SHANTI APARTMENT
by KRUSHI NITYANAND PRIVATE LIMITED · Vajira Naka, Ratnagiri
Possession: SHANTI APARTMENT is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800005933. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHANTI APARTMENT?
How the possession date of SHANTI APARTMENT has moved
31 March 2020
Completion date given when the project was registered
31 March 2021
Extended at the builder's request (MahaRERA application EXT52800006011)
Reason the builder gave MahaRERA: “DUE TO SOME TECHNICAL ISSUES AND SHORTAGE OF RAW MATERIALS.”
31 December 2024
Extended at the builder's request (MahaRERA application EXT52800010947)
Reason the builder gave MahaRERA: “Due to Kovid 19, our work could not be completed within the given time. However, we request to get an extension of next 18 months to complete this work.”
30 December 2030
Extended at the builder's request (MahaRERA application EA28092517966)
Reason the builder gave MahaRERA: “Booking is veery slow. Building 2 completed and oc obtained. No further building construction start. we are going to correction in project Phase wise with concent of allotee.”
Source: SHANTI APARTMENT’s extension records on MahaRERA (P52800005933), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHANTI APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800005933
- Status
- Completed
- Builder
- KRUSHI NITYANAND PRIVATE LIMITED
- Location
- Vajira Naka, Ratnagiri · 415606
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2020
- Latest completion date
- December 2030
- Delay so far
- 129 months
- Homes
- 40
- Sold or booked
- 65%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHANTI APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHANTI APARTMENT BLDG-2 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SHANTI APARTMENT BLDG-2: covers 5 (Ground + 4 Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHANTI APARTMENT every month.
SHANTI APARTMENT: buildings, flats and land, as filed on MahaRERA
- Buildings: SHANTI APARTMENT BLDG-2 (5 floors, 40 units)
- Car parking: 4 covered
- Land: 3,300 sq m (about 0.8 acres) · sanctioned built-up 1,543 sq m · recreational space 330 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHANTI APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHANTI APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHANTI APARTMENT
What is the possession date of SHANTI APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHANTI APARTMENT in Vajira Naka, Ratnagiri is 30 December 2030 — 129 months later than 31 March 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHANTI APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHANTI APARTMENT's builder has filed on MahaRERA, the official one, is 30 December 2030, already 129 months later than the 31 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHANTI APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHANTI APARTMENT's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2021, giving the reason "DUE TO SOME TECHNICAL ISSUES AND SHORTAGE OF RAW MATERIALS."; to 31 December 2024, giving the reason "Due to Kovid 19, our work could not be completed within the given time. However, we request to get an extension of next 18 months to complete this work."; to 30 December 2030, giving the reason "Booking is veery slow. Building 2 completed and oc obtained. No further building construction start. we are going to correction in project Phase wise with concent of allotee.".
What is the RERA number of SHANTI APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHANTI APARTMENT in Vajira Naka, Ratnagiri is P52800005933.
Is SHANTI APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHANTI APARTMENT is registered as P52800005933 and its status is "Completed".
What is the construction status of SHANTI APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SHANTI APARTMENT's status on MahaRERA is "Completed". As filed by the builder, slab work on SHANTI APARTMENT BLDG-2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHANTI APARTMENT have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHANTI APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHANTI APARTMENT is registered on MahaRERA as P52800005933, its MahaRERA status is "Completed", its completion date has moved 129 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHANTI APARTMENT's possession date changes?
The latest dates are on SHANTI APARTMENT's MahaRERA page (P52800005933). GharKundli's Kundli Watch sends a free WhatsApp update on SHANTI APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHANTI APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHANTI APARTMENT has one building filed: SHANTI APARTMENT BLDG-2 with 5 floors and 40 units.
How much parking does SHANTI APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 4 covered car parking spaces for SHANTI APARTMENT.
How big is the land of SHANTI APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SHANTI APARTMENT stands on 3,300 sq m of land (about 0.8 acres), with 1,543 sq m of sanctioned built-up area and 330 sq m of recreational open space.
Where can I read reviews of SHANTI APARTMENT?
Google Maps has reviews of SHANTI APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHANTI APARTMENT?
SHANTI APARTMENT by KRUSHI NITYANAND PRIVATE LIMITED is in Vajira Naka, Ratnagiri (pincode 415606), Maharashtra, and is registered on MahaRERA as P52800005933, per GharKundli's check of MahaRERA records.
How many homes are in SHANTI APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SHANTI APARTMENT has 40 homes in 1 tower registered on MahaRERA, and 65% of them are sold or booked.
When was SHANTI APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHANTI APARTMENT was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHANTI APARTMENT?
No court cases are listed for SHANTI APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHANTI APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KRUSHI NITYANAND PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of SHANTI APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Chiplun
- SHARDA ENCLAVE
- RAMCHANDRA PARK ‘D’ WING’
- SONAL LAXMI VILLAGE
- EVERGREEN TOWER
- SHREE SAMARTH SANKUL PHASE-2
- APARANT PRIME
- CITY LANDMARK
- SWAPNASRUSHTI BLDG-2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.