STANBERTH ANNEX
by Shivam Developers · Uthalsar, ThaneAlso near Charai, Majiwada, Naupada
Possession date of STANBERTH ANNEX: 31 December 2026, moved from 28 November 2023 (37 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700023104, and currently active. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about STANBERTH ANNEX?
How the possession date of STANBERTH ANNEX has moved
28 November 2023
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025356)
Reason the builder gave MahaRERA:
“Constitution of the Partnership Firm The delay in the execution of the real estate project can be attributed to significant changes in the constitution of the Partnership Firm managing the project. Demise of a Key Partner: One of the workin…” Read the full reason
“Constitution of the Partnership Firm The delay in the execution of the real estate project can be attributed to significant changes in the constitution of the Partnership Firm managing the project. Demise of a Key Partner: One of the working partners, Late Mr. Nizar Kasar, passed away on 29.01.2022. The demise of this key partner had a profound impact on the functioning and decision-making processes of the firm, leading to disruption in the continuity of business operations. Health Issues of Another Partner: The second working partner, Mr. Dhanji Virji Furia, was afflicted with a severe ill…”31 December 2026
Extended at the builder's request (MahaRERA application EA29122519085)
Reason the builder gave MahaRERA:
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of…” Read the full reason
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…”
Source: STANBERTH ANNEX’s extension records on MahaRERA (P51700023104), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on STANBERTH ANNEX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700023104
- Status
- Registered and active
- Builder
- Shivam Developers
- Location
- Uthalsar, Thane · 400601
- Project type
- Residential / Group Housing
- Registered on
- 2 Dec 2019
- Completion date at registration
- November 2023
- Latest completion date
- December 2026
- Delay so far
- 37 months
- Homes
- 36
- Sold or booked
- 95%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 12
Construction progress of STANBERTH ANNEX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| STANBERTH ANNEX | 100% | 100% | 80% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- STANBERTH ANNEX: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on STANBERTH ANNEX every month.
STANBERTH ANNEX: buildings, flats and land, as filed on MahaRERA
- Buildings: STANBERTH ANNEX (10 floors, 47 units)
- Car parking: 1 covered
- Land: 925 sq m (about 0.2 acres) · sanctioned built-up 2,154 sq m
- Boundaries filed include: Public Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of STANBERTH ANNEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
STANBERTH ANNEX: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about STANBERTH ANNEX
What is the possession date of STANBERTH ANNEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for STANBERTH ANNEX in Uthalsar, Thane is 31 December 2026 — 37 months later than 28 November 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for STANBERTH ANNEX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date STANBERTH ANNEX's builder has filed on MahaRERA, the official one, is 31 December 2026, already 37 months later than the 28 November 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of STANBERTH ANNEX extended?
According to GharKundli's check of MahaRERA records (updated October 2026), STANBERTH ANNEX's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Constitution of the Partnership Firm The delay in the execution of the real estate project can be attributed to significant changes in the constitution of the Partnership Firm managing the project. Demise of a Key Partner: One of the working partners, Late Mr. Nizar Kasar, passed away on 29.01.2022. The demise of this key partner had a profound impact on the functioning and decision-making processes of the firm, leading to disruption in the continuity of business operations. Health Issues of Another Partner: The second working partner, Mr. Dhanji Virji Furia, was afflicted with a severe ill…"; to 31 December 2026, giving the reason "Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…".
What is the RERA number of STANBERTH ANNEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of STANBERTH ANNEX in Uthalsar, Thane is P51700023104.
Is STANBERTH ANNEX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), STANBERTH ANNEX is registered as P51700023104 and its status is "Registered and active".
What is the construction status of STANBERTH ANNEX?
According to GharKundli's check of MahaRERA records (updated October 2026), STANBERTH ANNEX's status on MahaRERA is "Registered and active". As filed by the builder, slab work on STANBERTH ANNEX is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does STANBERTH ANNEX have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is STANBERTH ANNEX safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), STANBERTH ANNEX is registered on MahaRERA as P51700023104, its completion date has moved 37 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if STANBERTH ANNEX's possession date changes?
The latest dates are on STANBERTH ANNEX's MahaRERA page (P51700023104). GharKundli's Kundli Watch sends a free WhatsApp update on STANBERTH ANNEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does STANBERTH ANNEX have?
According to GharKundli's check of MahaRERA records (updated October 2026), STANBERTH ANNEX has one building filed: STANBERTH ANNEX with 10 floors and 47 units.
How much parking does STANBERTH ANNEX have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for STANBERTH ANNEX.
How big is the land of STANBERTH ANNEX?
According to GharKundli's check of MahaRERA records (updated October 2026), STANBERTH ANNEX stands on 925 sq m of land (about 0.2 acres), with 2,154 sq m of sanctioned built-up area.
Where can I read reviews of STANBERTH ANNEX?
Google Maps has reviews of STANBERTH ANNEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is STANBERTH ANNEX?
STANBERTH ANNEX by Shivam Developers is in Uthalsar, Thane (pincode 400601), near Charai, Majiwada, Naupada, Maharashtra, and is registered on MahaRERA as P51700023104, per GharKundli's check of MahaRERA records. Its boundaries filed there include Public Road.
How many homes are in STANBERTH ANNEX?
According to GharKundli's check of MahaRERA records (updated October 2026), STANBERTH ANNEX has 36 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.
When was STANBERTH ANNEX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), STANBERTH ANNEX was registered on MahaRERA on 2 December 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on STANBERTH ANNEX?
No court cases are listed for STANBERTH ANNEX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of STANBERTH ANNEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shivam Developers, which has 12 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of STANBERTH ANNEX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Thane
- SRINATHJI VISHWASHREE
- Jeevan Lifestyles
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- GURUKRUPA NITYAM
- MAULI KRUPA
- ASAVARI CO OP HSG SOC LTD
- Panache
Other projects by Shivam Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.