DATTATRAY RESIDENCY
by SHRI KRISHNA VASTU · Badlapur, ThaneAlso near Kulgaon
Possession date of DATTATRAY RESIDENCY: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700049960, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about DATTATRAY RESIDENCY?
How the possession date of DATTATRAY RESIDENCY has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: DATTATRAY RESIDENCY’s extension records on MahaRERA (P51700049960), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DATTATRAY RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700049960
- Status
- Registered and active
- Builder
- SHRI KRISHNA VASTU
- Location
- Badlapur, Thane · 421503
- Project type
- Others
- Registered on
- 6 Mar 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 168
- Sold or booked
- 19%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of DATTATRAY RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 90% | 90% | 0% |
| WING B | 0% | 0% | 0% | 0% |
| WING C | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 13 floors
- WING B: covers 2 floors
- WING C: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DATTATRAY RESIDENCY every month.
DATTATRAY RESIDENCY: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 317 | 134 |
| 1 Room Kitchen | 297 | 30 |
| 2 BHK | 413 | 4 |
- Buildings: WING A (15 floors, 128 units) · WING B (4 floors, 20 units) · WING C (4 floors, 20 units)
- Land: 6,580 sq m (about 1.6 acres) · sanctioned built-up 7,525 sq m · recreational space 632 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DATTATRAY RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DATTATRAY RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DATTATRAY RESIDENCY
What is the possession date of DATTATRAY RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DATTATRAY RESIDENCY in Badlapur, Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for DATTATRAY RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DATTATRAY RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of DATTATRAY RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DATTATRAY RESIDENCY in Badlapur, Thane is P51700049960.
Is DATTATRAY RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DATTATRAY RESIDENCY is registered as P51700049960 and its status is "Registered and active".
What is the construction status of DATTATRAY RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), DATTATRAY RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 90% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does DATTATRAY RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is DATTATRAY RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DATTATRAY RESIDENCY is registered on MahaRERA as P51700049960, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DATTATRAY RESIDENCY's possession date changes?
The latest dates are on DATTATRAY RESIDENCY's MahaRERA page (P51700049960). GharKundli's Kundli Watch sends a free WhatsApp update on DATTATRAY RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DATTATRAY RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), DATTATRAY RESIDENCY has 3 buildings filed: WING A with 15 floors and 128 units; WING B with 4 floors and 20 units; WING C with 4 floors and 20 units.
What are the flat sizes (carpet area) in DATTATRAY RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for DATTATRAY RESIDENCY: 1 BHK: 317 sq ft carpet (134 homes); 1 Room Kitchen: 297 sq ft carpet (30 homes); 2 BHK: 413 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of DATTATRAY RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), DATTATRAY RESIDENCY stands on 6,580 sq m of land (about 1.6 acres), with 7,525 sq m of sanctioned built-up area and 632 sq m of recreational open space.
Where can I read reviews of DATTATRAY RESIDENCY?
Google Maps has reviews of DATTATRAY RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DATTATRAY RESIDENCY?
DATTATRAY RESIDENCY by SHRI KRISHNA VASTU is in Badlapur, Thane (pincode 421503), near Kulgaon, Maharashtra, and is registered on MahaRERA as P51700049960, per GharKundli's check of MahaRERA records.
How many homes are in DATTATRAY RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), DATTATRAY RESIDENCY has 168 homes in 3 towers registered on MahaRERA, and 19% of them are sold or booked.
When was DATTATRAY RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DATTATRAY RESIDENCY was registered on MahaRERA on 6 March 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on DATTATRAY RESIDENCY?
No court cases are listed for DATTATRAY RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of DATTATRAY RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRI KRISHNA VASTU.
Check it yourself on MahaRERA
- How to check the possession date of DATTATRAY RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in pincode 421503
- SHIV TIRTH B WING
- PRABHU DARSHAN CO-OPERATIVE HOUSING SOCIETY LIMITED
- SAI UNIVERSE
- HARI SHRUSHTI WING A PHASE II
- MERY VILLA CHSL
- Gokul Heights
- MAHAVIR HERITAGE
- INFINITY MEADOWS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.