Ekveera Shimmer Ocean Pearl

by EKVEERA ENTERPRISES · Chawk Taluka District, Thane 401107Registered on MahaRERA as “SHIMMER OCEAN PEARL”

What’s in the report? →

Possession date of Ekveera Shimmer Ocean Pearl (MahaRERA P51700024373): 30 December 2025, moved from 30 December 2024 (12 months later), and it has already passed. It has 1 home, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700024373. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700024373, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Ekveera Shimmer Ocean Pearl?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ekveera Shimmer Ocean Pearl has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT51700027640)

    Reason the builder gave MahaRERA: “Thaer is no sale single unit till today we promoters have arrange capital fund for construction of the project therefore we need further time to complete the construction work as we have to arrange fund by ourselves”

Source: Ekveera Shimmer Ocean Pearl’s extension records on MahaRERA (P51700024373), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ekveera Shimmer Ocean Pearl

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700024373
Status
Lapsed (registration period ended)
Builder
EKVEERA ENTERPRISES
Location
Chawk Taluka District, Thane · 401107
Project type
Residential / Group Housing
Registered on
7 Feb 2020
Completion date at registration
December 2024
Latest completion date
December 2025
Delay so far
12 months
Homes
1
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of Ekveera Shimmer Ocean Pearl, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHIMMER OCEAN PEARL100%100%100%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ekveera Shimmer Ocean Pearl every 1–2 months.

Ekveera Shimmer Ocean Pearl: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHIMMER OCEAN PEARL (4 floors)
  • Land: 5,120 sq m (about 1.3 acres) · sanctioned built-up 965 sq m
  • Boundaries filed include: MUNICIPAL ROAD
  • Land, as filed: NEW SNO 10 OLD SNO 129 HNO 2A
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Ekveera Shimmer Ocean Pearl →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ekveera Shimmer Ocean Pearl: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ekveera Shimmer Ocean Pearl

What is the possession date of Ekveera Shimmer Ocean Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ekveera Shimmer Ocean Pearl in Chawk Taluka District, Thane is 30 December 2025 — 12 months later than 30 December 2024, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Ekveera Shimmer Ocean Pearl?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ekveera Shimmer Ocean Pearl's builder has filed on MahaRERA, the official one, is 30 December 2025, already 12 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ekveera Shimmer Ocean Pearl extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl's builder applied to MahaRERA to extend the completion date once: to 30 December 2025, giving the reason "Thaer is no sale single unit till today we promoters have arrange capital fund for construction of the project therefore we need further time to complete the construction work as we have to arrange fund by ourselves".

What is the RERA number of Ekveera Shimmer Ocean Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ekveera Shimmer Ocean Pearl in Chawk Taluka District, Thane is P51700024373.

Is Ekveera Shimmer Ocean Pearl registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl is registered as P51700024373 and its status is "Lapsed (registration period ended)".

What is the current construction status of Ekveera Shimmer Ocean Pearl? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHIMMER OCEAN PEARL is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Ekveera Shimmer Ocean Pearl have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Ekveera Shimmer Ocean Pearl safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl is registered on MahaRERA as P51700024373, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ekveera Shimmer Ocean Pearl?

Ekveera Shimmer Ocean Pearl isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ekveera Shimmer Ocean Pearl?

For a flat in Ekveera Shimmer Ocean Pearl (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Ekveera Shimmer Ocean Pearl received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Ekveera Shimmer Ocean Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Ekveera Shimmer Ocean Pearl uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ekveera Shimmer Ocean Pearl was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ekveera Shimmer Ocean Pearl's possession date changes?

The latest dates are on Ekveera Shimmer Ocean Pearl's MahaRERA page (P51700024373). GharKundli's Kundli Watch sends a free WhatsApp update on Ekveera Shimmer Ocean Pearl every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ekveera Shimmer Ocean Pearl have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl has one building filed: SHIMMER OCEAN PEARL with 4 floors.

How big is the land of Ekveera Shimmer Ocean Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl stands on 5,120 sq m of land (about 1.3 acres), with 965 sq m of sanctioned built-up area.

What are the reviews of Ekveera Shimmer Ocean Pearl?

Google Maps has reviews of Ekveera Shimmer Ocean Pearl written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ekveera Shimmer Ocean Pearl?

Ekveera Shimmer Ocean Pearl by EKVEERA ENTERPRISES is in Chawk Taluka District, Thane, pincode 401107, Maharashtra, and is registered on MahaRERA as P51700024373, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNICIPAL ROAD. Its land is filed as NEW SNO 10 OLD SNO 129 HNO 2A. GharKundli lists all 323 MahaRERA projects in Mira Road East (401107).

How many flats are in Ekveera Shimmer Ocean Pearl, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl has 1 home in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Ekveera Shimmer Ocean Pearl registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekveera Shimmer Ocean Pearl was registered on MahaRERA on 7 February 2020. GharKundli did not find a title report on the land on file there.

Does Ekveera Shimmer Ocean Pearl have any legal issues or court cases?

1 court case is listed for Ekveera Shimmer Ocean Pearl on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Ekveera Shimmer Ocean Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EKVEERA ENTERPRISES, which has 8 other projects registered on MahaRERA.

Other projects in Thane

All 323 projects in Mira Road East (401107) →

Other projects by EKVEERA ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.