Prannav Developers Project Sarodarshan

by PRANNAV DEVELOPERS · Naupada, Thane 400602

What’s in the report? →

Possession date of Prannav Developers Project Sarodarshan (MahaRERA P51700021978): 15 June 2026, moved from 30 June 2023 (36 months later), and it has already passed. It has 13 homes, 38% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700021978. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700021978, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about Prannav Developers Project Sarodarshan?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Prannav Developers Project Sarodarshan has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 29 June 2024

    Extended at the builder's request (MahaRERA application EXT51700015315)

    Reason the builder gave MahaRERA:
    “During Covid-19 lockdown period & post lockdown period, we faced many difficulties like financial crunches, shortage of labour etc. Also, due to coming into effect of the new rules, we had to take amended approval of the project as per UDCP…” Read the full reason“During Covid-19 lockdown period & post lockdown period, we faced many difficulties like financial crunches, shortage of labour etc. Also, due to coming into effect of the new rules, we had to take amended approval of the project as per UDCPR due to which the construction of the buildings slowed down & the project completion got delayed.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51700019634)

    Reason the builder gave MahaRERA:
    “Our plot is located at the junction of two 18 mt wide D P roads. The said locality is very busy & adjoining M H High school which restricted our working hours. There was a road set back of 194.98 sq.mt. area affecting our plot & was handed…” Read the full reason“Our plot is located at the junction of two 18 mt wide D P roads. The said locality is very busy & adjoining M H High school which restricted our working hours. There was a road set back of 194.98 sq.mt. area affecting our plot & was handed over to TMC. TMC had put a condition on us in the permission certificate dtd. 27.03.2018, that the road set back area should be transferred in the name of TMC & separate P R cards of the same should be generated through City Survey Dept & to be submitted to TMC before obtaining plinth certificate of Bldg A/B. We started the procedure by submitting registe…”
  4. 15 June 2026

    Extended at the builder's request (MahaRERA application EA22012619538)

    Reason the builder gave MahaRERA:
    “Project was completed and application to TMC for OC was done before the rera completion date. OC Approval process took 2 months & on 04.09.25 OC was granted. Therefore, we had applied to extend the completion date till OC date so that we co…” Read the full reason“Project was completed and application to TMC for OC was done before the rera completion date. OC Approval process took 2 months & on 04.09.25 OC was granted. Therefore, we had applied to extend the completion date till OC date so that we could proceed for completion update. But, we have been now suggested to extend the completion date even further from the extension proposal application to cover up the days required for further corrections & completion update. So, for safer side, we want to extend the date till mid-June as the scrutiny takes much longer than expected. Kindly consider.”

Source: Prannav Developers Project Sarodarshan’s extension records on MahaRERA (P51700021978), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Prannav Developers Project Sarodarshan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700021978
Status
Lapsed (registration period ended)
Builder
PRANNAV DEVELOPERS
Location
Naupada, Thane · 400602
Project type
Mixed
Registered on
25 Aug 2019
Completion date at registration
June 2023
Latest completion date
June 2026
Delay so far
36 months
Homes
13
Sold or booked
38%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Prannav Developers Project Sarodarshan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A100%100%100%100%
BUILDING B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING A: covers Ground + 7 Floors
  • BUILDING B: covers Ground + 7 Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prannav Developers Project Sarodarshan every 1–2 months.

Prannav Developers Project Sarodarshan: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A (8 floors, 19 units) · BUILDING B (8 floors, 20 units)
  • Car parking: 37 covered
  • Land: 1,112 sq m (about 0.3 acres) · sanctioned built-up 1,986 sq m
  • Land, as filed: C.S.NO. 13/A
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Prannav Developers Project Sarodarshan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Prannav Developers Project Sarodarshan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Prannav Developers Project Sarodarshan

