Anandam Vihar Phase I WING A

by SV SMART CITY DEVELOPERS · Gandhinagar, SolapurAlso near Railway Lines, Majrewadi

Possession: Anandam Vihar Phase I WING A is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600013748. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Anandam Vihar Phase I WING A?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Anandam Vihar Phase I WING A has moved

  1. 31 March 2020

    Completion date given when the project was registered

  2. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT52600001266)

    Reason the builder gave MahaRERA: “Received Revised Permission on 03/07/2018”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT52600011772)

    Reason the builder gave MahaRERA: “resolution of flat owner obtained”

Source: Anandam Vihar Phase I WING A’s extension records on MahaRERA (P52600013748), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Anandam Vihar Phase I WING A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600013748
Status
Completed
Builder
SV SMART CITY DEVELOPERS
Location
Gandhinagar, Solapur · 413005
Project type
Residential / Group Housing
Registered on
25 Oct 2017
Completion date at registration
March 2020
Latest completion date
June 2022
Delay so far
27 months
Homes
96
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Anandam Vihar Phase I WING A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anandam Vihar Phase I WING A every month.

Anandam Vihar Phase I WING A: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Anandam Vihar Phase I WING A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Anandam Vihar Phase I WING A: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Anandam Vihar Phase I WING A

What is the possession date of Anandam Vihar Phase I WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Anandam Vihar Phase I WING A in Gandhinagar, Solapur is 30 June 2022 — 27 months later than 31 March 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Anandam Vihar Phase I WING A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Anandam Vihar Phase I WING A's builder has filed on MahaRERA, the official one, is 30 June 2022, already 27 months later than the 31 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Anandam Vihar Phase I WING A extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Vihar Phase I WING A's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2021, giving the reason "Received Revised Permission on 03/07/2018"; to 30 June 2022, giving the reason "resolution of flat owner obtained".

What is the RERA number of Anandam Vihar Phase I WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Anandam Vihar Phase I WING A in Gandhinagar, Solapur is P52600013748.

Is Anandam Vihar Phase I WING A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Vihar Phase I WING A is registered as P52600013748 and its status is "Completed".

What is the construction status of Anandam Vihar Phase I WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Vihar Phase I WING A's status on MahaRERA is "Completed". As filed by the builder, slab work on WING A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Anandam Vihar Phase I WING A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Anandam Vihar Phase I WING A safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Vihar Phase I WING A is registered on MahaRERA as P52600013748, its MahaRERA status is "Completed", its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Anandam Vihar Phase I WING A's possession date changes?

The latest dates are on Anandam Vihar Phase I WING A's MahaRERA page (P52600013748). GharKundli's Kundli Watch sends a free WhatsApp update on Anandam Vihar Phase I WING A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Anandam Vihar Phase I WING A have?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Vihar Phase I WING A has one building filed: WING A with 10 floors.

How big is the land of Anandam Vihar Phase I WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Vihar Phase I WING A stands on 5,148 sq m of land (about 1.3 acres), with 3,688 sq m of sanctioned built-up area and 546 sq m of recreational open space.

Where can I read reviews of Anandam Vihar Phase I WING A?

Google Maps has reviews of Anandam Vihar Phase I WING A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Anandam Vihar Phase I WING A?

Anandam Vihar Phase I WING A by SV SMART CITY DEVELOPERS is in Gandhinagar, Solapur (pincode 413005), near Railway Lines, Majrewadi, Maharashtra, and is registered on MahaRERA as P52600013748, per GharKundli's check of MahaRERA records.

How many homes are in Anandam Vihar Phase I WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Vihar Phase I WING A has 96 homes in 1 tower registered on MahaRERA.

When was Anandam Vihar Phase I WING A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Vihar Phase I WING A was registered on MahaRERA on 25 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Anandam Vihar Phase I WING A?

No court cases are listed for Anandam Vihar Phase I WING A on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Anandam Vihar Phase I WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SV SMART CITY DEVELOPERS, which has 1 other project registered on MahaRERA.

Other projects in Solapur North

Other projects by SV SMART CITY DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.