Skip to content
GharKundli

Mangal Mahalaxmi

by Mangal Builders · Mahalaxmi Che Maal, Ratnagiri

Possession date of Mangal Mahalaxmi: 30 April 2027, moved from 28 November 2021 (61 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800014983, and currently active. Its completion date has moved from November 2021 to April 2027: 61 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Mangal Mahalaxmi?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Mangal Mahalaxmi has moved

  1. 28 November 2021

    Completion date given when the project was registered

  2. 28 November 2022

    Extended at the builder's request (MahaRERA application EXT52800011066)

    Reason the builder gave MahaRERA:
    “The project has been delayed on account of first wave of Covid -19, which started from second half of March 2020 and lasted till December 2020 i.e 9 months. During this period cyclone “Nisarga’ also impacted the project. The activities came…” Read the full reason“The project has been delayed on account of first wave of Covid -19, which started from second half of March 2020 and lasted till December 2020 i.e 9 months. During this period cyclone “Nisarga’ also impacted the project. The activities came to total standstill during this period. Further it was very difficult to get the labourers thereafter as most of the labourers from other states migrated and they started coming back only in the month of January and February 2021. During the month of April 2021, as the second wave of Covid-19 causalities increased, the lockdown was imposed in Maharashtra…”
  3. 28 November 2023

    Extended at the builder's request (MahaRERA application EXT52800012914)

    Reason the builder gave MahaRERA:
    “The project site is located at Dapoli , District Ratnagiri. The area is prone to heavy rainfall. The construction was disturbed due to heavy rains. The commencement of construction activity was further delayed due to shortage of electricity…” Read the full reason“The project site is located at Dapoli , District Ratnagiri. The area is prone to heavy rainfall. The construction was disturbed due to heavy rains. The commencement of construction activity was further delayed due to shortage of electricity, impacted movement of material and labour. The project comprise of five buildings A, B , CD, E and F. We have completed the construction of buildings CD and F and A , B and E are in progress.”
  4. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT52800018471)

    Reason the builder gave MahaRERA:
    “The Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into susp…” Read the full reason“The Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into suspension of construction activities. Further project was suspended during the period May & June 2021 due to cyclone “Tauktae”.”
  5. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT52800024320)

    Reason the builder gave MahaRERA:
    “The Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into susp…” Read the full reason“The Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into suspension of construction activities. Further project was suspended during the period May & June 2021 due to cyclone “Tauktae”. Due to unavailability of required material & labour project completion is getting delayed. However as on date 90% project is completed. Project is almost 90% is completed as per Architect certificates.”
  6. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT52800027795)

    Reason the builder gave MahaRERA: “We, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52800014983 up to 30/12/2025.”
  7. 31 December 2026

    Extended at the builder's request (MahaRERA application EA18022619891)

    Reason the builder gave MahaRERA:
    “We have obtained Occupancy Certificate dated 05/06/2025 for the Following Buildings – Building A, Building C and D, Building F. The above-mentioned buildings are complete in all aspects with respect to construction and development works. Th…” Read the full reason“We have obtained Occupancy Certificate dated 05/06/2025 for the Following Buildings – Building A, Building C and D, Building F. The above-mentioned buildings are complete in all aspects with respect to construction and development works. The Project has been affected by the shortage of skilled labour force due to the recent festive seasons. Shortage of raw material has also resulted into the delay of the construction in view of the latest sanctioned plans received for Building B and Building E upto the Parking + 6 Floors”
  8. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Mangal Mahalaxmi’s extension records on MahaRERA (P52800014983), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mangal Mahalaxmi

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800014983
Status
Registered and active
Builder
Mangal Builders
Location
Mahalaxmi Che Maal, Ratnagiri · 415712
Project type
Others
Registered on
15 Jan 2018
Completion date at registration
November 2021
Latest completion date
April 2027
Delay so far
61 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
121
Sold or booked
62%
Towers
5
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Mangal Mahalaxmi, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building A100%5%100%1000%
Building B100%9%80%70%
Building C and D100%4%100%100%
Building E100%7%80%80%
Building F100%4%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Building A: covers 5 floors
  • Building B: covers 7 floors
  • Building C and D: covers 4 floors
  • Building E: covers 7 floors
  • Building F: covers 4 floors

Latest CC order on MahaRERA: dated 06/05/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mangal Mahalaxmi every month.

