How the possession date of SUYOG SHRUSHTI PHASE 2 has moved
16 March 2025
Completion date given when the project was registered
15 March 2026
Extended at the builder's request (MahaRERA application EA28062501833)
Reason the builder gave MahaRERA:
“The project though materially completed though slight delay is encountered in completion of some small part and post connstruction finishing work due to non availability of construction material especially lifts etc. We have also not been a…” Read the full reason
“The project though materially completed though slight delay is encountered in completion of some small part and post connstruction finishing work due to non availability of construction material especially lifts etc. We have also not been able to secure the partial completion certificate though application is pending with Solapur Muncipal Corporation due to operational and staff transfer issues at SMC. Your Authority is kindly requested to condone the delay.”
Source: SUYOG SHRUSHTI PHASE 2’s extension records on MahaRERA (P52600053307), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SUYOG SHRUSHTI PHASE 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SUYOG SHRUSHTIP52600021132
- MahaRERA registration
- P52600053307
- Status
- Completed
- Builder
- SUYOG DEVELOPERS
- Location
- Ravivar Peth, Solapur · 413002
- Project type
- Residential / Group Housing
- Registered on
- 23 Oct 2023
- Completion date at registration
- March 2025
- Latest completion date
- March 2026
- Delay so far
- 12 months
- Homes
- 56
- Sold or booked
- 36%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of SUYOG SHRUSHTI PHASE 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Suyog Shrushti Phase 2 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Suyog Shrushti Phase 2: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUYOG SHRUSHTI PHASE 2 every month.
SUYOG SHRUSHTI PHASE 2: buildings, flats and land, as filed on MahaRERA
- Buildings: Suyog Shrushti Phase 2 (7 floors, 56 units)
- Car parking: 18 covered
- Land: 2,500 sq m (about 0.6 acres) · sanctioned built-up 3,444 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SUYOG SHRUSHTI PHASE 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SUYOG SHRUSHTI PHASE 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SUYOG SHRUSHTI PHASE 2
What is the possession date of SUYOG SHRUSHTI PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SUYOG SHRUSHTI PHASE 2 in Ravivar Peth, Solapur is 15 March 2026 — 12 months later than 16 March 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SUYOG SHRUSHTI PHASE 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SUYOG SHRUSHTI PHASE 2's builder has filed on MahaRERA, the official one, is 15 March 2026, already 12 months later than the 16 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SUYOG SHRUSHTI PHASE 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SUYOG SHRUSHTI PHASE 2's builder applied to MahaRERA to extend the completion date once: to 15 March 2026, giving the reason "The project though materially completed though slight delay is encountered in completion of some small part and post connstruction finishing work due to non availability of construction material especially lifts etc. We have also not been able to secure the partial completion certificate though application is pending with Solapur Muncipal Corporation due to operational and staff transfer issues at SMC. Your Authority is kindly requested to condone the delay.".
What is the RERA number of SUYOG SHRUSHTI PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SUYOG SHRUSHTI PHASE 2 in Ravivar Peth, Solapur is P52600053307.
Is SUYOG SHRUSHTI PHASE 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUYOG SHRUSHTI PHASE 2 is registered as P52600053307 and its status is "Completed".
What is the construction status of SUYOG SHRUSHTI PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SUYOG SHRUSHTI PHASE 2's status on MahaRERA is "Completed". As filed by the builder, slab work on Suyog Shrushti Phase 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SUYOG SHRUSHTI PHASE 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SUYOG SHRUSHTI PHASE 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SUYOG SHRUSHTI PHASE 2 is registered on MahaRERA as P52600053307, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does SUYOG SHRUSHTI PHASE 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SUYOG SHRUSHTI (P52600021132). Check that your agreement names the registration of your own wing.
How can I get updates if SUYOG SHRUSHTI PHASE 2's possession date changes?
The latest dates are on SUYOG SHRUSHTI PHASE 2's MahaRERA page (P52600053307). GharKundli's Kundli Watch sends a free WhatsApp update on SUYOG SHRUSHTI PHASE 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SUYOG SHRUSHTI PHASE 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), SUYOG SHRUSHTI PHASE 2 has one building filed: Suyog Shrushti Phase 2 with 7 floors and 56 units.
How much parking does SUYOG SHRUSHTI PHASE 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered car parking spaces for SUYOG SHRUSHTI PHASE 2.
How big is the land of SUYOG SHRUSHTI PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SUYOG SHRUSHTI PHASE 2 stands on 2,500 sq m of land (about 0.6 acres), with 3,444 sq m of sanctioned built-up area.
Where can I read reviews of SUYOG SHRUSHTI PHASE 2?
Google Maps has reviews of SUYOG SHRUSHTI PHASE 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SUYOG SHRUSHTI PHASE 2?
SUYOG SHRUSHTI PHASE 2 by SUYOG DEVELOPERS is in Ravivar Peth, Solapur (pincode 413002), Maharashtra, and is registered on MahaRERA as P52600053307, per GharKundli's check of MahaRERA records.
How many homes are in SUYOG SHRUSHTI PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SUYOG SHRUSHTI PHASE 2 has 56 homes in 1 tower registered on MahaRERA, and 36% of them are sold or booked.
When was SUYOG SHRUSHTI PHASE 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUYOG SHRUSHTI PHASE 2 was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SUYOG SHRUSHTI PHASE 2?
No court cases are listed for SUYOG SHRUSHTI PHASE 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SUYOG SHRUSHTI PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUYOG DEVELOPERS, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SUYOG SHRUSHTI PHASE 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Solapur North
- Samasta Barajati Gujarathi Mahajan
- Kaizen Emerald
- SAMARTH PRASAD
- VIJAYS THE PRESTIGE
- Shivtej Plaza
- F.F AMORA
- PRAJAY HEIGHTS
- Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha
Other projects by SUYOG DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.