by Jayant Yeshwant Kolhatkar · Deccan Gymkhana, RatnagiriAlso near Dapoli

Possession date of Green Park: 30 June 2023, moved from 30 June 2019 (48 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52800008479. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2023) has passed.

What do you want to know about Green Park?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Green Park has moved

  1. 30 June 2019

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT52800006338)

    Reason the builder gave MahaRERA: “Due to shortage of Sand and other material required for construction”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT52800010347)

    Reason the builder gave MahaRERA:
    “Due to uncertainties created by lockdown, facing labour shortage as well as raw material shortage. Faced two cyclones, Nisarga cyclone in 2020 and Taukte cyclone in 2021 due to which have faced damages and losses on site and also on the sit…” Read the full reason“Due to uncertainties created by lockdown, facing labour shortage as well as raw material shortage. Faced two cyclones, Nisarga cyclone in 2020 and Taukte cyclone in 2021 due to which have faced damages and losses on site and also on the sites of raw material providers.”
  4. 30 June 2023

    Revised completion date on MahaRERA

Source: Green Park’s extension records on MahaRERA (P52800008479), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Green Park

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800008479
Status
Lapsed (registration period ended)
Builder
Jayant Yeshwant Kolhatkar
Location
Deccan Gymkhana, Ratnagiri · 415712
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
June 2019
Latest completion date
June 2023
Delay so far
48 months
Homes
18
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Green Park, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
D and E wing100%35%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Green Park every month.

Green Park: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Green Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Green Park: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Green Park

What is the possession date of Green Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Green Park in Deccan Gymkhana, Ratnagiri is 30 June 2023 — 48 months later than 30 June 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Green Park?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Green Park's builder has filed on MahaRERA, the official one, is 30 June 2023, already 48 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Green Park extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Green Park's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2020, giving the reason "Due to shortage of Sand and other material required for construction"; to 31 December 2022, giving the reason "Due to uncertainties created by lockdown, facing labour shortage as well as raw material shortage. Faced two cyclones, Nisarga cyclone in 2020 and Taukte cyclone in 2021 due to which have faced damages and losses on site and also on the sites of raw material providers.".

What is the RERA number of Green Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Green Park in Deccan Gymkhana, Ratnagiri is P52800008479.

Is Green Park registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Green Park is registered as P52800008479 and its status is "Lapsed (registration period ended)".

What is the construction status of Green Park?

According to GharKundli's check of MahaRERA records (updated November 2026), Green Park's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on D and E wing is 35% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Green Park have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Green Park safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Green Park is registered on MahaRERA as P52800008479, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Green Park's possession date changes?

The latest dates are on Green Park's MahaRERA page (P52800008479). GharKundli's Kundli Watch sends a free WhatsApp update on Green Park every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Green Park have?

According to GharKundli's check of MahaRERA records (updated November 2026), Green Park has one building filed: D and E wing with 5 floors.

How big is the land of Green Park?

According to GharKundli's check of MahaRERA records (updated November 2026), Green Park stands on 1,022 sq m of land (about 0.3 acres), with 938 sq m of sanctioned built-up area.

Where can I read reviews of Green Park?

Google Maps has reviews of Green Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Green Park?

Green Park by Jayant Yeshwant Kolhatkar is in Deccan Gymkhana, Ratnagiri (pincode 415712), near Dapoli, Maharashtra, and is registered on MahaRERA as P52800008479, per GharKundli's check of MahaRERA records.

How many homes are in Green Park?

According to GharKundli's check of MahaRERA records (updated November 2026), Green Park has 18 homes in 1 tower registered on MahaRERA.

When was Green Park registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Green Park was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Green Park?

No court cases are listed for Green Park on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Green Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Jayant Yeshwant Kolhatkar, which has 1 other project registered on MahaRERA.