TULIP APARTMENTS

by SPACE EDGE PROJECTS PVT LTD · Kalyan East, Thane

Possession date of TULIP APARTMENTS: 30 October 2026, moved from 30 December 2024 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700022565, and currently active. Its completion date has moved from December 2024 to October 2026: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about TULIP APARTMENTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TULIP APARTMENTS has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT51700025409)

    Reason the builder gave MahaRERA:
    “Reference : RERA Registration No. P51700022565 Subject : Permission / Approval from RERA for Extension of Date of Completion of the project named “TULIP APARTMENTS” With respect to the above-mentioned subject, I, Mr. Saurav Kedar, one of th…” Read the full reason“Reference : RERA Registration No. P51700022565 Subject : Permission / Approval from RERA for Extension of Date of Completion of the project named “TULIP APARTMENTS” With respect to the above-mentioned subject, I, Mr. Saurav Kedar, one of the director in Space Edge Projects Pvt Ltd, on behalf of the Company (Promoter) , would like to request you to extend the Proposed Date of Completion of ‘Tulip Project’ from 30th December, 2024 to 3oth December,¬2025. The delay in date of completion of the project is due to the following reasons – 1. Non-availability of skilled, semi-skilled and unskilled…”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EA02012619227)

    Reason the builder gave MahaRERA: “Delay in completion of external infrastructure / utility connections (water, drainage, electrical and other services) by local authorities, without which occupation certificate (OC) / building completion certificate (CC) cannot be obtained.”
  4. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: TULIP APARTMENTS’s extension records on MahaRERA (P51700022565), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TULIP APARTMENTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700022565
Status
Registered and active
Builder
SPACE EDGE PROJECTS PVT LTD
Location
Kalyan East, Thane · 421306
Project type
Others
Registered on
7 Oct 2019
Completion date at registration
December 2024
Latest completion date
October 2026
Delay so far
18 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
314
Sold or booked
37%
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of TULIP APARTMENTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BLDG 1100%100%100%0%
BLDG 2100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • BLDG 1: covers 24 floors
  • BLDG 2: covers 12 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TULIP APARTMENTS every month.

TULIP APARTMENTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: BLDG 1 (22 floors, 237 units) · BLDG 2 (12 floors, 94 units)
  • Land: 5,494 sq m (about 1.4 acres) · sanctioned built-up 5,620 sq m · recreational space 668 sq m

The builder’s record and reviews

Space Edge Projects has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of TULIP APARTMENTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TULIP APARTMENTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TULIP APARTMENTS

What is the possession date of TULIP APARTMENTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TULIP APARTMENTS in Kalyan East, Thane is 30 October 2026 — 18 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for TULIP APARTMENTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TULIP APARTMENTS's builder has filed on MahaRERA, the official one, is 30 October 2026, already 18 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TULIP APARTMENTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TULIP APARTMENTS's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "Reference : RERA Registration No. P51700022565 Subject : Permission / Approval from RERA for Extension of Date of Completion of the project named “TULIP APARTMENTS” With respect to the above-mentioned subject, I, Mr. Saurav Kedar, one of the director in Space Edge Projects Pvt Ltd, on behalf of the Company (Promoter) , would like to request you to extend the Proposed Date of Completion of ‘Tulip Project’ from 30th December, 2024 to 3oth December,¬2025. The delay in date of completion of the project is due to the following reasons – 1. Non-availability of skilled, semi-skilled and unskilled…"; to 30 June 2026, giving the reason "Delay in completion of external infrastructure / utility connections (water, drainage, electrical and other services) by local authorities, without which occupation certificate (OC) / building completion certificate (CC) cannot be obtained.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of TULIP APARTMENTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TULIP APARTMENTS in Kalyan East, Thane is P51700022565.

Is TULIP APARTMENTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TULIP APARTMENTS is registered as P51700022565 and its status is "Registered and active".

What is the construction status of TULIP APARTMENTS?

According to GharKundli's check of MahaRERA records (updated October 2026), TULIP APARTMENTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does TULIP APARTMENTS have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TULIP APARTMENTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TULIP APARTMENTS is registered on MahaRERA as P51700022565, its completion date has moved 18 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TULIP APARTMENTS's possession date changes?

The latest dates are on TULIP APARTMENTS's MahaRERA page (P51700022565). GharKundli's Kundli Watch sends a free WhatsApp update on TULIP APARTMENTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TULIP APARTMENTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), TULIP APARTMENTS has 2 buildings filed: BLDG 1 with 22 floors and 237 units; BLDG 2 with 12 floors and 94 units.

How big is the land of TULIP APARTMENTS?

According to GharKundli's check of MahaRERA records (updated October 2026), TULIP APARTMENTS stands on 5,494 sq m of land (about 1.4 acres), with 5,620 sq m of sanctioned built-up area and 668 sq m of recreational open space.

What is the track record of TULIP APARTMENTS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Space Edge Projects has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TULIP APARTMENTS?

Google Maps has reviews of TULIP APARTMENTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TULIP APARTMENTS?

TULIP APARTMENTS by SPACE EDGE PROJECTS PVT LTD is in Kalyan East, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700022565, per GharKundli's check of MahaRERA records.

How many homes are in TULIP APARTMENTS?

According to GharKundli's check of MahaRERA records (updated October 2026), TULIP APARTMENTS has 314 homes in 2 towers registered on MahaRERA, and 37% of them are sold or booked.

When was TULIP APARTMENTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TULIP APARTMENTS was registered on MahaRERA on 7 October 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on TULIP APARTMENTS?

No court cases are listed for TULIP APARTMENTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of TULIP APARTMENTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SPACE EDGE PROJECTS PVT LTD.

All projects with possession due in 2026 in Thane →