by Sugee Developers Pvt. Ltd. · Worli, MumbaiAlso near Prabhadevi, Delisle Road

Possession date of Sea Krest: 30 April 2030, moved from 31 December 2027 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900051903, and currently active. Its completion date has moved from December 2027 to April 2030: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Sea Krest?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sea Krest has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EXT51900027387)

    Reason the builder gave MahaRERA: “Application is under section 7(3) of MahaRERA Act read with order 40/ 2022. Please find attached Chairperson MahaRERA order granting Extension upto 31.12.2029 vide Order RC 421 of 2025 SEA KREST Extension at Sr No. 13.”
  3. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sea Krest’s extension records on MahaRERA (P51900051903), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sea Krest

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900051903
Status
Registered and active
Builder
Sugee Developers Pvt. Ltd.
Location
Worli, Mumbai · 400030
Project type
Residential / Group Housing
Registered on
7 Jul 2023
Completion date at registration
December 2027
Latest completion date
April 2030
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Sea Krest, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sea Krest-Sale Building0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sea Krest every month.

Sea Krest: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sugee Developers (a group of 14 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 9 months); 11 still being built, none past the promised date yet; 4 lapsed. 5 complaints on MahaRERA across 4 projects.

Read Google reviews of Sea Krest →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sea Krest: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sea Krest

What is the possession date of Sea Krest?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sea Krest in Worli, Mumbai is 30 April 2030 — 24 months later than 31 December 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sea Krest?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sea Krest's builder has filed on MahaRERA, the official one, is 30 April 2030, already 24 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sea Krest extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sea Krest's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "Application is under section 7(3) of MahaRERA Act read with order 40/ 2022. Please find attached Chairperson MahaRERA order granting Extension upto 31.12.2029 vide Order RC 421 of 2025 SEA KREST Extension at Sr No. 13.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Sea Krest?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sea Krest in Worli, Mumbai is P51900051903.

Is Sea Krest registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sea Krest is registered as P51900051903 and its status is "Registered and active".

What is the construction status of Sea Krest?

According to GharKundli's check of MahaRERA records (updated October 2026), Sea Krest's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sea Krest-Sale Building is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Sea Krest have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sea Krest safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sea Krest is registered on MahaRERA as P51900051903, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sea Krest's possession date changes?

The latest dates are on Sea Krest's MahaRERA page (P51900051903). GharKundli's Kundli Watch sends a free WhatsApp update on Sea Krest every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sea Krest have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sea Krest has one building filed: Sea Krest-Sale Building with 36 floors.

How big is the land of Sea Krest?

According to GharKundli's check of MahaRERA records (updated October 2026), Sea Krest stands on 3,201 sq m of land (about 0.8 acres), with 6,867 sq m of sanctioned built-up area.

What is the track record of Sea Krest's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sugee Developers (a group of 14 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 9 months); 11 still being built, none past the promised date yet; 4 lapsed. 5 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sea Krest?

Google Maps has reviews of Sea Krest written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sea Krest?

Sea Krest by Sugee Developers Pvt. Ltd. is in Worli, Mumbai (pincode 400030), near Prabhadevi, Delisle Road, Maharashtra, and is registered on MahaRERA as P51900051903, per GharKundli's check of MahaRERA records. Its boundaries filed there include Dr Annie Besant Road.

How many homes are in Sea Krest?

According to GharKundli's check of MahaRERA records (updated October 2026), Sea Krest has 12 homes in 1 tower registered on MahaRERA.

When was Sea Krest registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sea Krest was registered on MahaRERA on 7 July 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Sea Krest?

No court cases are listed for Sea Krest on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Sea Krest?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sugee Developers Pvt. Ltd., which has 2 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai City →

Other projects in pincode 400030

All 10 projects in Worli (400030) →

Other projects by Sugee Developers Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.