REDEVELOPMENT PROJECT OF DAYAWANI CHAWL
by ANIL MURARILAL AGARWAL · parel, MumbaiAlso near Worli, Prabhadevi, Delisle Road
Possession date of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL: 31 December 2027, moved from 31 January 2021 (83 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900004866, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
How the possession date of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL has moved
31 January 2021
Completion date given when the project was registered
31 January 2022
Extended at the builder's request (MahaRERA application EXT51900010016)
Reason the builder gave MahaRERA:
“The work is 95% completed. The architect certificate stating the same is attached with the application. The delay is because of the pandemic condition which has created a lot many troubles in the flow of the project. Request you to kindly g…” Read the full reason
“The work is 95% completed. The architect certificate stating the same is attached with the application. The delay is because of the pandemic condition which has created a lot many troubles in the flow of the project. Request you to kindly grant us the extension for the period of one year.”31 July 2023
Extended at the builder's request (MahaRERA application EXT51900012239)
Reason the builder gave MahaRERA: “OC UNDER PROESS”
30 November 2025
Extended at the builder's request (MahaRERA application EXT51900017259)
Reason the builder gave MahaRERA: “OC pending”
31 December 2027
Extended at the builder's request (MahaRERA application EA17122518720)
Reason the builder gave MahaRERA: “Full OC pending (part oc received) Ammalgamtion of 2 CS number is pending”
Source: REDEVELOPMENT PROJECT OF DAYAWANI CHAWL’s extension records on MahaRERA (P51900004866), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on REDEVELOPMENT PROJECT OF DAYAWANI CHAWL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900004866
- Status
- Registered and active
- Builder
- ANIL MURARILAL AGARWAL
- Location
- parel, Mumbai · 400030
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- January 2021
- Latest completion date
- December 2027
- Delay so far
- 83 months
- Homes
- 20
- Sold or booked
- 50%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHARDA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SHARDA: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on REDEVELOPMENT PROJECT OF DAYAWANI CHAWL every month.
REDEVELOPMENT PROJECT OF DAYAWANI CHAWL: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 306 – 309 | 14 |
| 2 BHK | 586 – 626 | 6 |
| Shops | 96 | 1 |
| Other | 191 | 1 |
| Office Space | 133 | 1 |
- Buildings: SHARDA (17 floors, 23 units)
- Car parking: 6 covered
- Land: 226 sq m (about 0.1 acres) · sanctioned built-up 1,265 sq m
- Boundaries filed include: BHAGWANTRAO PARELKAR MARG, BHAGWANTRAO PARELKAR ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
REDEVELOPMENT PROJECT OF DAYAWANI CHAWL: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about REDEVELOPMENT PROJECT OF DAYAWANI CHAWL
What is the possession date of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for REDEVELOPMENT PROJECT OF DAYAWANI CHAWL in parel, Mumbai is 31 December 2027 — 83 months later than 31 January 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date REDEVELOPMENT PROJECT OF DAYAWANI CHAWL's builder has filed on MahaRERA, the official one, is 31 December 2027, already 83 months later than the 31 January 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), REDEVELOPMENT PROJECT OF DAYAWANI CHAWL's builder applied to MahaRERA to extend the completion date 4 times: to 31 January 2022, giving the reason "The work is 95% completed. The architect certificate stating the same is attached with the application. The delay is because of the pandemic condition which has created a lot many troubles in the flow of the project. Request you to kindly grant us the extension for the period of one year."; to 31 July 2023, giving the reason "OC UNDER PROESS"; to 30 November 2025, giving the reason "OC pending"; to 31 December 2027, giving the reason "Full OC pending (part oc received) Ammalgamtion of 2 CS number is pending".
What is the RERA number of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL in parel, Mumbai is P51900004866.
Is REDEVELOPMENT PROJECT OF DAYAWANI CHAWL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), REDEVELOPMENT PROJECT OF DAYAWANI CHAWL is registered as P51900004866 and its status is "Registered and active".
What is the construction status of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
According to GharKundli's check of MahaRERA records (updated October 2026), REDEVELOPMENT PROJECT OF DAYAWANI CHAWL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHARDA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does REDEVELOPMENT PROJECT OF DAYAWANI CHAWL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is REDEVELOPMENT PROJECT OF DAYAWANI CHAWL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), REDEVELOPMENT PROJECT OF DAYAWANI CHAWL is registered on MahaRERA as P51900004866, its completion date has moved 83 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if REDEVELOPMENT PROJECT OF DAYAWANI CHAWL's possession date changes?
The latest dates are on REDEVELOPMENT PROJECT OF DAYAWANI CHAWL's MahaRERA page (P51900004866). GharKundli's Kundli Watch sends a free WhatsApp update on REDEVELOPMENT PROJECT OF DAYAWANI CHAWL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does REDEVELOPMENT PROJECT OF DAYAWANI CHAWL have?
According to GharKundli's check of MahaRERA records (updated October 2026), REDEVELOPMENT PROJECT OF DAYAWANI CHAWL has one building filed: SHARDA with 17 floors and 23 units.
What are the flat sizes (carpet area) in REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for REDEVELOPMENT PROJECT OF DAYAWANI CHAWL: 1 BHK: 306 to 309 sq ft carpet (14 homes); 2 BHK: 586 to 626 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does REDEVELOPMENT PROJECT OF DAYAWANI CHAWL have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered car parking spaces for REDEVELOPMENT PROJECT OF DAYAWANI CHAWL.
How big is the land of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
According to GharKundli's check of MahaRERA records (updated October 2026), REDEVELOPMENT PROJECT OF DAYAWANI CHAWL stands on 226 sq m of land (about 0.1 acres), with 1,265 sq m of sanctioned built-up area.
Where can I read reviews of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
Google Maps has reviews of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
REDEVELOPMENT PROJECT OF DAYAWANI CHAWL by ANIL MURARILAL AGARWAL is in parel, Mumbai (pincode 400030), near Worli, Prabhadevi, Delisle Road, Maharashtra, and is registered on MahaRERA as P51900004866, per GharKundli's check of MahaRERA records. Its boundaries filed there include BHAGWANTRAO PARELKAR MARG, BHAGWANTRAO PARELKAR ROAD.
How many homes are in REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
According to GharKundli's check of MahaRERA records (updated October 2026), REDEVELOPMENT PROJECT OF DAYAWANI CHAWL has 20 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.
When was REDEVELOPMENT PROJECT OF DAYAWANI CHAWL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), REDEVELOPMENT PROJECT OF DAYAWANI CHAWL was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
No court cases are listed for REDEVELOPMENT PROJECT OF DAYAWANI CHAWL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ANIL MURARILAL AGARWAL.
Check it yourself on MahaRERA
- How to check the possession date of REDEVELOPMENT PROJECT OF DAYAWANI CHAWL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Mumbai City
- Privia Navkar
- THE CANVAS RESIDENCES - CANVAS 1, CANVAS 2, CANVAS 3
- Waterview
- Harsh Oasis
- AL AMIR APARTMENT
- Lodha Promina
- Lodha Sewri Project
- OJAS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.