SAI SADAN

by ADITH BUILDERS AND DEVELOPERS · Camp Dapoli, Ratnagiri

Possession date of SAI SADAN: 31 May 2028, moved from 31 January 2026 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800077065, and currently active. Its completion date has moved from January 2026 to May 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAI SADAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI SADAN has moved

  1. 31 January 2026

    Completion date given when the project was registered

  2. 31 January 2028

    Extended at the builder's request (MahaRERA application EA27022620039)

    Reason the builder gave MahaRERA: “The project extension is sought due to shortages of skilled and unskilled labour and contractor resources, along with supply chain disruptions between May and December that delayed construction progress.”
  3. 31 May 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAI SADAN’s extension records on MahaRERA (P52800077065), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI SADAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800077065
Status
Registered and active
Builder
ADITH BUILDERS AND DEVELOPERS
Location
Camp Dapoli, Ratnagiri · 415712
Project type
Residential / Group Housing
Registered on
23 Jul 2024
Completion date at registration
January 2026
Latest completion date
May 2028
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
42
Sold or booked
35%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SAI SADAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI SADAN100%83%37%0%

Commencement certificate (CC), as filed on MahaRERA

  • SAI SADAN: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI SADAN every month.

SAI SADAN: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI SADAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI SADAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI SADAN

What is the possession date of SAI SADAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI SADAN in Camp Dapoli, Ratnagiri is 31 May 2028 — 24 months later than 31 January 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAI SADAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI SADAN's builder has filed on MahaRERA, the official one, is 31 May 2028, already 24 months later than the 31 January 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI SADAN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI SADAN's builder applied to MahaRERA to extend the completion date once: to 31 January 2028, giving the reason "The project extension is sought due to shortages of skilled and unskilled labour and contractor resources, along with supply chain disruptions between May and December that delayed construction progress.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SAI SADAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI SADAN in Camp Dapoli, Ratnagiri is P52800077065.

Is SAI SADAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI SADAN is registered as P52800077065 and its status is "Registered and active".

What is the construction status of SAI SADAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI SADAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI SADAN is 83% done and internal work 37%. GharKundli's full report compares construction progress with the deadline.

Does SAI SADAN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SAI SADAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI SADAN is registered on MahaRERA as P52800077065, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI SADAN's possession date changes?

The latest dates are on SAI SADAN's MahaRERA page (P52800077065). GharKundli's Kundli Watch sends a free WhatsApp update on SAI SADAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI SADAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI SADAN has one building filed: SAI SADAN with 8 floors and 42 units.

How much parking does SAI SADAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 7 covered car parking spaces for SAI SADAN.

How big is the land of SAI SADAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI SADAN stands on 1,015 sq m of land (about 0.3 acres), with 2,466 sq m of sanctioned built-up area.

Where can I read reviews of SAI SADAN?

Google Maps has reviews of SAI SADAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI SADAN?

SAI SADAN by ADITH BUILDERS AND DEVELOPERS is in Camp Dapoli, Ratnagiri (pincode 415712), Maharashtra, and is registered on MahaRERA as P52800077065, per GharKundli's check of MahaRERA records.

How many homes are in SAI SADAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI SADAN has 42 homes in 1 tower registered on MahaRERA, and 35% of them are sold or booked.

When was SAI SADAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI SADAN was registered on MahaRERA on 23 July 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI SADAN?

No court cases are listed for SAI SADAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAI SADAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITH BUILDERS AND DEVELOPERS.

All projects with possession due in 2028 in Ratnagiri →

Other projects in pincode 415712

All 77 projects in Dapoli (415712) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.