Gopal Gaondevi Crown
by GOPAL KRISHNA DEVELOPERS · Kalyan East, Thane 421306Registered on MahaRERA as “Gaondevi Crown”
What’s in the report? →Possession date of Gopal Gaondevi Crown (MahaRERA P51700031502): 30 April 2027, moved from 31 March 2026 (9 months later). It has 168 homes, 67% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700031502, and currently active. Its completion date has moved from March 2026 to April 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700031502, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Gopal Gaondevi Crown?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Gopal Gaondevi Crown has moved
31 March 2026
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA24032620353)
Reason the builder gave MahaRERA:
“The project completion has been delayed due to circumstances beyond the control of the promoter. The project was adversely affected by delays in statutory approvals, disruption in availability of labor and construction materials, and interr…” Read the full reason
“The project completion has been delayed due to circumstances beyond the control of the promoter. The project was adversely affected by delays in statutory approvals, disruption in availability of labor and construction materials, and interruptions caused by external factors. In addition, unforeseen administrative and operational challenges impacted the planned construction schedule. Despite these difficulties, the promoter has continued construction activities and remains fully committed to completing the project at the earliest. The extension is sought to ensure timely completion with requ…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Gopal Gaondevi Crown’s extension records on MahaRERA (P51700031502), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gopal Gaondevi Crown
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700031502
- Status
- Registered and active
- Builder
- GOPAL KRISHNA DEVELOPERS
- Location
- Kalyan East, Thane · 421306
- Project type
- Others
- Registered on
- 25 Oct 2021
- Completion date at registration
- March 2026
- Latest completion date
- April 2027
- Delay so far
- 9 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 168
- Sold or booked
- 67%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Gopal Gaondevi Crown, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Gaondevi Crown | 100% | 100% | 68% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Gaondevi Crown: covers 22 floors
Latest CC order on MahaRERA: dated 26/09/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gopal Gaondevi Crown every 1–2 months.
Gopal Gaondevi Crown: buildings, flats and land, as filed on MahaRERA
- Buildings: Gaondevi Crown (22 floors, 168 units)
- Car parking: 71 covered
- Land: 2,600 sq m (about 0.6 acres) · sanctioned built-up 9,862 sq m · recreational space 313 sq m
- Boundaries filed include: Gaondevi Road
- Land, as filed: 48/2, 3
- Map: Get directions
The builder’s record and reviews
Sonawane Infrastructure (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, all within the promised date; 5 still being built, 3 past the promised date (typically 13 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Gopal Gaondevi Crown →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gopal Gaondevi Crown: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Gopal Gaondevi Crown
What is the possession date of Gopal Gaondevi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gopal Gaondevi Crown in Kalyan East, Thane is 30 April 2027 — 9 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 9 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Gopal Gaondevi Crown?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gopal Gaondevi Crown's builder has filed on MahaRERA, the official one, is 30 April 2027, already 9 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gopal Gaondevi Crown extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The project completion has been delayed due to circumstances beyond the control of the promoter. The project was adversely affected by delays in statutory approvals, disruption in availability of labor and construction materials, and interruptions caused by external factors. In addition, unforeseen administrative and operational challenges impacted the planned construction schedule. Despite these difficulties, the promoter has continued construction activities and remains fully committed to completing the project at the earliest. The extension is sought to ensure timely completion with requ…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Gopal Gaondevi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gopal Gaondevi Crown in Kalyan East, Thane is P51700031502.
Is Gopal Gaondevi Crown registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown is registered as P51700031502 and its status is "Registered and active".
What is the current construction status of Gopal Gaondevi Crown? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Gaondevi Crown is 100% done and internal work 68%. GharKundli's full report compares construction progress with the deadline.
Does Gopal Gaondevi Crown have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Gopal Gaondevi Crown safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown is registered on MahaRERA as P51700031502, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Gopal Gaondevi Crown?
Gopal Gaondevi Crown is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Gopal Gaondevi Crown?
For a flat in Gopal Gaondevi Crown (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Gopal Gaondevi Crown received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Gopal Gaondevi Crown uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Gopal Gaondevi Crown was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Gopal Gaondevi Crown's possession date changes?
The latest dates are on Gopal Gaondevi Crown's MahaRERA page (P51700031502). GharKundli's Kundli Watch sends a free WhatsApp update on Gopal Gaondevi Crown every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gopal Gaondevi Crown have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown has one building filed: Gaondevi Crown with 22 floors and 168 units.
How much parking does Gopal Gaondevi Crown have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 71 covered car parking spaces for Gopal Gaondevi Crown.
How big is the land of Gopal Gaondevi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown stands on 2,600 sq m of land (about 0.6 acres), with 9,862 sq m of sanctioned built-up area and 313 sq m of recreational open space.
What is the track record of Gopal Gaondevi Crown's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sonawane Infrastructure (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, all within the promised date; 5 still being built, 3 past the promised date (typically 13 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Gopal Gaondevi Crown?
Google Maps has reviews of Gopal Gaondevi Crown written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Gopal Gaondevi Crown?
Gopal Gaondevi Crown by GOPAL KRISHNA DEVELOPERS is in Kalyan East, Thane, pincode 421306, Maharashtra, and is registered on MahaRERA as P51700031502, per GharKundli's check of MahaRERA records. Its boundaries filed there include Gaondevi Road. Its land is filed as 48/2, 3. GharKundli lists all 270 MahaRERA projects in Kalyan East (421306).
How many flats are in Gopal Gaondevi Crown, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown has 168 homes in 1 tower registered on MahaRERA, and 67% of them are sold or booked.
When was Gopal Gaondevi Crown registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gopal Gaondevi Crown was registered on MahaRERA on 25 October 2021. GharKundli did not find a title report on the land on file there.
Does Gopal Gaondevi Crown have any legal issues or court cases?
No court cases are listed for Gopal Gaondevi Crown on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Gopal Gaondevi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GOPAL KRISHNA DEVELOPERS, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Gopal Gaondevi Crown
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan East (421306)
- Davakhar Elegance Phase II
- Krishna Anand
- Kohinoor Eden
- Royale Galaxy
- Kohinoor Eden B4
- Kohinoor Eden B5
- Kohinoor Eden Ph 2
- Vishnu Vertex
Other projects by GOPAL KRISHNA DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.