RSM DHARASHIV SHELTERS- OSMANABAD PROJECT
by RSM DHARASHIV SHELTERS · Osmanabad
Possession date of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT: 30 April 2028, moved from 31 May 2025 (31 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52500029666, and currently active. Its completion date has moved from May 2025 to April 2028: 31 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
How the possession date of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT has moved
31 May 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA03092502499)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RSM DHARASHIV SHELTERS- OSMANABAD PROJECT’s extension records on MahaRERA (P52500029666), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RSM DHARASHIV SHELTERS- OSMANABAD PROJECT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52500029666
- Status
- Registered and active
- Builder
- RSM DHARASHIV SHELTERS
- Location
- Osmanabad · 413501
- Project type
- Residential / Group Housing
- Registered on
- 26 Jun 2021
- Completion date at registration
- May 2025
- Latest completion date
- April 2028
- Delay so far
- 31 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 899
- Sold or booked
- 56%
- Towers
- 18
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A1 | 100% | 100% | 75% | 60% |
| A2 | 100% | 100% | 75% | 60% |
| A3 | 100% | 100% | 75% | 60% |
| A4 | 100% | 100% | 75% | 60% |
| A5 | 100% | 100% | 75% | 60% |
| A6 | 100% | 100% | 75% | 60% |
| A7 | 100% | 100% | 75% | 60% |
| A8 | 100% | 100% | 75% | 60% |
| A9 | 100% | 100% | 75% | 60% |
| A10 | 100% | 100% | 75% | 60% |
| A11 | 100% | 100% | 75% | 60% |
| A12 | 100% | 100% | 75% | 60% |
| A13 | 100% | 100% | 75% | 60% |
| A14 | 100% | 100% | 75% | 60% |
| A15 | 100% | 100% | 75% | 60% |
| 0 | 100% | 100% | 75% | 60% |
| G1 | 100% | 100% | 75% | 60% |
| H1 | 100% | 100% | 75% | 60% |
Commencement certificate (CC), as filed on MahaRERA
- A1: covers 5 floors
- A2: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RSM DHARASHIV SHELTERS- OSMANABAD PROJECT every month.
RSM DHARASHIV SHELTERS- OSMANABAD PROJECT: buildings, flats and land, as filed on MahaRERA
- Buildings: A1 (5 floors, 60 units) · A2 (5 floors, 60 units) · A3 (5 floors, 60 units) · A4 (5 floors, 60 units) · A5 (5 floors, 60 units) · A6 (5 floors, 60 units) · A7 (5 floors, 59 units) · A8 (5 floors, 60 units) · and 7 more
- Land: 27,000 sq m (about 6.7 acres) · sanctioned built-up 35,126 sq m · recreational space 2,200 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RSM DHARASHIV SHELTERS- OSMANABAD PROJECT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RSM DHARASHIV SHELTERS- OSMANABAD PROJECT
What is the possession date of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RSM DHARASHIV SHELTERS- OSMANABAD PROJECT in Osmanabad is 30 April 2028 — 31 months later than 31 May 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RSM DHARASHIV SHELTERS- OSMANABAD PROJECT's builder has filed on MahaRERA, the official one, is 30 April 2028, already 31 months later than the 31 May 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), RSM DHARASHIV SHELTERS- OSMANABAD PROJECT's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT in Osmanabad is P52500029666.
Is RSM DHARASHIV SHELTERS- OSMANABAD PROJECT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RSM DHARASHIV SHELTERS- OSMANABAD PROJECT is registered as P52500029666 and its status is "Registered and active".
What is the construction status of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
According to GharKundli's check of MahaRERA records (updated October 2026), RSM DHARASHIV SHELTERS- OSMANABAD PROJECT's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 18 towers. GharKundli's full report compares construction progress with the deadline.
Does RSM DHARASHIV SHELTERS- OSMANABAD PROJECT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is RSM DHARASHIV SHELTERS- OSMANABAD PROJECT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RSM DHARASHIV SHELTERS- OSMANABAD PROJECT is registered on MahaRERA as P52500029666, its completion date has moved 31 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RSM DHARASHIV SHELTERS- OSMANABAD PROJECT's possession date changes?
The latest dates are on RSM DHARASHIV SHELTERS- OSMANABAD PROJECT's MahaRERA page (P52500029666). GharKundli's Kundli Watch sends a free WhatsApp update on RSM DHARASHIV SHELTERS- OSMANABAD PROJECT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RSM DHARASHIV SHELTERS- OSMANABAD PROJECT have?
According to GharKundli's check of MahaRERA records (updated October 2026), RSM DHARASHIV SHELTERS- OSMANABAD PROJECT has 15 buildings filed: A1 with 5 floors and 60 units; A2 with 5 floors and 60 units; A3 with 5 floors and 60 units; A4 with 5 floors and 60 units; A5 with 5 floors and 60 units; A6 with 5 floors and 60 units; and 9 more.
How big is the land of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
According to GharKundli's check of MahaRERA records (updated October 2026), RSM DHARASHIV SHELTERS- OSMANABAD PROJECT stands on 27,000 sq m of land (about 6.7 acres), with 35,126 sq m of sanctioned built-up area and 2,200 sq m of recreational open space.
Where can I read reviews of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
Google Maps has reviews of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
RSM DHARASHIV SHELTERS- OSMANABAD PROJECT by RSM DHARASHIV SHELTERS is in Osmanabad (pincode 413501), Maharashtra, and is registered on MahaRERA as P52500029666, per GharKundli's check of MahaRERA records.
How many homes are in RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
According to GharKundli's check of MahaRERA records (updated October 2026), RSM DHARASHIV SHELTERS- OSMANABAD PROJECT has 899 homes in 18 towers registered on MahaRERA, and 56% of them are sold or booked.
When was RSM DHARASHIV SHELTERS- OSMANABAD PROJECT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RSM DHARASHIV SHELTERS- OSMANABAD PROJECT was registered on MahaRERA on 26 June 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
No court cases are listed for RSM DHARASHIV SHELTERS- OSMANABAD PROJECT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RSM DHARASHIV SHELTERS.
Check it yourself on MahaRERA
- How to check the possession date of RSM DHARASHIV SHELTERS- OSMANABAD PROJECT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Osmanabad →
Other projects in Osmanabad
- MANJIRI PRATHAM
- DHANESHWAR HEIGHTS
- TULJAI TOWER
- DHANESHWAR TOWER
- SUDARSHAN TOWER
- THE GRAND PADMAKSH PHASE 3
- NAKSHATRA HIGHTS
- SHIVRAI SOCIETY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.