Skip to content
GharKundli

Mangal Kalash

by M/s Mangal Developers · Jogale, Ratnagiri

Possession: Mangal Kalash is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800032039. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Mangal Kalash?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Mangal Kalash has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT52800016818)

    Reason the builder gave MahaRERA: “The project has been delayed on account of non availability of labour and more of unweather rainfall in the costal area of Ratnagiri district.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT52800024995)

    Reason the builder gave MahaRERA: “We, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52800032039 up to 31/12/2024.”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EA31072502258)

    Reason the builder gave MahaRERA:
    “We hereby request an extension of the project timeline under RERA due to unforeseen delays caused by a shortage of both skilled labour and essential construction materials. Over the past few months, our project has faced significant disrupt…” Read the full reason“We hereby request an extension of the project timeline under RERA due to unforeseen delays caused by a shortage of both skilled labour and essential construction materials. Over the past few months, our project has faced significant disruptions in workforce availability, which has slowed down on-site progress of the building. Additionally, the supply chain for critical raw materials such as cement and steel has been inconsistent, leading to delays in procurement and execution of key construction activities.”
  5. 15 April 2026

    Extended at the builder's request (MahaRERA application EA19062621441)

    Reason the builder gave MahaRERA: “I/We hereby declare that the Occupancy Certificate (OC) for the above-mentioned project has been duly obtained vide Approval No. NPDPO/FO/2026/APL/00022, the same is attached in the extension application.”

Source: Mangal Kalash’s extension records on MahaRERA (P52800032039), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mangal Kalash

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800032039
Status
Completed
Builder
M/s Mangal Developers
Location
Jogale, Ratnagiri · 415712
Project type
Residential / Group Housing
Registered on
3 Dec 2021
Completion date at registration
June 2023
Latest completion date
April 2026
Delay so far
34 months
Homes
23
Sold or booked
74%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Mangal Kalash, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Mangal Kalash100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • Mangal Kalash: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mangal Kalash every month.

Mangal Kalash: buildings, flats and land, as filed on MahaRERA

  • Buildings: Mangal Kalash (7 floors, 23 units)
  • Car parking: 6 covered
  • Land: 527 sq m (about 0.1 acres) · sanctioned built-up 1,230 sq m
  • Boundaries filed include: Dapoli Kolbandre Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Mangal Kalash →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mangal Kalash: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Mangal Kalash

What is the possession date of Mangal Kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mangal Kalash in Jogale, Ratnagiri is 15 April 2026 — 34 months later than 30 June 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Mangal Kalash?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mangal Kalash's builder has filed on MahaRERA, the official one, is 15 April 2026, already 34 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mangal Kalash extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Kalash's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2024, giving the reason "The project has been delayed on account of non availability of labour and more of unweather rainfall in the costal area of Ratnagiri district."; to 30 June 2025, giving the reason "We, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52800032039 up to 31/12/2024."; to 31 December 2025, giving the reason "We hereby request an extension of the project timeline under RERA due to unforeseen delays caused by a shortage of both skilled labour and essential construction materials. Over the past few months, our project has faced significant disruptions in workforce availability, which has slowed down on-site progress of the building. Additionally, the supply chain for critical raw materials such as cement and steel has been inconsistent, leading to delays in procurement and execution of key construction activities."; to 15 April 2026, giving the reason "I/We hereby declare that the Occupancy Certificate (OC) for the above-mentioned project has been duly obtained vide Approval No. NPDPO/FO/2026/APL/00022, the same is attached in the extension application.".

What is the RERA number of Mangal Kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mangal Kalash in Jogale, Ratnagiri is P52800032039.

Is Mangal Kalash registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Kalash is registered as P52800032039 and its status is "Completed".

What is the construction status of Mangal Kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Kalash's status on MahaRERA is "Completed". As filed by the builder, slab work on Mangal Kalash is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Mangal Kalash have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Mangal Kalash safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Kalash is registered on MahaRERA as P52800032039, its MahaRERA status is "Completed", its completion date has moved 34 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Mangal Kalash's possession date changes?

The latest dates are on Mangal Kalash's MahaRERA page (P52800032039). GharKundli's Kundli Watch sends a free WhatsApp update on Mangal Kalash every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mangal Kalash have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Kalash has one building filed: Mangal Kalash with 7 floors and 23 units.

How much parking does Mangal Kalash have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered car parking spaces for Mangal Kalash.

How big is the land of Mangal Kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Kalash stands on 527 sq m of land (about 0.1 acres), with 1,230 sq m of sanctioned built-up area.

Where can I read reviews of Mangal Kalash?

Google Maps has reviews of Mangal Kalash written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Mangal Kalash?

Mangal Kalash by M/s Mangal Developers is in Jogale, Ratnagiri (pincode 415712), Maharashtra, and is registered on MahaRERA as P52800032039, per GharKundli's check of MahaRERA records. Its boundaries filed there include Dapoli Kolbandre Road.

How many homes are in Mangal Kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Kalash has 23 homes in 1 tower registered on MahaRERA, and 74% of them are sold or booked.

When was Mangal Kalash registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Kalash was registered on MahaRERA on 3 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Mangal Kalash?

No court cases are listed for Mangal Kalash on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Mangal Kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s Mangal Developers.

Other projects in Dapoli

All 77 projects in Dapoli (415712) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.