by GOPAL KRISHNA DEVELOPERS · Kalyan East, Thane

Possession date of KRISHNA SQUARE: 30 November 2027, moved from 31 July 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700013776, and currently active. Its completion date has moved from July 2023 to November 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about KRISHNA SQUARE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KRISHNA SQUARE has moved

  1. 31 July 2023

    Completion date given when the project was registered

  2. 30 July 2024

    Extended at the builder's request (MahaRERA application EXT51700017202)

    Reason the builder gave MahaRERA:
    “Respected Sir, We are applying for extension due to following reasons: a) Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis. b) Construction of Wing A is completed and we…” Read the full reason“Respected Sir, We are applying for extension due to following reasons: a) Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis. b) Construction of Wing A is completed and we have obtained completion certificate from Kalyan Dombivali Municipal Corporation dated 01.09.2018. Construction of Wing B is in process and we have obtained part occupancy certificate from Kalyan Dombivali Municipal Corporation dated 24.08.2022. c) Construction of Wing C is in process and will be handed over to Kalyan Dombivali Municipal Corporation. We r…”
  3. 30 July 2026

    Extended at the builder's request (MahaRERA application EXT51700025537)

    Reason the builder gave MahaRERA: “The delay was caused by unforeseen circumstances beyond our control. Despite our best efforts, we were unable to complete the project within the stipulated timeline. Therefore, we request an extension until 30 July 2026.”
  4. 31 July 2027

    Extended at the builder's request (MahaRERA application EA28072621902)

    Reason the builder gave MahaRERA:
    “The project could not be completed within the originally registered timeline due to a combination of unforeseen and practical challenges encountered during the course of execution. The construction activities were adversely affected by fluc…” Read the full reason“The project could not be completed within the originally registered timeline due to a combination of unforeseen and practical challenges encountered during the course of execution. The construction activities were adversely affected by fluctuations in the availability and cost of construction materials, shortage of skilled labour, and delays in the mobilization of contractors and other agencies involved in the project. These factors impacted the planned construction schedule and resulted in slower progress than originally anticipated. In addition, certain activities requiring coordination w…”
  5. 30 November 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: KRISHNA SQUARE’s extension records on MahaRERA (P51700013776), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KRISHNA SQUARE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700013776
Status
Registered and active
Builder
GOPAL KRISHNA DEVELOPERS
Location
Kalyan East, Thane · 421306
Project type
Others
Registered on
25 Oct 2017
Completion date at registration
July 2023
Latest completion date
November 2027
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
184
Sold or booked
70%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of KRISHNA SQUARE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%100%100%
WING B100%100%100%100%
WING C100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • WING A: covers Basement (P)Stilt (P) Ground (P)+1st Floor to 2nd Floor
  • WING B: covers Stilt+1st & 2nd level Parking+3rd to 29th floor
  • WING C: covers Stilt (p) Ground (p) +1st to 4th Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KRISHNA SQUARE every month.

KRISHNA SQUARE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Unspecified—198
1 BHK306 – 341108
Office Space95 – 1,30953
2 BHK126 – 50749
3 BHK120 – 56827
Shops159 – 39817
  • Buildings: WING A (4 floors, 218 units) · WING B (36 floors, 36 units) · WING C (6 floors)
  • Car parking: 75 covered
  • Land: 3,850 sq m (about 1.0 acres) · sanctioned built-up 2,965 sq m · recreational space 500 sq m

The builder’s record and reviews

Sonawane Infrastructure (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, all within the promised date; 5 still being built, 3 past the promised date (typically 13 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of KRISHNA SQUARE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KRISHNA SQUARE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KRISHNA SQUARE

What is the possession date of KRISHNA SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KRISHNA SQUARE in Kalyan East, Thane is 30 November 2027 — 48 months later than 31 July 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for KRISHNA SQUARE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KRISHNA SQUARE's builder has filed on MahaRERA, the official one, is 30 November 2027, already 48 months later than the 31 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KRISHNA SQUARE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SQUARE's builder applied to MahaRERA to extend the completion date 3 times: to 30 July 2024, giving the reason "Respected Sir, We are applying for extension due to following reasons: a) Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis. b) Construction of Wing A is completed and we have obtained completion certificate from Kalyan Dombivali Municipal Corporation dated 01.09.2018. Construction of Wing B is in process and we have obtained part occupancy certificate from Kalyan Dombivali Municipal Corporation dated 24.08.2022. c) Construction of Wing C is in process and will be handed over to Kalyan Dombivali Municipal Corporation. We r…"; to 30 July 2026, giving the reason "The delay was caused by unforeseen circumstances beyond our control. Despite our best efforts, we were unable to complete the project within the stipulated timeline. Therefore, we request an extension until 30 July 2026."; to 31 July 2027, giving the reason "The project could not be completed within the originally registered timeline due to a combination of unforeseen and practical challenges encountered during the course of execution. The construction activities were adversely affected by fluctuations in the availability and cost of construction materials, shortage of skilled labour, and delays in the mobilization of contractors and other agencies involved in the project. These factors impacted the planned construction schedule and resulted in slower progress than originally anticipated. In addition, certain activities requiring coordination w…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of KRISHNA SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KRISHNA SQUARE in Kalyan East, Thane is P51700013776.

Is KRISHNA SQUARE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SQUARE is registered as P51700013776 and its status is "Registered and active".

What is the construction status of KRISHNA SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SQUARE's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does KRISHNA SQUARE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is KRISHNA SQUARE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SQUARE is registered on MahaRERA as P51700013776, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KRISHNA SQUARE's possession date changes?

The latest dates are on KRISHNA SQUARE's MahaRERA page (P51700013776). GharKundli's Kundli Watch sends a free WhatsApp update on KRISHNA SQUARE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KRISHNA SQUARE have?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SQUARE has 3 buildings filed: WING A with 4 floors and 218 units; WING B with 36 floors and 36 units; WING C with 6 floors.

What are the flat sizes (carpet area) in KRISHNA SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for KRISHNA SQUARE: 1 BHK: 306 to 341 sq ft carpet (108 homes); 2 BHK: 126 to 507 sq ft carpet (49 homes); 3 BHK: 120 to 568 sq ft carpet (27 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does KRISHNA SQUARE have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 75 covered car parking spaces for KRISHNA SQUARE.

How big is the land of KRISHNA SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SQUARE stands on 3,850 sq m of land (about 1.0 acres), with 2,965 sq m of sanctioned built-up area and 500 sq m of recreational open space.

What is the track record of KRISHNA SQUARE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonawane Infrastructure (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, all within the promised date; 5 still being built, 3 past the promised date (typically 13 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of KRISHNA SQUARE?

Google Maps has reviews of KRISHNA SQUARE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KRISHNA SQUARE?

KRISHNA SQUARE by GOPAL KRISHNA DEVELOPERS is in Kalyan East, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700013776, per GharKundli's check of MahaRERA records.

How many homes are in KRISHNA SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SQUARE has 184 homes in 3 towers registered on MahaRERA, and 70% of them are sold or booked.

When was KRISHNA SQUARE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SQUARE was registered on MahaRERA on 25 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KRISHNA SQUARE?

No court cases are listed for KRISHNA SQUARE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of KRISHNA SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GOPAL KRISHNA DEVELOPERS, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan East

All 270 projects in Kalyan East (421306) →

Other projects by GOPAL KRISHNA DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.