Skip to content
GharKundli

MANJIRI PRATHAM

by SHRI DEVELOPERS · Shri Samarth Society, Osmanabad

Possession: MANJIRI PRATHAM is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52500047191. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MANJIRI PRATHAM?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MANJIRI PRATHAM has moved

  1. 31 July 2025

    Completion date given when the project was registered

  2. 14 October 2025

    Extended at the builder's request (MahaRERA application EA07012619334)

    Reason the builder gave MahaRERA: “POST FACTO”

Source: MANJIRI PRATHAM’s extension records on MahaRERA (P52500047191), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MANJIRI PRATHAM

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52500047191
Status
Completed
Builder
SHRI DEVELOPERS
Location
Shri Samarth Society, Osmanabad · 413501
Project type
Residential / Group Housing
Registered on
11 Oct 2022
Completion date at registration
July 2025
Latest completion date
October 2025
Delay so far
3 months
Homes
10
Sold or booked
10%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of MANJIRI PRATHAM, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MANJIRI PRATHAM100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • MANJIRI PRATHAM: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANJIRI PRATHAM every month.

MANJIRI PRATHAM: buildings, flats and land, as filed on MahaRERA

  • Buildings: MANJIRI PRATHAM (3 floors, 10 units)
  • Land: 979 sq m (about 0.2 acres) · sanctioned built-up 1,266 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MANJIRI PRATHAM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MANJIRI PRATHAM: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MANJIRI PRATHAM

What is the possession date of MANJIRI PRATHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MANJIRI PRATHAM in Shri Samarth Society, Osmanabad is 14 October 2025 — 3 months later than 31 July 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for MANJIRI PRATHAM?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MANJIRI PRATHAM's builder has filed on MahaRERA, the official one, is 14 October 2025, already 3 months later than the 31 July 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MANJIRI PRATHAM extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MANJIRI PRATHAM's builder applied to MahaRERA to extend the completion date once: to 14 October 2025, giving the reason "POST FACTO".

What is the RERA number of MANJIRI PRATHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MANJIRI PRATHAM in Shri Samarth Society, Osmanabad is P52500047191.

Is MANJIRI PRATHAM registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MANJIRI PRATHAM is registered as P52500047191 and its status is "Completed".

What is the construction status of MANJIRI PRATHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), MANJIRI PRATHAM's status on MahaRERA is "Completed". As filed by the builder, slab work on MANJIRI PRATHAM is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MANJIRI PRATHAM have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MANJIRI PRATHAM safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MANJIRI PRATHAM is registered on MahaRERA as P52500047191, its MahaRERA status is "Completed", its completion date has moved 3 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MANJIRI PRATHAM's possession date changes?

The latest dates are on MANJIRI PRATHAM's MahaRERA page (P52500047191). GharKundli's Kundli Watch sends a free WhatsApp update on MANJIRI PRATHAM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MANJIRI PRATHAM have?

According to GharKundli's check of MahaRERA records (updated October 2026), MANJIRI PRATHAM has one building filed: MANJIRI PRATHAM with 3 floors and 10 units.

How big is the land of MANJIRI PRATHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), MANJIRI PRATHAM stands on 979 sq m of land (about 0.2 acres), with 1,266 sq m of sanctioned built-up area.

Where can I read reviews of MANJIRI PRATHAM?

Google Maps has reviews of MANJIRI PRATHAM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MANJIRI PRATHAM?

MANJIRI PRATHAM by SHRI DEVELOPERS is in Shri Samarth Society, Osmanabad (pincode 413501), Maharashtra, and is registered on MahaRERA as P52500047191, per GharKundli's check of MahaRERA records.

How many homes are in MANJIRI PRATHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), MANJIRI PRATHAM has 10 homes in 1 tower registered on MahaRERA, and 10% of them are sold or booked.

When was MANJIRI PRATHAM registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MANJIRI PRATHAM was registered on MahaRERA on 11 October 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on MANJIRI PRATHAM?

No court cases are listed for MANJIRI PRATHAM on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MANJIRI PRATHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRI DEVELOPERS, which has 8 other projects registered on MahaRERA.

Other projects in Osmanabad

All 8 projects in Osmanabad (413501) →

Other projects by SHRI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.