Davakhar Sereno Phase III
by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED · Adivali Dhokali, Thane
Possession date of Davakhar Sereno Phase III: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700077873, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Davakhar Sereno Phase III?
How the possession date of Davakhar Sereno Phase III has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Davakhar Sereno Phase III’s extension records on MahaRERA (P51700077873), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Davakhar Sereno Phase III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- DAVAKHAR SERENO PHASE IP51700077564 · possession 30 Apr 2030
- DAVAKHAR SERENO PHASE III BP51700080045 · possession 31 Jul 2030
- DAVAKHAR SERENO PHASE III CPR1332022601763 · possession 31 Dec 2030
- MahaRERA registration
- P51700077873
- Status
- Registered and active
- Builder
- DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED
- Location
- Adivali Dhokali, Thane · 421306
- Project type
- Others
- Registered on
- 7 Nov 2024
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 169
- Sold or booked
- 73%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Davakhar Sereno Phase III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Davakhar Sereno Phase III | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Davakhar Sereno Phase III every month.
Davakhar Sereno Phase III: buildings, flats and land, as filed on MahaRERA
- Buildings: Davakhar Sereno Phase III (13 floors)
- Car parking: 1 covered, 246 open
- Land: 4,970 sq m (about 1.2 acres) · sanctioned built-up 9,845 sq m
The builder’s record and reviews
Davakhar Infrastructure has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. 4 complaints on MahaRERA across 4 projects.
Read Google reviews of Davakhar Sereno Phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Davakhar Sereno Phase III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Davakhar Sereno Phase III
What is the possession date of Davakhar Sereno Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Davakhar Sereno Phase III in Adivali Dhokali, Thane is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Davakhar Sereno Phase III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Davakhar Sereno Phase III's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Davakhar Sereno Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Davakhar Sereno Phase III in Adivali Dhokali, Thane is P51700077873.
Is Davakhar Sereno Phase III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Sereno Phase III is registered as P51700077873 and its status is "Registered and active".
What is the construction status of Davakhar Sereno Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Sereno Phase III's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Davakhar Sereno Phase III is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Davakhar Sereno Phase III have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Davakhar Sereno Phase III safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Sereno Phase III is registered on MahaRERA as P51700077873, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Davakhar Sereno Phase III have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: DAVAKHAR SERENO PHASE I (P51700077564, possession 30 Apr 2030); DAVAKHAR SERENO PHASE III B (P51700080045, possession 31 Jul 2030); DAVAKHAR SERENO PHASE III C (PR1332022601763, possession 31 Dec 2030). Check that your agreement names the registration of your own wing.
How can I get updates if Davakhar Sereno Phase III's possession date changes?
The latest dates are on Davakhar Sereno Phase III's MahaRERA page (P51700077873). GharKundli's Kundli Watch sends a free WhatsApp update on Davakhar Sereno Phase III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Davakhar Sereno Phase III have?
According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Sereno Phase III has one building filed: Davakhar Sereno Phase III with 13 floors.
How much parking does Davakhar Sereno Phase III have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 246 open car parking spaces for Davakhar Sereno Phase III.
How big is the land of Davakhar Sereno Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Sereno Phase III stands on 4,970 sq m of land (about 1.2 acres), with 9,845 sq m of sanctioned built-up area.
What is the track record of Davakhar Sereno Phase III's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Infrastructure has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. 4 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Davakhar Sereno Phase III?
Google Maps has reviews of Davakhar Sereno Phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Davakhar Sereno Phase III?
Davakhar Sereno Phase III by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED is in Adivali Dhokali, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700077873, per GharKundli's check of MahaRERA records.
How many homes are in Davakhar Sereno Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Sereno Phase III has 169 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.
When was Davakhar Sereno Phase III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Davakhar Sereno Phase III was registered on MahaRERA on 7 November 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Davakhar Sereno Phase III?
No court cases are listed for Davakhar Sereno Phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Davakhar Sereno Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Davakhar Sereno Phase III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Thane →
Other projects in Ambarnath
- Mountain Serenity
- Mountain City Building No. 1
- Nature Vista Building - 1
- MIDTOWN B AND C WING
- SAI UNIVERSE
- MERY VILLA CHSL
- DATTATRAY RESIDENCY
- MAHADEV HEIGHTS
Other projects by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.