What is the possession date of Prannav Developers Project Sarodarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Prannav Developers Project Sarodarshan in Naupada, Thane is 15 June 2026 — 36 months later than 30 June 2023, the date given at registration. That date has already passed.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Prannav Developers Project Sarodarshan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Prannav Developers Project Sarodarshan's builder has filed on MahaRERA, the official one, is 15 June 2026, already 36 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Prannav Developers Project Sarodarshan extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan's builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2024, giving the reason "During Covid-19 lockdown period & post lockdown period, we faced many difficulties like financial crunches, shortage of labour etc. Also, due to coming into effect of the new rules, we had to take amended approval of the project as per UDCPR due to which the construction of the buildings slowed down & the project completion got delayed."; to 30 June 2025, giving the reason "Our plot is located at the junction of two 18 mt wide D P roads. The said locality is very busy & adjoining M H High school which restricted our working hours. There was a road set back of 194.98 sq.mt. area affecting our plot & was handed over to TMC. TMC had put a condition on us in the permission certificate dtd. 27.03.2018, that the road set back area should be transferred in the name of TMC & separate P R cards of the same should be generated through City Survey Dept & to be submitted to TMC before obtaining plinth certificate of Bldg A/B. We started the procedure by submitting registe…"; to 15 June 2026, giving the reason "Project was completed and application to TMC for OC was done before the rera completion date. OC Approval process took 2 months & on 04.09.25 OC was granted. Therefore, we had applied to extend the completion date till OC date so that we could proceed for completion update. But, we have been now suggested to extend the completion date even further from the extension proposal application to cover up the days required for further corrections & completion update. So, for safer side, we want to extend the date till mid-June as the scrutiny takes much longer than expected. Kindly consider.".

What is the RERA number of Prannav Developers Project Sarodarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Prannav Developers Project Sarodarshan in Naupada, Thane is P51700021978.

Is Prannav Developers Project Sarodarshan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan is registered as P51700021978 and its status is "Lapsed (registration period ended)".

What is the current construction status of Prannav Developers Project Sarodarshan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Prannav Developers Project Sarodarshan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Prannav Developers Project Sarodarshan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan is registered on MahaRERA as P51700021978, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Prannav Developers Project Sarodarshan?

Prannav Developers Project Sarodarshan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Prannav Developers Project Sarodarshan?

For a flat in Prannav Developers Project Sarodarshan (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Prannav Developers Project Sarodarshan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 15 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Prannav Developers Project Sarodarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (15 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Prannav Developers Project Sarodarshan a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan is a redevelopment: 11 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Prannav Developers Project Sarodarshan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Prannav Developers Project Sarodarshan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Prannav Developers Project Sarodarshan's possession date changes?

The latest dates are on Prannav Developers Project Sarodarshan's MahaRERA page (P51700021978). GharKundli's Kundli Watch sends a free WhatsApp update on Prannav Developers Project Sarodarshan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Prannav Developers Project Sarodarshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan has 2 buildings filed: BUILDING A with 8 floors and 19 units; BUILDING B with 8 floors and 20 units.

How much parking does Prannav Developers Project Sarodarshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 37 covered car parking spaces for Prannav Developers Project Sarodarshan.

How big is the land of Prannav Developers Project Sarodarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan stands on 1,112 sq m of land (about 0.3 acres), with 1,986 sq m of sanctioned built-up area.

What are the reviews of Prannav Developers Project Sarodarshan?

Google Maps has reviews of Prannav Developers Project Sarodarshan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Prannav Developers Project Sarodarshan?

Prannav Developers Project Sarodarshan by PRANNAV DEVELOPERS is in Naupada, Thane, pincode 400602, Maharashtra, and is registered on MahaRERA as P51700021978, per GharKundli's check of MahaRERA records. Its land is filed as C.S.NO. 13/A. GharKundli lists all 258 MahaRERA projects in Naupada (400602).

How many flats are in Prannav Developers Project Sarodarshan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan has 13 homes in 2 towers registered on MahaRERA, and 38% of them are sold or booked.

When was Prannav Developers Project Sarodarshan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prannav Developers Project Sarodarshan was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.

Does Prannav Developers Project Sarodarshan have any legal issues or court cases?

No court cases are listed for Prannav Developers Project Sarodarshan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Prannav Developers Project Sarodarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRANNAV DEVELOPERS.

All projects with possession due in 2026 in Thane →

Other projects in Naupada (400602)

All 258 projects in Naupada (400602) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.