by Sumit Developers · Murbad, Thane

Possession date of Morya Garden: 30 August 2027, moved from 30 April 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700023720, and currently active. Its completion date has moved from April 2024 to August 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Morya Garden?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Morya Garden has moved

  1. 30 April 2024

    Completion date given when the project was registered

  2. 30 April 2027

    Extended at the builder's request (MahaRERA application EXT51700027775)

    Reason the builder gave MahaRERA:
    “1. Revision of Sanctioned Plans & Increased Scope: The project was initially envisioned and approved as a Ground + 6 floor structure. However, to optimize the land potential and meet market demand, the building plans were significantly revi…” Read the full reason“1. Revision of Sanctioned Plans & Increased Scope: The project was initially envisioned and approved as a Ground + 6 floor structure. However, to optimize the land potential and meet market demand, the building plans were significantly revised and subsequently approved by the Murbad Nagar Panchayat on 30/07/2024. The project has now expanded to a Ground + 11 floor structure. This substantial increase in built-up area and the number of floors has fundamentally altered the construction timeline, requiring an additional 36 months for structural completion, finishing, and service installations.…”
  3. 30 August 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Morya Garden’s extension records on MahaRERA (P51700023720), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Morya Garden

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700023720
Status
Registered and active
Builder
Sumit Developers
Location
Murbad, Thane · 421401
Project type
Residential / Group Housing
Registered on
2 Jan 2020
Completion date at registration
April 2024
Latest completion date
August 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
70
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Morya Garden, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building A0%7%0%0%
Building B100%25%0%0%
Building C100%5%95%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Morya Garden every month.

Morya Garden: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building A (8 floors) · Building B (9 floors) · Building C (5 floors)
  • Land: 3,110 sq m (about 0.8 acres) · sanctioned built-up 3,229 sq m
  • Boundaries filed include: Lake, School

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Morya Garden →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Morya Garden: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Morya Garden

What is the possession date of Morya Garden?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Morya Garden in Murbad, Thane is 30 August 2027 — 36 months later than 30 April 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Morya Garden?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Morya Garden's builder has filed on MahaRERA, the official one, is 30 August 2027, already 36 months later than the 30 April 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Morya Garden extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Morya Garden's builder applied to MahaRERA to extend the completion date once: to 30 April 2027, giving the reason "1. Revision of Sanctioned Plans & Increased Scope: The project was initially envisioned and approved as a Ground + 6 floor structure. However, to optimize the land potential and meet market demand, the building plans were significantly revised and subsequently approved by the Murbad Nagar Panchayat on 30/07/2024. The project has now expanded to a Ground + 11 floor structure. This substantial increase in built-up area and the number of floors has fundamentally altered the construction timeline, requiring an additional 36 months for structural completion, finishing, and service installations.…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Morya Garden?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Morya Garden in Murbad, Thane is P51700023720.

Is Morya Garden registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Morya Garden is registered as P51700023720 and its status is "Registered and active".

What is the construction status of Morya Garden?

According to GharKundli's check of MahaRERA records (updated October 2026), Morya Garden's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 5% to 25% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Morya Garden have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Morya Garden safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Morya Garden is registered on MahaRERA as P51700023720, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Morya Garden's possession date changes?

The latest dates are on Morya Garden's MahaRERA page (P51700023720). GharKundli's Kundli Watch sends a free WhatsApp update on Morya Garden every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Morya Garden have?

According to GharKundli's check of MahaRERA records (updated October 2026), Morya Garden has 3 buildings filed: Building A with 8 floors; Building B with 9 floors; Building C with 5 floors.

How big is the land of Morya Garden?

According to GharKundli's check of MahaRERA records (updated October 2026), Morya Garden stands on 3,110 sq m of land (about 0.8 acres), with 3,229 sq m of sanctioned built-up area.

Where can I read reviews of Morya Garden?

Google Maps has reviews of Morya Garden written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Morya Garden?

Morya Garden by Sumit Developers is in Murbad, Thane (pincode 421401), Maharashtra, and is registered on MahaRERA as P51700023720, per GharKundli's check of MahaRERA records. Its boundaries filed there include Lake, School.

How many homes are in Morya Garden?

According to GharKundli's check of MahaRERA records (updated October 2026), Morya Garden has 70 homes in 3 towers registered on MahaRERA.

When was Morya Garden registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Morya Garden was registered on MahaRERA on 2 January 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Morya Garden?

No court cases are listed for Morya Garden on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Morya Garden?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sumit Developers, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in pincode 421401

All 42 projects in Murbad (421401) →

Other projects by Sumit Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.