Mangal Mahalaxmi: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building A (5 floors, 16 units) · Building B (7 floors, 42 units) · Building C and D (4 floors, 33 units) · Building E (7 floors, 24 units) · Building F (4 floors, 15 units)
  • Car parking: 14 covered
  • Land: 3,600 sq m (about 0.9 acres) · sanctioned built-up 5,982 sq m · recreational space 339 sq m
  • Boundaries filed include: Dapoli To Kolbandre Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Mangal Mahalaxmi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mangal Mahalaxmi: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Mangal Mahalaxmi

What is the possession date of Mangal Mahalaxmi?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mangal Mahalaxmi in Mahalaxmi Che Maal, Ratnagiri is 30 April 2027 — 61 months later than 28 November 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Mangal Mahalaxmi?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mangal Mahalaxmi's builder has filed on MahaRERA, the official one, is 30 April 2027, already 61 months later than the 28 November 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mangal Mahalaxmi extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Mahalaxmi's builder applied to MahaRERA to extend the completion date 6 times: to 28 November 2022, giving the reason "The project has been delayed on account of first wave of Covid -19, which started from second half of March 2020 and lasted till December 2020 i.e 9 months. During this period cyclone “Nisarga’ also impacted the project. The activities came to total standstill during this period. Further it was very difficult to get the labourers thereafter as most of the labourers from other states migrated and they started coming back only in the month of January and February 2021. During the month of April 2021, as the second wave of Covid-19 causalities increased, the lockdown was imposed in Maharashtra…"; to 28 November 2023, giving the reason "The project site is located at Dapoli , District Ratnagiri. The area is prone to heavy rainfall. The construction was disturbed due to heavy rains. The commencement of construction activity was further delayed due to shortage of electricity, impacted movement of material and labour. The project comprise of five buildings A, B , CD, E and F. We have completed the construction of buildings CD and F and A , B and E are in progress."; to 30 June 2024, giving the reason "The Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into suspension of construction activities. Further project was suspended during the period May & June 2021 due to cyclone “Tauktae”."; to 30 December 2024, giving the reason "The Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into suspension of construction activities. Further project was suspended during the period May & June 2021 due to cyclone “Tauktae”. Due to unavailability of required material & labour project completion is getting delayed. However as on date 90% project is completed. Project is almost 90% is completed as per Architect certificates."; to 30 December 2025, giving the reason "We, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52800014983 up to 30/12/2025."; to 31 December 2026, giving the reason "We have obtained Occupancy Certificate dated 05/06/2025 for the Following Buildings – Building A, Building C and D, Building F. The above-mentioned buildings are complete in all aspects with respect to construction and development works. The Project has been affected by the shortage of skilled labour force due to the recent festive seasons. Shortage of raw material has also resulted into the delay of the construction in view of the latest sanctioned plans received for Building B and Building E upto the Parking + 6 Floors". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Mangal Mahalaxmi?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mangal Mahalaxmi in Mahalaxmi Che Maal, Ratnagiri is P52800014983.

Is Mangal Mahalaxmi registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Mahalaxmi is registered as P52800014983 and its status is "Registered and active".

What is the construction status of Mangal Mahalaxmi?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Mahalaxmi's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 4% to 9% across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does Mangal Mahalaxmi have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Mangal Mahalaxmi safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Mahalaxmi is registered on MahaRERA as P52800014983, its completion date has moved 61 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Mangal Mahalaxmi's possession date changes?

The latest dates are on Mangal Mahalaxmi's MahaRERA page (P52800014983). GharKundli's Kundli Watch sends a free WhatsApp update on Mangal Mahalaxmi every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mangal Mahalaxmi have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Mahalaxmi has 5 buildings filed: Building A with 5 floors and 16 units; Building B with 7 floors and 42 units; Building C and D with 4 floors and 33 units; Building E with 7 floors and 24 units; Building F with 4 floors and 15 units.

How much parking does Mangal Mahalaxmi have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 14 covered car parking spaces for Mangal Mahalaxmi.

How big is the land of Mangal Mahalaxmi?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Mahalaxmi stands on 3,600 sq m of land (about 0.9 acres), with 5,982 sq m of sanctioned built-up area and 339 sq m of recreational open space.

Where can I read reviews of Mangal Mahalaxmi?

Google Maps has reviews of Mangal Mahalaxmi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Mangal Mahalaxmi?

Mangal Mahalaxmi by Mangal Builders is in Mahalaxmi Che Maal, Ratnagiri (pincode 415712), Maharashtra, and is registered on MahaRERA as P52800014983, per GharKundli's check of MahaRERA records. Its boundaries filed there include Dapoli To Kolbandre Road.

How many homes are in Mangal Mahalaxmi?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Mahalaxmi has 121 homes in 5 towers registered on MahaRERA, and 62% of them are sold or booked.

When was Mangal Mahalaxmi registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Mahalaxmi was registered on MahaRERA on 15 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Mangal Mahalaxmi?

No court cases are listed for Mangal Mahalaxmi on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Mangal Mahalaxmi?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mangal Builders.

All projects with possession due in 2027 in Ratnagiri →

Other projects in Dapoli

All 77 projects in Dapoli (415712) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.