Davakhar Elegance Phase II

by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED · Kalyan East, Thane

Possession date of Davakhar Elegance Phase II: 29 April 2026, moved from 31 March 2024 (25 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700046008. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (April 2026) has passed.

What do you want to know about Davakhar Elegance Phase II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Davakhar Elegance Phase II has moved

  1. 31 March 2024

    Completion date given when the project was registered

  2. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51700019481)

    Reason the builder gave MahaRERA:
    “we could not complete the said project within stipulated period due to shortage of sand, inadequate labour supply and changes in policies. The finishing work, fire fighting NOC, electricity main line connection and solar work are yet to be…” Read the full reason“we could not complete the said project within stipulated period due to shortage of sand, inadequate labour supply and changes in policies. The finishing work, fire fighting NOC, electricity main line connection and solar work are yet to be completed. we request you to kindly grant extension till 31.03.2025”
  3. 31 March 2026

    Extended at the builder's request (MahaRERA application EA19052501176)

    Reason the builder gave MahaRERA:
    “We say that our project 80% completed in March-2025. However, we have sold 18 units till dated. Hence, there is an issue for cash flow for the project. There are some inquiries from customer for flats/shops and we are expecting the said inq…” Read the full reason“We say that our project 80% completed in March-2025. However, we have sold 18 units till dated. Hence, there is an issue for cash flow for the project. There are some inquiries from customer for flats/shops and we are expecting the said inquiries shall be converted into bookings. Considering this situation, we assure you that we shall complete the project by 31.03.2026 in all aspect. Hence, we want to apply for extension for 1 year till 31.03.2026.”
  4. 29 April 2026

    Extended at the builder's request (MahaRERA application EA19082622232)

    Reason the builder gave MahaRERA:
    “The project received its Occupancy Certificate (OC) on 29.04.2026. However, the approved project completion date was 31.03.2026. Since the completion date had already expired before the OC was received, the project has been marked as lapsed…” Read the full reason“The project received its Occupancy Certificate (OC) on 29.04.2026. However, the approved project completion date was 31.03.2026. Since the completion date had already expired before the OC was received, the project has been marked as lapsed, and the completion status is currently not getting updated. Therefore, we are applying for an extension of the project completion date in RERA to regularize the project status and update the completion details accordingly.”

Source: Davakhar Elegance Phase II’s extension records on MahaRERA (P51700046008), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Davakhar Elegance Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700046008
Status
Lapsed (registration period ended)
Builder
DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED
Location
Kalyan East, Thane · 421306
Project type
Others
Registered on
15 Jun 2022
Completion date at registration
March 2024
Latest completion date
April 2026
Delay so far
25 months
Homes
12
Sold or booked
47%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Davakhar Elegance Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building no 2100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Building no 2: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Davakhar Elegance Phase II every month.

Davakhar Elegance Phase II: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space766 – 88920
1 Room Kitchen434 – 46512
Shops438 – 5266
  • Buildings: Building no 2 (8 floors, 38 units)
  • Car parking: 42 covered
  • Land: 750 sq m (about 0.2 acres) · sanctioned built-up 3,091 sq m
  • Boundaries filed include: Kalyan- Malang Road

The builder’s record and reviews

Davakhar Infrastructure has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. 4 complaints on MahaRERA across 4 projects.

Read Google reviews of Davakhar Elegance Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Davakhar Elegance Phase II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Davakhar Elegance Phase II

What is the possession date of Davakhar Elegance Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Davakhar Elegance Phase II in Kalyan East, Thane is 29 April 2026 — 25 months later than 31 March 2024, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Davakhar Elegance Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Davakhar Elegance Phase II's builder has filed on MahaRERA, the official one, is 29 April 2026, already 25 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Davakhar Elegance Phase II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Elegance Phase II's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2025, giving the reason "we could not complete the said project within stipulated period due to shortage of sand, inadequate labour supply and changes in policies. The finishing work, fire fighting NOC, electricity main line connection and solar work are yet to be completed. we request you to kindly grant extension till 31.03.2025"; to 31 March 2026, giving the reason "We say that our project 80% completed in March-2025. However, we have sold 18 units till dated. Hence, there is an issue for cash flow for the project. There are some inquiries from customer for flats/shops and we are expecting the said inquiries shall be converted into bookings. Considering this situation, we assure you that we shall complete the project by 31.03.2026 in all aspect. Hence, we want to apply for extension for 1 year till 31.03.2026."; to 29 April 2026, giving the reason "The project received its Occupancy Certificate (OC) on 29.04.2026. However, the approved project completion date was 31.03.2026. Since the completion date had already expired before the OC was received, the project has been marked as lapsed, and the completion status is currently not getting updated. Therefore, we are applying for an extension of the project completion date in RERA to regularize the project status and update the completion details accordingly.".

What is the RERA number of Davakhar Elegance Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Davakhar Elegance Phase II in Kalyan East, Thane is P51700046008.

Is Davakhar Elegance Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Elegance Phase II is registered as P51700046008 and its status is "Lapsed (registration period ended)".

What is the construction status of Davakhar Elegance Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Elegance Phase II's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Building no 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Davakhar Elegance Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Davakhar Elegance Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Elegance Phase II is registered on MahaRERA as P51700046008, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Davakhar Elegance Phase II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: DAVAKHAR ELEGANCE (P51700016124, possession 31 Mar 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Davakhar Elegance Phase II's possession date changes?

The latest dates are on Davakhar Elegance Phase II's MahaRERA page (P51700046008). GharKundli's Kundli Watch sends a free WhatsApp update on Davakhar Elegance Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Davakhar Elegance Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Elegance Phase II has one building filed: Building no 2 with 8 floors and 38 units.

What are the flat sizes (carpet area) in Davakhar Elegance Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Davakhar Elegance Phase II: 1 Room Kitchen: 434 to 465 sq ft carpet (12 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Davakhar Elegance Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 42 covered car parking spaces for Davakhar Elegance Phase II.

How big is the land of Davakhar Elegance Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Elegance Phase II stands on 750 sq m of land (about 0.2 acres), with 3,091 sq m of sanctioned built-up area.

What is the track record of Davakhar Elegance Phase II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Infrastructure has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. 4 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Davakhar Elegance Phase II?

Google Maps has reviews of Davakhar Elegance Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Davakhar Elegance Phase II?

Davakhar Elegance Phase II by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED is in Kalyan East, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700046008, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kalyan- Malang Road.

How many homes are in Davakhar Elegance Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Elegance Phase II has 12 homes in 1 tower registered on MahaRERA, and 47% of them are sold or booked.

When was Davakhar Elegance Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Elegance Phase II was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Davakhar Elegance Phase II?

No court cases are listed for Davakhar Elegance Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Davakhar Elegance Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Kalyan East

All 270 projects in Kalyan East (421306) →

Other projects by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.