis?

Google Maps has reviews of 25 Downtown-Wing 5-Amber Oasis written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 25 Downtown-Wing 5-Amber Oasis?

25 Downtown-Wing 5-Amber Oasis by TWENTY FIVE DOWNTOWN REALTY LIMITED is in Tardeo, Mumbai (pincode 400034), near agripada, Mahalaxmi, Byculla, Maharashtra, and is registered on MahaRERA as PR1170002502282, per GharKundli's check of MahaRERA records.

How many homes are in 25 Downtown-Wing 5-Amber Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), 25 Downtown-Wing 5-Amber Oasis has 34 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was 25 Downtown-Wing 5-Amber Oasis registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 25 Downtown-Wing 5-Amber Oasis was registered on MahaRERA on 6 February 2026. GharKundli did not find a title report on the land on file there.

Are there court cases on 25 Downtown-Wing 5-Amber Oasis?

No court cases are listed for 25 Downtown-Wing 5-Amber Oasis on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of 25 Downtown-Wing 5-Amber Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TWENTY FIVE DOWNTOWN REALTY LIMITED, which has 5 other projects registered on MahaRERA.

Other projects in Tardeo

All 19 projects in Tardeo (400034) →

Other projects by TWENTY FIVE DOWNTOWN REALTY LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.