Possession date of Shri Pralhad Smurti Residency: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600079243, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Shri Pralhad Smurti Residency?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Shri Pralhad Smurti Residency has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shri Pralhad Smurti Residency’s extension records on MahaRERA (P52600079243), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shri Pralhad Smurti Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600079243
Status
Registered and active
Builder
Vijayratna Developers
Location
Pralhad Nagar, Solapur · 413008
Project type
Residential / Group Housing
Registered on
18 Feb 2025
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
44
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Shri Pralhad Smurti Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Vijayratna Residency100%100%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shri Pralhad Smurti Residency every month.

Shri Pralhad Smurti Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: Vijayratna Residency (8 floors)
  • Land: 658 sq m (about 0.2 acres) · sanctioned built-up 2,527 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shri Pralhad Smurti Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shri Pralhad Smurti Residency: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shri Pralhad Smurti Residency

What is the possession date of Shri Pralhad Smurti Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shri Pralhad Smurti Residency in Pralhad Nagar, Solapur is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Shri Pralhad Smurti Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shri Pralhad Smurti Residency's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shri Pralhad Smurti Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shri Pralhad Smurti Residency in Pralhad Nagar, Solapur is P52600079243.

Is Shri Pralhad Smurti Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Pralhad Smurti Residency is registered as P52600079243 and its status is "Registered and active".

What is the construction status of Shri Pralhad Smurti Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Pralhad Smurti Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vijayratna Residency is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Shri Pralhad Smurti Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shri Pralhad Smurti Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Pralhad Smurti Residency is registered on MahaRERA as P52600079243, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shri Pralhad Smurti Residency's possession date changes?

The latest dates are on Shri Pralhad Smurti Residency's MahaRERA page (P52600079243). GharKundli's Kundli Watch sends a free WhatsApp update on Shri Pralhad Smurti Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shri Pralhad Smurti Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Pralhad Smurti Residency has one building filed: Vijayratna Residency with 8 floors.

How big is the land of Shri Pralhad Smurti Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Pralhad Smurti Residency stands on 658 sq m of land (about 0.2 acres), with 2,527 sq m of sanctioned built-up area.

Where can I read reviews of Shri Pralhad Smurti Residency?

Google Maps has reviews of Shri Pralhad Smurti Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shri Pralhad Smurti Residency?

Shri Pralhad Smurti Residency by Vijayratna Developers is in Pralhad Nagar, Solapur (pincode 413008), Maharashtra, and is registered on MahaRERA as P52600079243, per GharKundli's check of MahaRERA records.

How many homes are in Shri Pralhad Smurti Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Pralhad Smurti Residency has 44 homes in 1 tower registered on MahaRERA.

When was Shri Pralhad Smurti Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Pralhad Smurti Residency was registered on MahaRERA on 18 February 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on Shri Pralhad Smurti Residency?

No court cases are listed for Shri Pralhad Smurti Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Shri Pralhad Smurti Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vijayratna Developers, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Solapur →

Other projects in Solapur North

All 5 projects in SRPF Camp Solapur (413008) →

Other projects by Vijayratna Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.