SWAPNASRUSHTI BLDG-2

by SWAPNAPURTEE REALTY PVT LTD · Radhakrishna Nagar, Ratnagiri

Possession date of SWAPNASRUSHTI BLDG-2: 31 July 2027, moved from 30 December 2024 (27 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800019873, and currently active. Its completion date has moved from December 2024 to July 2027: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SWAPNASRUSHTI BLDG-2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SWAPNASRUSHTI BLDG-2 has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA20012619509)

    Reason the builder gave MahaRERA:
    “Initial permission was taken till 5th floor and date of completion was committed as 31.12.2024 on Rera portal. the said floors and possessions were delivered on 24-07.2024, i.e before the date of completion. in due course of time permission…” Read the full reason“Initial permission was taken till 5th floor and date of completion was committed as 31.12.2024 on Rera portal. the said floors and possessions were delivered on 24-07.2024, i.e before the date of completion. in due course of time permission was applied and granted for 6y=th and 7th floor. no sale was intended for the same floors until completion certificate is received. now the afore mentioned extention is requested to complete and sell the 6th and 7th floor.”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SWAPNASRUSHTI BLDG-2’s extension records on MahaRERA (P52800019873), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SWAPNASRUSHTI BLDG-2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800019873
Status
Registered and active
Builder
SWAPNAPURTEE REALTY PVT LTD
Location
Radhakrishna Nagar, Ratnagiri · 415605
Project type
Residential / Group Housing
Registered on
7 Mar 2019
Completion date at registration
December 2024
Latest completion date
July 2027
Delay so far
27 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
50
Sold or booked
88%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SWAPNASRUSHTI BLDG-2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SWAPNASRUSHTI BLDG 2100%100%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SWAPNASRUSHTI BLDG 2: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SWAPNASRUSHTI BLDG-2 every month.

SWAPNASRUSHTI BLDG-2: buildings, flats and land, as filed on MahaRERA

  • Buildings: SWAPNASRUSHTI BLDG 2 (6 floors, 50 units)
  • Land: 3,280 sq m (about 0.8 acres) · sanctioned built-up 3,868 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SWAPNASRUSHTI BLDG-2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SWAPNASRUSHTI BLDG-2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SWAPNASRUSHTI BLDG-2

What is the possession date of SWAPNASRUSHTI BLDG-2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SWAPNASRUSHTI BLDG-2 in Radhakrishna Nagar, Ratnagiri is 31 July 2027 — 27 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SWAPNASRUSHTI BLDG-2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SWAPNASRUSHTI BLDG-2's builder has filed on MahaRERA, the official one, is 31 July 2027, already 27 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SWAPNASRUSHTI BLDG-2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAPNASRUSHTI BLDG-2's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Initial permission was taken till 5th floor and date of completion was committed as 31.12.2024 on Rera portal. the said floors and possessions were delivered on 24-07.2024, i.e before the date of completion. in due course of time permission was applied and granted for 6y=th and 7th floor. no sale was intended for the same floors until completion certificate is received. now the afore mentioned extention is requested to complete and sell the 6th and 7th floor.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SWAPNASRUSHTI BLDG-2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SWAPNASRUSHTI BLDG-2 in Radhakrishna Nagar, Ratnagiri is P52800019873.

Is SWAPNASRUSHTI BLDG-2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAPNASRUSHTI BLDG-2 is registered as P52800019873 and its status is "Registered and active".

What is the construction status of SWAPNASRUSHTI BLDG-2?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAPNASRUSHTI BLDG-2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SWAPNASRUSHTI BLDG 2 is 100% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SWAPNASRUSHTI BLDG-2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SWAPNASRUSHTI BLDG-2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAPNASRUSHTI BLDG-2 is registered on MahaRERA as P52800019873, its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SWAPNASRUSHTI BLDG-2's possession date changes?

The latest dates are on SWAPNASRUSHTI BLDG-2's MahaRERA page (P52800019873). GharKundli's Kundli Watch sends a free WhatsApp update on SWAPNASRUSHTI BLDG-2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SWAPNASRUSHTI BLDG-2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAPNASRUSHTI BLDG-2 has one building filed: SWAPNASRUSHTI BLDG 2 with 6 floors and 50 units.

How big is the land of SWAPNASRUSHTI BLDG-2?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAPNASRUSHTI BLDG-2 stands on 3,280 sq m of land (about 0.8 acres), with 3,868 sq m of sanctioned built-up area.

Where can I read reviews of SWAPNASRUSHTI BLDG-2?

Google Maps has reviews of SWAPNASRUSHTI BLDG-2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SWAPNASRUSHTI BLDG-2?

SWAPNASRUSHTI BLDG-2 by SWAPNAPURTEE REALTY PVT LTD is in Radhakrishna Nagar, Ratnagiri (pincode 415605), Maharashtra, and is registered on MahaRERA as P52800019873, per GharKundli's check of MahaRERA records.

How many homes are in SWAPNASRUSHTI BLDG-2?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAPNASRUSHTI BLDG-2 has 50 homes in 1 tower registered on MahaRERA, and 88% of them are sold or booked.

When was SWAPNASRUSHTI BLDG-2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAPNASRUSHTI BLDG-2 was registered on MahaRERA on 7 March 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on SWAPNASRUSHTI BLDG-2?

No court cases are listed for SWAPNASRUSHTI BLDG-2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SWAPNASRUSHTI BLDG-2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SWAPNAPURTEE REALTY PVT LTD, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Ratnagiri →