Aradhana Homes
by ABHINANDAN DAGADU RATHOD · Kumtha Naka, Solapur 413004
What’s in the report? →Possession date of Aradhana Homes (MahaRERA P52600004041): 30 December 2021, moved from 30 December 2018 (36 months later), and it has already passed. It has 10 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600004041. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52600004041, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2021) has passed.
What do you want to know about Aradhana Homes?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Aradhana Homes has moved
30 December 2018
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT52600001238)
Reason the builder gave MahaRERA:
“THE NON AVAILABILITY OF RIVER SAND IN THE REGION HAS COST THE DELAY OF THE PROJECT. THE AUTHORITIES HAVE SAELED VARIOUS QUARRY AROUND THE REGION DUE TO ENVIRONMENTAL PROBLEMS AND ROYALTY ISSUES.THE UNEXPECTED RAINS THROUGHOUT YEAR HAS CAUSE…” Read the full reason
“THE NON AVAILABILITY OF RIVER SAND IN THE REGION HAS COST THE DELAY OF THE PROJECT. THE AUTHORITIES HAVE SAELED VARIOUS QUARRY AROUND THE REGION DUE TO ENVIRONMENTAL PROBLEMS AND ROYALTY ISSUES.THE UNEXPECTED RAINS THROUGHOUT YEAR HAS CAUSED A GREAT DEAL OF INCONVENIENCE AND THIS HASRESULTED IN THE PROJECT BEING FURTHER DELAYED. AS PROMOTER I HAVE FULL INTENTION OF COMPLETING THE PROJECT AT ITS EARLIEST.”30 December 2021
Revised completion date on MahaRERA
Source: Aradhana Homes’s extension records on MahaRERA (P52600004041), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aradhana Homes
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52600004041
- Status
- Lapsed (registration period ended)
- Builder
- ABHINANDAN DAGADU RATHOD
- Location
- Kumtha Naka, Solapur · 413004
- Project type
- Residential / Group Housing
- Registered on
- 7 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2021
- Delay so far
- 36 months
- Homes
- 10
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Aradhana Homes, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ARADHANA HOMES | 100% | 65% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aradhana Homes every 1–2 months.
Aradhana Homes: buildings, flats and land, as filed on MahaRERA
- Buildings: ARADHANA HOMES (7 floors)
- Land: 370 sq m (about 0.1 acres) · sanctioned built-up 509 sq m
- Land, as filed: 24/8
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Aradhana Homes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aradhana Homes: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Aradhana Homes
What is the possession date of Aradhana Homes?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aradhana Homes in Kumtha Naka, Solapur is 30 December 2021 — 36 months later than 30 December 2018, the date given at registration. That date has already passed.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Aradhana Homes?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aradhana Homes's builder has filed on MahaRERA, the official one, is 30 December 2021, already 36 months later than the 30 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aradhana Homes extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes's builder applied to MahaRERA to extend the completion date once: to 31 December 2020, giving the reason "THE NON AVAILABILITY OF RIVER SAND IN THE REGION HAS COST THE DELAY OF THE PROJECT. THE AUTHORITIES HAVE SAELED VARIOUS QUARRY AROUND THE REGION DUE TO ENVIRONMENTAL PROBLEMS AND ROYALTY ISSUES.THE UNEXPECTED RAINS THROUGHOUT YEAR HAS CAUSED A GREAT DEAL OF INCONVENIENCE AND THIS HASRESULTED IN THE PROJECT BEING FURTHER DELAYED. AS PROMOTER I HAVE FULL INTENTION OF COMPLETING THE PROJECT AT ITS EARLIEST.".
What is the RERA number of Aradhana Homes?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aradhana Homes in Kumtha Naka, Solapur is P52600004041.
Is Aradhana Homes registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes is registered as P52600004041 and its status is "Lapsed (registration period ended)".
What is the current construction status of Aradhana Homes? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ARADHANA HOMES is 65% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Aradhana Homes have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Aradhana Homes safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes is registered on MahaRERA as P52600004041, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Aradhana Homes?
Aradhana Homes isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Aradhana Homes?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aradhana Homes: gharkundli.com/tools/property-cost-calculator
Has Aradhana Homes received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Aradhana Homes?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Aradhana Homes uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aradhana Homes was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Aradhana Homes's possession date changes?
The latest dates are on Aradhana Homes's MahaRERA page (P52600004041). GharKundli's Kundli Watch sends a free WhatsApp update on Aradhana Homes every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aradhana Homes have?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes has one building filed: ARADHANA HOMES with 7 floors.
How big is the land of Aradhana Homes?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes stands on 370 sq m of land (about 0.1 acres), with 509 sq m of sanctioned built-up area.
What are the reviews of Aradhana Homes?
Google Maps has reviews of Aradhana Homes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Aradhana Homes?
Aradhana Homes by ABHINANDAN DAGADU RATHOD is in Kumtha Naka, Solapur, pincode 413004, Maharashtra, and is registered on MahaRERA as P52600004041, per GharKundli's check of MahaRERA records. Its land is filed as 24/8. GharKundli lists all 62 MahaRERA projects in Solapur (413004).
How many flats are in Aradhana Homes?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes has 10 homes in 1 tower registered on MahaRERA.
When was Aradhana Homes registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aradhana Homes was registered on MahaRERA on 7 August 2017. GharKundli did not find a title report on the land on file there.
Does Aradhana Homes have any legal issues or court cases?
No court cases are listed for Aradhana Homes on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Aradhana Homes?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ABHINANDAN DAGADU RATHOD.
Check it yourself on MahaRERA
- How to check the possession date of Aradhana Homes
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Solapur North
- Kaizen Emerald
- Samarth Prasad
- Vijays the Prestige
- Shivtej Plaza
- F.F Amora
- Prajay Heights
- Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha
- Balaji Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.