DHANESHWAR HEIGHTS
by RAMCHANDRA NANABHAU SANGLE · Dharshiv MIDC, Osmanabad
Possession date of DHANESHWAR HEIGHTS: 31 March 2027, moved from 30 June 2026 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52500079870, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about DHANESHWAR HEIGHTS?
How the possession date of DHANESHWAR HEIGHTS has moved
30 June 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA20082622251)
Reason the builder gave MahaRERA:
“The project "Dhaneshwar Heights" is located at Dharashiv, which is a semi-urban area with limited local availability of skilled and unskilled construction labour as well as construction machinery and equipment. This has consistently constra…” Read the full reason
“The project "Dhaneshwar Heights" is located at Dharashiv, which is a semi-urban area with limited local availability of skilled and unskilled construction labour as well as construction machinery and equipment. This has consistently constrained the pace of construction activity as compared to projects located in urban centres with better resource access. Further, the geopolitical conflict between Iraq and Iran during the currency of this project has led to disruption in fuel supply chains, resulting in shortage and increased cost of diesel and other fuel required to operate construction mac…”
Source: DHANESHWAR HEIGHTS’s extension records on MahaRERA (P52500079870), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DHANESHWAR HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52500079870
- Status
- Registered and active
- Builder
- RAMCHANDRA NANABHAU SANGLE
- Location
- Dharshiv MIDC, Osmanabad · 413501
- Project type
- Residential / Group Housing
- Registered on
- 28 Mar 2025
- Completion date at registration
- June 2026
- Latest completion date
- March 2027
- Delay so far
- 9 months
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of DHANESHWAR HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DHANESHWAR HEIGHTS | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- DHANESHWAR HEIGHTS: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DHANESHWAR HEIGHTS every month.
DHANESHWAR HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: DHANESHWAR HEIGHTS (8 floors)
- Car parking: 25 covered
- Land: 727 sq m (about 0.2 acres) · sanctioned built-up 1,976 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DHANESHWAR HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DHANESHWAR HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DHANESHWAR HEIGHTS
What is the possession date of DHANESHWAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DHANESHWAR HEIGHTS in Dharshiv MIDC, Osmanabad is 31 March 2027 — 9 months later than 30 June 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for DHANESHWAR HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DHANESHWAR HEIGHTS's builder has filed on MahaRERA, the official one, is 31 March 2027, already 9 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DHANESHWAR HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANESHWAR HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The project "Dhaneshwar Heights" is located at Dharashiv, which is a semi-urban area with limited local availability of skilled and unskilled construction labour as well as construction machinery and equipment. This has consistently constrained the pace of construction activity as compared to projects located in urban centres with better resource access. Further, the geopolitical conflict between Iraq and Iran during the currency of this project has led to disruption in fuel supply chains, resulting in shortage and increased cost of diesel and other fuel required to operate construction mac…".
What is the RERA number of DHANESHWAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DHANESHWAR HEIGHTS in Dharshiv MIDC, Osmanabad is P52500079870.
Is DHANESHWAR HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANESHWAR HEIGHTS is registered as P52500079870 and its status is "Registered and active".
What is the construction status of DHANESHWAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANESHWAR HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DHANESHWAR HEIGHTS is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does DHANESHWAR HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is DHANESHWAR HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANESHWAR HEIGHTS is registered on MahaRERA as P52500079870, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DHANESHWAR HEIGHTS's possession date changes?
The latest dates are on DHANESHWAR HEIGHTS's MahaRERA page (P52500079870). GharKundli's Kundli Watch sends a free WhatsApp update on DHANESHWAR HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DHANESHWAR HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANESHWAR HEIGHTS has one building filed: DHANESHWAR HEIGHTS with 8 floors.
How much parking does DHANESHWAR HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 25 covered car parking spaces for DHANESHWAR HEIGHTS.
How big is the land of DHANESHWAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANESHWAR HEIGHTS stands on 727 sq m of land (about 0.2 acres), with 1,976 sq m of sanctioned built-up area.
Where can I read reviews of DHANESHWAR HEIGHTS?
Google Maps has reviews of DHANESHWAR HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DHANESHWAR HEIGHTS?
DHANESHWAR HEIGHTS by RAMCHANDRA NANABHAU SANGLE is in Dharshiv MIDC, Osmanabad (pincode 413501), Maharashtra, and is registered on MahaRERA as P52500079870, per GharKundli's check of MahaRERA records.
When was DHANESHWAR HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANESHWAR HEIGHTS was registered on MahaRERA on 28 March 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on DHANESHWAR HEIGHTS?
No court cases are listed for DHANESHWAR HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of DHANESHWAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAMCHANDRA NANABHAU SANGLE.
Check it yourself on MahaRERA
- How to check the possession date of DHANESHWAR HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Osmanabad →
Other projects in Osmanabad
- MANJIRI PRATHAM
- RSM DHARASHIV SHELTERS- OSMANABAD PROJECT
- DHANESHWAR TOWER
- SUDARSHAN TOWER
- THE GRAND PADMAKSH PHASE 3
- NAKSHATRA HIGHTS
- SHIVRAI SOCIETY
- SHRI SAMARTH SOCIETY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.